ODOT contract 260127 bid tabulation
MAD-US 42-07.14,MAD-SR 38-12.40/31.74 (TWO LANE RESURFACING). Let by Ohio DOT on March 12, 2026, MAD. 5 bids received; low bid $1,276,732 by Fillmore Construction, -17% against the engineer's estimate of $1,540,000.
- Owner
- Ohio DOT
- Letting
- 12 MAR 2026
- Pay items
- 58
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Fillmore Construction | $1,276,732 | Low | -17% |
| 2 | Kokosing Construction Company Inc | $1,424,055 | +12% | -8.0% |
| 3 | Shelly & Sands Inc | $1,476,665 | +16% | -4.0% |
| 4 | A & B Asphalt Corporation | $1,517,034 | +19% | -1.0% |
| 5 | Shelly Company | $1,519,791 | +19% | -1.0% |
Engineer's estimate: $1,540,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Fillmore Construction | 2. Kokosing Construction Company Inc | 3. Shelly & Sands Inc | 4. A & B Asphalt Corporation | 5. Shelly Company |
|---|---|---|---|---|---|---|---|---|
| 1 | Walk removed, as per plan (202E30001) | SF | 64 | $10.00 | $30.00 | $12.00 | $5.94 | $30.00 |
| 2 | 4" concrete walk, as per plan (608E10001) | SF | 60 | $20.00 | $21.00 | $45.00 | $11.28 | $45.00 |
| 3 | Curb ramp (608E52000) | SF | 75 | $30.00 | $35.00 | $110.00 | $22.92 | $70.00 |
| 4 | Topsoil (659E00300) | CY | 66 | $50.00 | $75.00 | $75.00 | $250.00 | $110.00 |
| 5 | Seeding and mulching (659E10000) | SY | 600 | $4.25 | $9.00 | $6.45 | $5.00 | $6.00 |
| 6 | Commercial fertilizer (659E20000) | TON | 0.08 | $1,400.00 | $1,680.00 | $500.00 | $1,500.00 | $750.00 |
| 7 | Lime (659E31000) | ACRE | 0.12 | $450.00 | $800.00 | $20.00 | $200.00 | $800.00 |
| 8 | Water (659E35000) | MGAL | 4 | $10.00 | $50.00 | $2.00 | $1.00 | $100.00 |
| 9 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 10 | Aggregate drains (605E31100) | FT | 30 | $50.00 | $24.00 | $30.00 | $86.34 | $45.00 |
| 11 | Catch basin adjusted to grade (611E98630) | EACH | 4 | $1,500.00 | $825.00 | $900.00 | $4,166.20 | $1,750.00 |
| 12 | Manhole adjusted to grade (611E99654) | EACH | 4 | $1,000.00 | $825.00 | $875.00 | $2,756.67 | $1,750.00 |
| 13 | Partial depth pavement repair (asphalt concrete base) (251E01040) | SY | 4,935 | $44.00 | $41.00 | $50.00 | $52.27 | $43.00 |
| 14 | Partial depth pavement repair (asphalt concrete base) (251E01040) | SY | 1,542 | $52.00 | $63.00 | $60.00 | $58.07 | $56.00 |
| 15 | Pavement repair, as per plan (253E01001) | SY | 70 | $100.00 | $402.00 | $225.00 | $157.90 | $190.00 |
| 16 | Pavement planing, asphalt concrete, 1.5" (254E01000) | SY | 58,310 | $2.00 | $3.25 | $2.60 | $2.70 | $3.10 |
| 17 | Non-tracking tack coat (407E20000) | GAL | 4,959 | $3.00 | $2.65 | $3.50 | $4.01 | $3.00 |
| 18 | Sawing and sealing asphalt concrete pavement joints, as per plan (409E30001) | FT | 109 | $50.00 | $28.44 | $28.44 | $28.44 | $28.44 |
| 19 | Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000) | CY | 2,283 | $240.00 | $222.00 | $245.00 | $287.73 | $281.00 |
| 20 | Asphalt concrete surface course, 12.5 MM, type A (449) (442E22100) | CY | 150 | $230.00 | $503.00 | $500.00 | $272.10 | $281.00 |
| 21 | Compacted aggregate (617E10100) | CY | 52 | $300.00 | $292.00 | $195.00 | $159.37 | $120.00 |
| 22 | Shoulder preparation (617E20000) | SY | 1,588 | $5.00 | $0.50 | $0.75 | $4.81 | $1.85 |
| 23 | Water (617E25000) | MGAL | 2 | $10.00 | $7.36 | $1.00 | $1.00 | $220.00 |
| 24 | Valve box adjusted to grade (638E10800) | EACH | 4 | $300.00 | $850.00 | $865.00 | $984.30 | $100.00 |
| 25 | RPM (621E00100) | EACH | 25 | $136.00 | $136.00 | $136.00 | $136.00 | $100.00 |
| 26 | Raised pavement marker removed (621E54000) | EACH | 25 | $10.00 | $1.00 | $11.00 | $37.11 | $8.00 |
