ODOT contract 260338 bid tabulation
D11-LG-FY2027 (LIGHTING). Let by Ohio DOT on July 16, 2026, District 11. 1 bid received; low bid $781,876 by Cornerstone Electric Inc, -2.0% against the engineer's estimate of $798,000.
- Owner
- Ohio DOT
- Letting
- 16 JUL 2026
- Pay items
- 86
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Cornerstone Electric Inc | $781,876 | Low | -2.0% |
Engineer's estimate: $798,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Cornerstone Electric Inc |
|---|---|---|---|---|
| 1 | Erosion control (832E30000) | EACH | 1,000 | $1.00 |
| 2 | Removal misc.:portion of light pole foundation rem (202E98100) | EACH | 1 | $500.00 |
| 3 | 4" conduit, type E, as per plan (611E00401) | FT | 50 | $15.00 |
| 4 | Connection, fused pull apart (625E00450) | EACH | 28 | $200.00 |
| 5 | Connection, unfused permanent (625E00480) | EACH | 9 | $200.00 |
| 6 | Transformer base, misc.:by type (625E02803) | EACH | 15 | $1,000.00 |
| 7 | Light pole, conventional, design AT15B40 (625E10490) | EACH | 9 | $4,500.00 |
| 8 | Light pole, misc.:29.5' pole height, 34.2' mountin (625E10500) | EACH | 3 | $2,750.00 |
| 9 | Light pole, misc.:35.5' pole height, 41.7' mountin (625E10500) | EACH | 1 | $2,750.00 |
| 10 | Erecting reusable downed light pole, as per plan (625E10505) | EACH | 15 | $1,500.00 |
| 11 | Light tower, misc.:lightning protection system mod (625E13500) | EACH | 1 | $500.00 |
| 12 | Light pole foundation, 24" X 8' deep (625E14100) | EACH | 9 | $1,800.00 |
| 13 | Light pole foundation repair, as per plan (625E14401) | EACH | 1 | $2,000.00 |
| 14 | Light pole foundation, as per plan (625E14501) | EACH | 2 | $2,000.00 |
| 15 | Bracket arm, as per plan (625E17901) | EACH | 3 | $500.00 |
| 16 | No. 4 AWG 2400 volt distribution cable, as per plan (625E23201) | FT | 2,000 | $4.00 |
| 17 | No. 2 AWG 2400 volt distribution cable, as per plan (625E23301) | FT | 250 | $5.00 |
| 18 | No. 10 AWG pole and bracket cable (625E23400) | FT | 1,485 | $2.00 |
| 19 | No. 10 AWG pole and bracket cable, as per plan (625E23401) | FT | 1,000 | $2.00 |
| 20 | 1-1/2" duct cable with two no. 4 AWG 2400 volt cables, as per plan (625E24101) | FT | 1,000 | $9.50 |
| 21 | 1-1/2" duct cable with two no. 2 AWG 2400 volt cables, as per plan (625E24301) | FT | 300 | $12.50 |
| 22 | 1-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320) | FT | 1,528 | $15.00 |
| 23 | Conduit, 2", 725.04 (625E25400) | FT | 100 | $20.00 |
| 24 | Conduit, jacked or drilled, 3" (625E25900) | FT | 200 | $60.00 |
| 25 | Conduit, misc.:wall mounted, 2" (625E25920) | FT | 100 | $25.00 |
| 26 | Luminaire, conventional, solid state (LED) ies-III (625E26252) | EACH | 10 | $375.00 |
| 27 | Luminaire, conventional, solid state (LED) ies-III (625E26252) | EACH | 1 | $400.00 |
| 28 | Luminaire, conventional, solid state (LED) ies-III (625E26252) | EACH | 1 | $1,000.00 |
| 29 | Luminaire, conventional, solid state (LED) ies-III (625E26252) | EACH | 48 | $400.00 |
| 30 | Luminaire, conventional, solid state (LED) ies-II- (625E26252) | EACH | 1 | $325.00 |
| 31 | Luminaire, conventional, solid state (LED) ies-II- (625E26252) | EACH | 10 | $400.00 |
| 32 | Luminaire, conventional, solid state (LED) ies-II- (625E26252) | EACH | 2 | $375.00 |
| 33 | Luminaire, conventional, solid state (LED), ies-II (625E26252) | EACH | 2 | $325.00 |
| 34 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 1 | $950.00 |
| 35 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 1 | $750.00 |
| 36 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 9 | $700.00 |
