ODOT contract 250536 bid tabulation
VIN-SR 93-07.20 (MINOR RECONSTRUCTION). Let by Ohio DOT on November 13, 2025, VIN. 4 bids received; low bid $1,487,696 by Fillmore Construction, -0.9% against the engineer's estimate of $1,501,000.
- Owner
- Ohio DOT
- Letting
- 13 NOV 2025
- Pay items
- 65
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Fillmore Construction | $1,487,696 | Low | -1.0% |
| 2 | Shelly & Sands Inc | $1,680,336 | +13% | +12% |
| 3 | Axis Civil Construction LLC | $1,787,361 | +20% | +19% |
| 4 | Allard Excavation LLC | $1,878,513 | +26% | +25% |
Engineer's estimate: $1,501,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Fillmore Construction | 2. Shelly & Sands Inc | 3. Axis Civil Construction LLC | 4. Allard Excavation LLC |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $25,000 | $5,000.00 | $20,000 | $17,000 |
| 2 | Headwall removed (202E20010) | EACH | 2 | $500.00 | $800.00 | $1,300.00 | $1,681.00 |
| 3 | Pavement removed (202E23000) | SY | 361 | $20.00 | $14.50 | $22.00 | $11.00 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 817 | $20.00 | $24.00 | $30.00 | $13.00 |
| 5 | Guardrail removed (202E38000) | FT | 137.50 | $10.00 | $5.00 | $10.00 | $3.00 |
| 6 | Catch basin or inlet removed (202E58300) | EACH | 2 | $250.00 | $800.00 | $1,350.00 | $418.00 |
| 7 | Excavation (203E10000) | CY | 2,312 | $50.00 | $24.00 | $28.00 | $24.00 |
| 8 | Embankment (203E20000) | CY | 884 | $30.00 | $35.00 | $28.00 | $42.00 |
| 9 | Subgrade compaction (204E10000) | SY | 1,850 | $3.00 | $4.00 | $3.30 | $9.00 |
| 10 | Guardrail, type MGS with long posts (606E15100) | FT | 150 | $30.00 | $30.00 | $30.00 | $34.26 |
| 11 | Anchor assembly, type E (606E26100) | EACH | 1 | $2,750.00 | $2,750.00 | $2,750.00 | $2,340.00 |
| 12 | Anchor assembly, type T (606E26500) | EACH | 1 | $1,100.00 | $1,100.00 | $1,100.00 | $1,190.00 |
| 13 | Special - mailbox removed and reset (690E50350) | EACH | 17 | $300.00 | $150.00 | $245.00 | $182.00 |
| 14 | Rock channel protection, type B with filter (601E32100) | CY | 27 | $180.00 | $125.00 | $140.00 | $101.00 |
| 15 | Rock channel protection, type C with filter (601E32200) | CY | 16 | $140.00 | $180.00 | $195.00 | $133.00 |
| 16 | Soil analysis test (659E00100) | EACH | 2 | $300.00 | $135.00 | $150.00 | $150.00 |
| 17 | Topsoil (659E00300) | CY | 95 | $60.00 | $65.00 | $90.00 | $34.00 |
| 18 | Seeding and mulching (659E10000) | SY | 9,985 | $1.45 | $0.88 | $0.80 | $0.80 |
| 19 | Repair seeding and mulching (659E14000) | SY | 499 | $2.20 | $0.80 | $0.80 | $0.80 |
| 20 | Inter-seeding (659E15000) | SY | 499 | $2.20 | $0.80 | $0.80 | $0.80 |
| 21 | Commercial fertilizer (659E20000) | TON | 1.39 | $1,400.00 | $885.00 | $1,250.00 | $1,250.00 |
| 22 | Lime (659E31000) | ACRE | 2.06 | $450.00 | $160.00 | $150.00 | $150.00 |
| 23 | Water (659E35000) | MGAL | 55 | $100.00 | $1.00 | $1.00 | $1.00 |
| 24 | Mowing (659E40000) | MSF | 22 | $100.00 | $25.00 | $50.00 | $50.00 |
| 25 | Ditch erosion protection (670E00700) | SY | 1,699 | $2.00 | $1.35 | $2.50 | $2.50 |
| 26 | Storm water pollution prevention plan (832E15000) | LS | 1 | $5,000.00 | $2,800.00 | $3,000.00 | $3,000.00 |
| 27 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $5,000.00 | $4,280.00 | $6,750.00 | $11,750 |
| 28 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $7,500.00 | $11,054 | $13,500 | $11,100 |
| 29 | Erosion control (832E30000) | EACH | 18,750 | $1.00 | $1.00 | $1.00 | $1.00 |
| 30 | Concrete masonry (602E20000) | CY | 39 | $1,500.00 | $1,750.00 | $2,510.00 | $2,436.00 |
