ODOT contract 250549 bid tabulation
COL-US 30-34.73 (BRIDGE REPAIR). Let by Ohio DOT on December 4, 2025, COL. 4 bids received; low bid $318,689 by BCC Ohio Inc, +13% against the engineer's estimate of $283,000.
- Owner
- Ohio DOT
- Letting
- 04 DEC 2025
- Pay items
- 41
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | BCC Ohio Inc | $318,689 | Low | +13% |
| 2 | Apbn Inc | $459,029 | +44% | +62% |
| 3 | Madex Construction Co | $497,994 | +56% | +76% |
| 4 | Suburban Maintenance & Construction Inc | $547,623 | +72% | +94% |
Engineer's estimate: $283,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. BCC Ohio Inc | 2. Apbn Inc | 3. Madex Construction Co | 4. Suburban Maintenance & Construction Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $7,740.00 | $30,000 | $39,596 | $85,000 |
| 2 | Soil analysis test (659E00100) | EACH | 2 | $204.00 | $50.00 | $89.47 | $250.00 |
| 3 | Topsoil (659E00300) | CY | 500 | $64.80 | $30.00 | $59.47 | $70.00 |
| 4 | Seeding and mulching (659E10000) | SY | 4,500 | $2.57 | $2.45 | $4.63 | $2.57 |
| 5 | Repair seeding and mulching (659E14000) | SY | 225 | $1.94 | $2.85 | $2.32 | $1.85 |
| 6 | Commercial fertilizer (659E20000) | TON | 0.61 | $509.25 | $485.00 | $1,157.89 | $485.00 |
| 7 | Lime (659E31000) | ACRE | 0.93 | $31.51 | $30.00 | $568.42 | $30.00 |
| 8 | Water (659E35000) | MGAL | 25 | $0.21 | $0.20 | $8.95 | $0.20 |
| 9 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 10 | Ground mounted support, no. 3 post (630E03100) | FT | 30.90 | $26.25 | $25.00 | $28.95 | $26.25 |
| 11 | Ground mounted structural beam support, W8X18 (630E07000) | FT | 91.70 | $78.75 | $75.00 | $92.63 | $78.75 |
| 12 | Breakaway structural beam connection (630E09000) | EACH | 4 | $771.75 | $735.00 | $868.42 | $800.00 |
| 13 | Sign support assembly, pole mounted (630E79500) | EACH | 1 | $236.25 | $225.00 | $289.47 | $250.00 |
| 14 | Sign, flat sheet (630E80100) | SF | 22.70 | $21.00 | $20.00 | $28.95 | $22.00 |
| 15 | Sign, ground mounted extrusheet (630E80200) | SF | 289 | $30.45 | $29.00 | $37.05 | $31.00 |
| 16 | Ground mounted structural beam support foundation (630E84500) | EACH | 4 | $1,596.00 | $1,520.00 | $1,794.74 | $1,650.00 |
| 17 | Removal of ground mounted sign and disposal (630E84900) | EACH | 1 | $21.00 | $20.00 | $28.95 | $22.00 |
| 18 | Removal of ground mounted post support and disposal (630E86002) | EACH | 1 | $26.25 | $25.00 | $34.74 | $25.00 |
| 19 | Removal of structure mounted sign and disposal (630E86310) | EACH | 1 | $551.25 | $2,000.00 | $636.84 | $550.00 |
| 20 | Removal of structure mounted sign and disposal, as per plan (630E86311) | EACH | 2 | $4,803.75 | $5,000.00 | $5,326.32 | $5,500.00 |
| 21 | Lane line, 4" (646E10100) | MI | 0.04 | $2,404.50 | $2,290.00 | $31,842 | $7,500.00 |
| 22 | Center line (646E10200) | MI | 0.05 | $11,918 | $11,350 | $34,737 | $4,500.00 |
| 23 | Channelizing line, 8" (646E10300) | FT | 340 | $2.89 | $2.75 | $4.05 | $9.00 |
| 24 | Lane arrow (646E20300) | EACH | 12 | $367.50 | $350.00 | $405.26 | $115.00 |
| 25 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 50 | $90.30 | $40.00 | $115.79 | $90.00 |
| 26 | Asphalt concrete for maintaining traffic (614E13000) | CY | 10 | $525.00 | $100.00 | $168.42 | $300.00 |
| 27 | Removal misc.: oepa notification of demolition (202E98100) | EACH | 1 | $129.00 | $9,000.00 | $2,894.74 | $1,500.00 |
| 28 | Removal misc.: portions of approach slab removed (202E98200) | FT | 8 | $322.50 | $1,000.00 | $1,397.36 | $500.00 |
| 29 | Sealing concrete bridge decks with HMWM resin (512E10300) | SY | 1,283 | $17.93 | $20.00 | $35.00 | $32.00 |
| 30 | Removal of existing pavement marking (512E74500) | FT | 240 | $1.94 | $6.70 | $1.79 | $12.00 |
| 31 | Removal of existing pavement marking (512E74520) | EACH | 5 | $193.50 | $1,000.00 | $163.16 | $200.00 |
| 32 | Field painting of damaged structural steel, as per plan (514E20001) | SF | 144 | $233.17 | $690.00 | $160.26 | $125.00 |
| 33 | Approach slabs, misc.: curb repair (526E98200) | FT | 8 | $406.88 | $600.00 | $1,718.89 | $500.00 |
| 34 | Vandal protection fence, 12' curved, coated fabric, as per plan (607E39931) | FT | 322 | $249.38 | $238.00 | $289.47 | $517.00 |
| 35 | Structure grounding system (625E33000) | EACH | 1 | $10,578 | $15,000 | $34,421 | $6,800.00 |
| 36 | Patching concrete structures with trowelable mortar (843E50000) | SF | 3 | $232.50 | $500.00 | $578.95 | $500.00 |
| 37 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $3,781.39 | $7,800.00 | $19,534 | $10,000 |
| 38 | Maintaining traffic, as per plan (614E11001) | LS | 1 | $17,879 | $72,501 | $29,872 | $65,000 |
| 39 | Field office, type A (619E16000) | MNTH | 7 | $2,066.14 | $500.00 | $736.84 | $2,500.00 |
| 40 | Construction layout stakes and surveying (623E10000) | LS | 1 | $2,760.00 | $4,000.00 | $7,989.47 | $2,500.00 |
| 41 | Mobilization (624E10000) | LS | 1 | $17,284 | $20,000 | $55,923 | $20,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of December 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.