| 27 | Ground mounted support, no. 2 post (630E02100) | FT | 28 | $15.00 | $15.00 | $21.00 | $15.00 | $15.00 |
| 28 | Ground mounted support, no. 3 post (630E03100) | FT | 40 | $15.50 | $15.50 | $22.00 | $15.50 | $17.50 |
| 29 | Sign post reflector (630E08600) | EACH | 4 | $55.00 | $55.00 | $25.11 | $55.00 | $45.00 |
| 30 | Sign, flat sheet (630E80100) | SF | 35 | $16.00 | $16.00 | $30.00 | $16.00 | $27.50 |
| 31 | Removal of ground mounted sign and disposal, as per plan (630E84901) | EACH | 2 | $20.00 | $20.00 | $25.00 | $20.00 | $100.00 |
| 32 | Signing, misc.:solar-powered rectangular rapid fla (630E97700) | EACH | 2 | $7,495.00 | $7,495.00 | $10,200 | $7,495.00 | $10,000 |
| 33 | Crosswalk line, 24", type 1 (642E00630) | FT | 88 | $15.00 | $15.00 | $15.00 | $15.00 | $10.00 |
| 34 | Yield line, type 1 (642E20802) | FT | 22 | $25.00 | $25.00 | $10.00 | $25.00 | $10.00 |
| 35 | Removal of pavement marking (642E30000) | FT | 92 | $22.80 | $22.80 | $12.50 | $22.80 | $12.50 |
| 36 | Edge line, 4" (644E00100) | MI | 0.42 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 | $4,860.00 |
| 37 | Edge line, 6" (644E00104) | MI | 0.73 | $3,500.00 | $3,500.00 | $3,500.00 | $3,500.00 | $5,750.00 |
| 38 | Center line (644E00300) | MI | 3.58 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $4,750.00 |
| 39 | Channelizing line, 8" (644E00400) | FT | 3,378 | $1.50 | $1.50 | $1.50 | $1.50 | $2.00 |
| 40 | Stop line (644E00500) | FT | 437 | $7.00 | $7.00 | $7.00 | $7.00 | $8.00 |
| 41 | Crosswalk line, 12" (644E00620) | FT | 22 | $3.50 | $3.50 | $3.50 | $3.50 | $3.50 |
| 42 | Crosswalk line, 24" (644E00630) | FT | 1,000 | $7.00 | $7.00 | $7.00 | $7.00 | $7.00 |
| 43 | Transverse/diagonal line (644E00700) | FT | 1,671 | $7.00 | $7.00 | $7.00 | $7.00 | $7.00 |
| 44 | Lane arrow (644E01300) | EACH | 67 | $92.00 | $92.00 | $92.00 | $92.00 | $92.00 |
| 45 | Shared lane marking (644E19000) | EACH | 9 | $525.00 | $525.00 | $335.00 | $525.00 | $335.00 |
| 46 | Detector loop, as per plan (632E26501) | EACH | 4 | $2,500.00 | $1,900.00 | $1,900.00 | $1,900.00 | $1,800.00 |
| 47 | Loop detector tie in (632E27200) | EACH | 4 | $1,800.00 | $100.00 | $100.00 | $100.00 | $170.00 |
| 48 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 80 | $120.00 | $130.00 | $85.00 | $75.00 | $90.00 |
| 49 | Work zone marking sign (614E12460) | EACH | 40 | $115.00 | $115.00 | $90.87 | $115.00 | $85.00 |
| 50 | Portable changeable message sign, as per plan (614E18601) | SNMT | 3 | $895.00 | $1,260.00 | $850.00 | $895.00 | $1,000.00 |
| 51 | Work zone center line, class III, 642 paint (614E21550) | MI | 3.58 | $3,216.00 | $3,216.00 | $850.00 | $3,216.00 | $850.00 |
| 52 | Work zone edge line, class III, 4", 642 paint (614E22350) | MI | 1.15 | $1,250.00 | $1,250.00 | $600.00 | $1,250.00 | $600.00 |
| 53 | Work zone channelizing line, class III, 8", 642 paint (614E23680) | FT | 3,378 | $0.60 | $0.60 | $0.60 | $0.60 | $0.80 |
| 54 | Work zone stop line, class III, 642 paint (614E26610) | FT | 437 | $3.00 | $3.00 | $3.00 | $3.00 | $2.50 |
| 55 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $8,500.00 | $5,600.00 | $4,876.00 | $5,256.95 | $10,000 |
| 56 | Maintaining traffic (614E11000) | LS | 1 | $25,000 | $58,406 | $86,417 | $59,459 | $100,000 |
| 57 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $3,000.00 | $3,500.00 | $6,000.00 | $5,000.00 | $10,000 |
| 58 | Mobilization (624E10000) | LS | 1 | $35,000 | $70,000 | $58,500 | $15,060 | $40,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of March 12, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way