| 31 | 12" conduit, type B (611E04400) | FT | 89 | $80.00 | $80.00 | $75.00 | $103.00 |
| 32 | 12" conduit, type D (611E04900) | FT | 65 | $60.00 | $85.00 | $115.00 | $125.00 |
| 33 | 15" conduit, type D (611E06400) | FT | 50 | $135.00 | $250.00 | $310.00 | $336.00 |
| 34 | 24" conduit, type A (611E10200) | FT | 88 | $120.00 | $165.00 | $160.00 | $138.00 |
| 35 | 24" conduit, type B (611E10400) | FT | 63 | $140.00 | $160.00 | $225.00 | $224.00 |
| 36 | 24" conduit, type D (611E10900) | FT | 150 | $170.00 | $320.00 | $450.00 | $514.00 |
| 37 | 27" conduit, type D (611E12400) | FT | 35 | $210.00 | $650.00 | $550.00 | $615.00 |
| 38 | 30" conduit, type A (611E13200) | FT | 124 | $160.00 | $215.00 | $240.00 | $221.00 |
| 39 | 30" conduit, type D (611E13900) | FT | 195 | $210.00 | $650.00 | $560.00 | $605.00 |
| 40 | 36" conduit, type B (611E16400) | FT | 72 | $200.00 | $250.00 | $310.00 | $335.00 |
| 41 | 42" conduit, type A (611E19200) | FT | 68 | $180.00 | $315.00 | $265.00 | $300.00 |
| 42 | 48" conduit, type A (611E20700) | FT | 68 | $200.00 | $415.00 | $400.00 | $542.00 |
| 43 | Catch basin, no. 2-2B (611E98470) | EACH | 1 | $3,000.00 | $3,750.00 | $4,000.00 | $3,939.00 |
| 44 | Catch basin, no. 2-3 (611E98510) | EACH | 1 | $4,000.00 | $4,000.00 | $4,400.00 | $4,008.00 |
| 45 | Catch basin, no. 2-4 (611E98540) | EACH | 1 | $5,000.00 | $6,000.00 | $7,200.00 | $5,510.00 |
| 46 | Asphalt concrete base, PG64-22, (449) (302E56000) | CY | 2,900 | $182.00 | $195.00 | $198.00 | $215.00 |
| 47 | Aggregate base (304E20000) | CY | 787 | $80.00 | $110.00 | $145.00 | $117.00 |
| 48 | Tack coat (407E10000) | GAL | 1,710 | $3.50 | $3.50 | $2.50 | $2.50 |
| 49 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 382 | $218.00 | $236.50 | $240.00 | $247.00 |
| 50 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 445 | $204.00 | $215.00 | $230.00 | $239.00 |
| 51 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 72 | $250.00 | $600.00 | $315.00 | $485.00 |
| 52 | Asphalt concrete intermediate course, type 2, (449), (driveways) (441E70700) | CY | 43 | $240.00 | $550.00 | $290.00 | $405.00 |
| 53 | 6" non-reinforced concrete pavement, class QC 1P (452E10010) | SY | 232 | $60.00 | $70.00 | $128.00 | $107.00 |
| 54 | Fire hydrant removed and reset (638E10500) | EACH | 1 | $5,000.00 | $3,100.00 | $6,500.00 | $5,505.00 |
| 55 | Ground mounted support, no. 3 post (630E03100) | FT | 25 | $45.00 | $25.00 | $25.00 | $45.00 |
| 56 | Sign, flat sheet (630E80100) | SF | 11 | $95.00 | $25.00 | $25.00 | $95.00 |
| 57 | Removal of ground mounted sign and disposal (630E84900) | EACH | 2 | $325.00 | $25.00 | $25.00 | $36.00 |
| 58 | Removal of ground mounted post support and disposal (630E86002) | EACH | 2 | $325.00 | $25.00 | $25.00 | $36.00 |
| 59 | Edge line, 6" (646E10010) | MI | 0.98 | $8,831.00 | $3,300.00 | $7,400.00 | $8,028.00 |
| 60 | Center line (646E10200) | MI | 0.47 | $8,831.00 | $3,300.00 | $7,400.00 | $8,028.00 |
| 61 | Detour signing (614E12420) | LS | 1 | $8,800.00 | $8,800.00 | $8,800.00 | $8,800.00 |
| 62 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $15,000 | $8,858.18 | $15,000 | $14,000 |
| 63 | Maintaining traffic (614E11000) | LS | 1 | $47,700 | $30,000 | $28,000 | $15,000 |
| 64 | Construction layout stakes and surveying (623E10000) | LS | 1 | $7,500.00 | $31,000 | $20,000 | $27,890 |
| 65 | Mobilization (624E10000) | LS | 1 | $40,000 | $40,000 | $40,000 | $75,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of November 13, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.