ODOT contract 260188 bid tabulation

ASD-SR 60-14.97 (CULVERT REPLACEMENT). Let by Ohio DOT on April 9, 2026, ASD. 5 bids received; low bid $389,830 by Adena Corporation, -9.3% against the engineer's estimate of $430,000.

Owner
Ohio DOT
Letting
09 APR 2026
Pay items
49
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Adena Corporation$389,830Low-9.0%
2Eius Company$410,138+5.0%-5.0%
3Brennstuhl Construction Inc$426,047+9.0%-1.0%
4Eclipse Co LLC$448,215+15%+4.0%
5Rietschlin Construction Inc$468,359+20%+9.0%
ODOT contract 260188: bids by rank

Engineer's estimate: $430,000.

Bid tabulation

LinePay itemUnitQuantity1. Adena Corporation2. Eius Company3. Brennstuhl Construction Inc4. Eclipse Co LLC5. Rietschlin Construction Inc
1Clearing and grubbing (201E11000)LS1$6,299.00$3,480.00$26,802$32,500$8,000.00
2Structure removed, as per plan (202E11001)LS1$14,589$5,160.00$6,705.60$10,112$47,100
3Pavement removed (202E23000)SY327$8.07$6.58$10.26$23.70$15.00
4Pipe removed, 24" and under (202E35100)FT48$4.02$6.45$69.85$75.69$53.00
5Fence removed (202E75000)FT55$7.01$5.16$15.24$12.14$30.00
6Excavation (203E10000)CY51$18.92$12.90$32.88$10.74$65.00
7Embankment (203E20000)CY773$25.48$39.39$39.10$30.50$20.00
8Subgrade compaction (204E10000)SY395$3.90$2.58$2.83$2.08$5.00
9Monument assembly, type C (623E38500)EACH2$1,885.61$1,993.50$605.00$1,017.70$1,525.00
10Preconstruction survey monument verification and report (623E50000)LS1$1,150.67$1,728.00$1,639.00$2,300.00$1,005.00
11Post construction survey monument verification and report (623E51000)LS1$1,150.67$1,728.00$1,639.00$2,300.00$1,005.00
12Riprap, type D (601E11000)SY16$287.04$724.28$173.78$477.62$310.00
13Rock channel protection, type B with filter (601E32100)CY60$132.47$227.15$153.28$159.49$162.00
14Soil analysis test (659E00100)EACH2$125.00$63.00$165.88$60.00$150.00
15Topsoil (659E00300)CY150$23.88$51.86$116.21$65.00$48.00
16Seeding and mulching (659E10000)SY1,349$2.86$2.52$4.31$2.40$3.00
17Repair seeding and mulching (659E14000)SY67$1.00$2.10$6.82$2.00$3.00
18Inter-seeding (659E15000)SY67$1.00$0.74$6.82$0.70$3.00
19Commercial fertilizer (659E20000)TON0.19$1,810.32$945.00$4,629.26$900.00$1,300.00
20Lime (659E31000)ACRE0.28$698.18$50.39$3,219.86$1.00$100.00
21Water (659E35000)MGAL7.46$1.00$1.05$67.07$1.00$10.00
22Slope erosion protection mat, type B (670E00520)SY212$1.72$3.62$8.54$5.00$6.25
23Erosion control (832E30000)EACH5,000$1.00$1.00$1.00$1.00$1.00
24Aggregate drains (605E31100)FT156$11.82$8.20$21.35$34.62$15.00
258" conduit, type C (611E02000)FT8$55.05$153.05$88.00$53.25$170.00
2612" conduit, type C (611E04600)FT16$47.32$115.60$51.61$76.10$120.00
2718" conduit, type C (611E07600)FT110$55.36$138.74$91.41$88.35$100.00
2863" X 98" conduit, type A, 706.04 (611E53500)FT112$1,262.33$1,098.01$1,140.26$1,015.82$1,350.00
29Catch basin, no. 2-3 (611E98510)EACH1$2,627.98$8,270.40$4,769.80$4,199.27$2,800.00
30Manhole, no. 3 (611E99574)EACH2$3,508.93$7,480.05$3,264.90$5,738.61$4,900.00
31Pavement planing, asphalt concrete (varies 0" to 3 (254E01000)SY160$30.93$26.25$18.22$11.13$27.00
32Asphalt concrete base, PG64-22, (449) (301E56000)CY82$325.79$315.00$311.05$422.46$324.00
33Aggregate base (304E20000)CY111$99.57$153.61$132.66$109.45$113.00
34Aggregate base (304E20000)CY17$99.56$151.55$204.01$120.52$126.00
35Tack coat (407E10000)GAL70$7.95$2.63$8.12$24.14$2.70
36Prime coat, as per plan (408E10001)GAL86$10.51$15.75$12.00$24.14$16.50
37Asphalt concrete surface course, 9.5 MM, type A (4 (442E22001)CY42$681.68$577.50$416.39$543.16$594.00
38Raised pavement marker removed (621E54000)EACH3$20.00$20.64$37.26$1,266.67$48.00
39Edge line, 6", type 1 (642E00104)MI0.08$12,373$9,975.00$11,000$9,500.00$10,800
40Center line, type 1 (642E00300)MI0.04$12,373$9,975.00$11,000$9,500.00$10,800
41Detour signing (614E12420)LS1$5,877.09$6,499.50$5,225.00$7,771.85$5,200.00
42Portable changeable message sign, as per plan (614E18601)SNMT2$1,113.55$945.00$990.00$1,226.88$972.00
43Cofferdams and excavation bracing (503E11100)LS1$13,375$3,601.50$12,264$16,088$23,000
44Concrete masonry (602E20000)CY5.27$3,236.18$3,172.12$1,650.42$2,304.29$1,900.00
45Premium for contract performance bond and for payment bond (103E05000)LS1$5,530.65$5,063.44$6,394.00$6,454.28$7,000.00
46Maintaining traffic (614E11000)LS1$9,880.94$2,271.00$6,705.60$5,676.43$500.00
47Field office, type B (619E16010)MNTH6$500.00$3,625.00$2,500.00$1,416.18$1,400.00
48Construction layout stakes and surveying (623E10000)LS1$4,602.69$3,180.00$13,530$3,621.61$5,000.00
49Mobilization (624E10000)LS1$13,425$12,999$11,070$34,176$30,000
ODOT contract 260188: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of April 9, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy