ODOT contract 260234 bid tabulation
CUY-South Park Shared Use Path (BIKEWAYS). Let by Ohio DOT on May 7, 2026, CUY. 5 bids received; low bid $769,815 by Protect-A-Cote, +6.2% against the engineer's estimate of $725,000.
- Owner
- Ohio DOT
- Letting
- 07 MAY 2026
- Pay items
- 67
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Protect-A-Cote | $769,815 | Low | +6.0% |
| 2 | Eclipse Co LLC | $814,857 | +6.0% | +12% |
| 3 | Northeast Ohio Trenching Service Inc | $836,844 | +9.0% | +15% |
| 4 | Geauga Highway Co | $843,681 | +10% | +16% |
| 5 | Madex Construction Co | $854,153 | +11% | +18% |
Engineer's estimate: $725,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Protect-A-Cote | 2. Eclipse Co LLC | 3. Northeast Ohio Trenching Service Inc | 4. Geauga Highway Co | 5. Madex Construction Co |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $178,000 | $24,200 | $23,415 | $91,000 | $28,947 |
| 2 | Pavement removed (202E23000) | SY | 565 | $10.00 | $37.13 | $30.00 | $25.00 | $26.43 |
| 3 | Walk removed (202E30000) | SF | 2,185 | $4.00 | $5.89 | $15.00 | $2.25 | $5.79 |
| 4 | Curb removed (202E32000) | FT | 27 | $4.00 | $31.05 | $35.00 | $15.00 | $15.30 |
| 5 | Guardrail removed (202E38000) | FT | 502 | $3.00 | $2.75 | $3.00 | $2.50 | $5.79 |
| 6 | Fence removed (202E75000) | FT | 183 | $10.00 | $4.95 | $8.00 | $6.50 | $11.58 |
| 7 | Excavation (203E10000) | CY | 1,523 | $5.00 | $44.88 | $14.00 | $60.00 | $44.19 |
| 8 | Embankment (203E20000) | CY | 233 | $5.00 | $43.87 | $16.00 | $15.00 | $47.10 |
| 9 | Subgrade compaction (204E10000) | SY | 3,983 | $1.00 | $3.23 | $1.00 | $2.25 | $4.73 |
| 10 | Proof rolling (204E45000) | HR | 4 | $100.00 | $311.49 | $150.00 | $100.00 | $186.32 |
| 11 | Guardrail, type MGS (606E15050) | FT | 387.50 | $22.00 | $25.96 | $25.00 | $23.60 | $30.11 |
| 12 | Anchor assembly, MGS type T (606E26550) | EACH | 3 | $1,550.00 | $2,035.00 | $2,152.50 | $1,850.00 | $2,200.00 |
| 13 | 4" concrete walk (608E10000) | SF | 122 | $30.00 | $22.00 | $25.00 | $13.00 | $16.21 |
| 14 | Curb ramp (608E52000) | SF | 76 | $30.00 | $38.50 | $25.00 | $25.00 | $40.53 |
| 15 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $3,000.00 | $3,135.00 | $3,145.00 | $3,000.00 | $6,947.37 |
| 16 | Post construction survey monument verification and report (623E51000) | LS | 1 | $3,000.00 | $3,135.00 | $3,145.00 | $3,000.00 | $6,947.37 |
| 17 | Rock channel protection, type C without filter (601E34200) | CY | 2 | $500.00 | $284.78 | $750.00 | $400.00 | $463.16 |
| 18 | Topsoil furnished and placed (653E10000) | CY | 111 | $60.00 | $75.99 | $62.00 | $75.00 | $75.26 |
| 19 | Soil analysis test (659E00100) | EACH | 1 | $1,000.00 | $88.00 | $355.00 | $150.00 | $289.47 |
| 20 | Seeding and mulching, as per plan (659E10001) | SY | 5,209 | $1.00 | $2.31 | $3.00 | $3.75 | $3.47 |
| 21 | Commercial fertilizer (659E20000) | TON | 0.70 | $100.00 | $880.00 | $1,064.29 | $10.00 | $2,315.79 |
| 22 | Lime (659E31000) | ACRE | 1.08 | $100.00 | $5.50 | $1,537.04 | $10.00 | $868.42 |
| 23 | Water (659E35000) | MGAL | 28 | $1.00 | $0.55 | $142.00 | $100.00 | $70.53 |
| 24 | Mowing (659E40000) | MSF | 118 | $1.00 | $16.50 | $15.00 | $35.00 | $5.79 |
| 25 | Slope erosion protection (670E00500) | SY | 997 | $3.00 | $3.47 | $1.50 | $4.50 | $4.63 |
| 26 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,000.00 | $3,080.00 | $2,940.00 | $3,000.00 | $2,894.74 |
| 27 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $2,000.00 | $2,464.00 | $3,528.00 | $1,500.00 | $4,052.63 |
| 28 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $2,000.00 | $15,344 | $3,833.00 | $13,000 | $10,421 |
| 29 | Erosion control (832E30000) | EACH | 38,800 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 30 | Concrete masonry (602E20000) | CY | 0.40 | $1,000.00 | $4,116.62 | $15,380 | $2,500.00 | $4,052.62 |
| 31 | 6" unclassified pipe underdrains with geotextile fabric, as per plan (605E13411) | FT | 946 | $20.00 | $17.57 | $40.00 | $23.00 | $27.73 |
| 32 | 6" base pipe underdrains with geotextile fabric (605E14020) | FT | 2,509 | $20.00 | $15.87 | $40.00 | $23.00 | $26.74 |
| 33 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 60 | $40.00 | $30.10 | $52.00 | $30.00 | $74.55 |
| 34 | 12" conduit, type B (611E04400) | FT | 178 | $100.00 | $119.92 | $158.00 | $87.00 | $144.74 |
| 35 | 12" conduit, type C (611E04600) | FT | 63 | $70.00 | $132.77 | $150.00 | $65.00 | $150.53 |
| 36 | Catch basin, no. 2-2B (611E98470) | EACH | 6 | $6,000.00 | $3,596.84 | $2,710.00 | $3,000.00 | $3,242.11 |
| 37 | Catch basin adjusted to grade (611E98630) | EACH | 1 | $1,000.00 | $714.10 | $3,000.00 | $1,100.00 | $1,736.84 |
| 38 | Precast reinforced concrete outlet (611E99710) | EACH | 1 | $6,000.00 | $1,100.00 | $3,000.00 | $1,500.00 | $578.95 |
| 39 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 19 | $330.00 | $440.00 | $420.00 | $500.00 | $550.00 |
| 40 | Aggregate base, as per plan (304E20001) | CY | 630 | $120.00 | $107.46 | $105.00 | $124.00 | $144.74 |
| 41 | Tack coat (407E10000) | GAL | 186 | $4.00 | $2.20 | $2.50 | $3.50 | $3.47 |
| 42 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 149 | $350.00 | $355.30 | $375.00 | $280.00 | $443.47 |
| 43 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 249 | $330.00 | $258.50 | $268.00 | $268.00 | $334.63 |
| 44 | 6" non-reinforced concrete pavement, class QC MS (452E10050) | SY | 165 | $100.00 | $132.00 | $105.00 | $120.00 | $123.16 |
| 45 | Curb, type 6 (609E26000) | FT | 7 | $85.00 | $38.50 | $150.00 | $75.00 | $115.79 |
| 46 | Manhole adjusted to grade (611E99654) | EACH | 1 | $1,000.00 | $483.14 | $3,000.00 | $1,100.00 | $2,894.74 |
| 47 | Delineator, post ground mounted (620E00500) | EACH | 21 | $85.00 | $79.95 | $100.00 | $105.00 | $110.00 |
| 48 | Barrier reflector, type 2, BI-directional (626E00110) | EACH | 10 | $20.00 | $14.30 | $14.00 | $25.00 | $15.05 |
| 49 | Ground mounted support, no. 2 post (630E02100) | FT | 222.40 | $14.00 | $19.83 | $24.00 | $10.00 | $28.95 |
| 50 | Ground mounted support, no. 3 post (630E03100) | FT | 28 | $16.00 | $21.48 | $24.00 | $15.00 | $31.26 |
| 51 | Ground mounted support, no. 4 post (630E04100) | FT | 14.50 | $18.00 | $28.08 | $31.50 | $20.00 | $37.05 |
| 52 | Sign post reflector (630E08600) | EACH | 18 | $65.00 | $69.37 | $47.50 | $40.00 | $57.89 |
| 53 | Sign, flat sheet (630E80100) | SF | 94.50 | $16.00 | $24.62 | $27.50 | $22.50 | $34.74 |
| 54 | Removal of ground mounted sign and disposal (630E84900) | EACH | 18 | $30.00 | $19.23 | $10.50 | $30.00 | $70.53 |
| 55 | Removal of ground mounted post support and disposal (630E86002) | EACH | 22 | $40.00 | $25.63 | $21.00 | $30.00 | $34.74 |
| 56 | Edge line, 6", type 1 (642E00104) | MI | 0.08 | $7,500.00 | $14,300 | $14,000 | $30,000 | $16,211 |
| 57 | Mulch, as per plan (661E00501) | CY | 10 | $100.00 | $115.50 | $62.00 | $125.00 | $75.26 |
| 58 | Deciduous tree, 1-1/2" caliper ('autumn fantasy' M (661E40060) | EACH | 5 | $400.00 | $1,100.00 | $439.00 | $600.00 | $868.42 |
| 59 | Deciduous tree, 1-1/2" caliper ('ivory silk' tree (661E40060) | EACH | 8 | $400.00 | $1,100.00 | $522.00 | $600.00 | $868.42 |
| 60 | Deciduous tree, 1-1/2" caliper (red oak) (661E40060) | EACH | 5 | $400.00 | $1,100.00 | $470.00 | $600.00 | $868.42 |
| 61 | Landscape watering, as per plan (662E31001) | GAL | 5,400 | $0.05 | $1.32 | $0.50 | $1.00 | $0.50 |
| 62 | Water (616E10000) | MGAL | 10 | $10.00 | $56.30 | $7.00 | $55.00 | $2.00 |
| 63 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,000 | $9,939.28 | $11,000 | $8,000.00 | $19,947 |
| 64 | Maintaining traffic (614E11000) | LS | 1 | $25,000 | $86,125 | $30,000 | $95,000 | $14,088 |
| 65 | Field office, type B, as per plan (619E16011) | MNTH | 9 | $500.00 | $1,575.00 | $1,142.00 | $1,100.00 | $1,736.84 |
| 66 | Construction layout stakes and surveying (623E10000) | LS | 1 | $22,000 | $7,800.47 | $36,456 | $18,000 | $17,400 |
| 67 | Mobilization (624E10000) | LS | 1 | $20,000 | $57,236 | $80,000 | $4,500.00 | $27,176 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 7, 2026. Compiled by Mirage Metrics.