| 37 | Luminaire, high mast, solid state (LED) asymmetric (625E26262) | EACH | 10 | $950.00 |
| 38 | Luminaire, high mast, solid state (LED) symmetric, (625E26262) | EACH | 2 | $1,250.00 |
| 39 | Luminaire, high mast, solid state (LED) symmetric, (625E26262) | EACH | 6 | $950.00 |
| 40 | Luminaire, low mast, solid state (LED) symmetric, (625E26272) | EACH | 1 | $950.00 |
| 41 | Luminaire, post top, solid state (LED) ies-III-M-S (625E27402) | EACH | 1 | $900.00 |
| 42 | Luminaire, underpass, solid state (LED) ies-III-M- (625E27502) | EACH | 3 | $700.00 |
| 43 | Trench (625E29000) | FT | 1,418 | $12.00 |
| 44 | Trench, as per plan (625E29001) | FT | 1,000 | $10.00 |
| 45 | Trench in paved area (625E29400) | FT | 100 | $50.00 |
| 46 | Pull box, 725.08, 18" (625E30700) | EACH | 2 | $1,500.00 |
| 47 | Pull box, 725.08, 18", as per plan (625E30701) | EACH | 2 | $1,500.00 |
| 48 | Pull box, 725.08, 24", as per plan (625E30707) | EACH | 1 | $1,750.00 |
| 49 | Ground rod (625E32000) | EACH | 10 | $250.00 |
| 50 | Circuit breaker, tower lighting (625E33100) | EACH | 3 | $800.00 |
| 51 | Power service, as per plan (625E34001) | EACH | 4 | $13,500 |
| 52 | Power service, as per plan (625E34001) | EACH | 1 | $13,500 |
| 53 | Control center cabinet, complete, as per plan (100 (625E34451) | EACH | 2 | $200.00 |
| 54 | Control center cabinet, complete, as per plan (30A (625E34451) | EACH | 2 | $200.00 |
| 55 | Control center cabinet, complete, as per plan (60 (625E34451) | EACH | 2 | $200.00 |
| 56 | Remove and reerect bracket arm, as per plan (625E35521) | EACH | 4 | $500.00 |
| 57 | Underground warning marking tape (625E36010) | FT | 1,418 | $2.50 |
| 58 | Power cable for light tower, as per plan (625E36201) | FT | 150 | $5.00 |
| 59 | Lighting, minimal maintenance, as per plan (625E37211) | EACH | 500 | $250.00 |
| 60 | Repairing underground break of cable in duct or conduit (625E50000) | EACH | 20 | $350.00 |
| 61 | Repair integral luminaire lowering mechanism of tower lighting fixture, as per plan (625E50401) | EACH | 2 | $2,500.00 |
| 62 | Special - emergency response-knockdown, roadway hazard and/or live exposed wire (625E50500) | EACH | 10 | $500.00 |
| 63 | Lighting contactor, as per plan (100 amp) (625E70001) | EACH | 2 | $800.00 |
| 64 | Lighting contactor, as per plan (30 amp) (625E70001) | EACH | 2 | $600.00 |
| 65 | Lighting contactor, as per plan (60 amp) (625E70001) | EACH | 2 | $750.00 |
| 66 | Arc flash calculations and label, (S.R. 7 southbou (625E76000) | EACH | 1 | $500.00 |
| 67 | Lighting, misc.: annual operation and inspection O (625E98000) | EACH | 82 | $250.00 |
| 68 | Lighting, misc.: disconnect switch with enclosure, (625E98000) | EACH | 1 | $1,000.00 |
| 69 | Lighting, misc.: disconnect switch with enclosure, (625E98000) | EACH | 1 | $1,000.00 |
| 70 | Lighting, misc.: disconnect switch, 100 amp (625E98000) | EACH | 2 | $250.00 |
| 71 | Lighting, misc.: disconnect switch, 30 amp (625E98000) | EACH | 2 | $250.00 |
| 72 | Lighting, misc.: disconnect switch, 60 amp (625E98000) | EACH | 2 | $250.00 |
| 73 | Lighting, misc.: H.O.A. switch (625E98000) | EACH | 2 | $500.00 |
| 74 | Lighting, misc.: lightning rod repair (625E98000) | EACH | 1 | $1,000.00 |
| 75 | Lighting, misc.: lightning surge arrestor system R (625E98000) | EACH | 3 | $250.00 |
| 76 | Lighting, misc.: photo-cell transformer, 0.75 kva (625E98000) | EACH | 3 | $750.00 |
| 77 | Lighting, misc.: remove and reerect standing light (625E98000) | EACH | 2 | $2,000.00 |
| 78 | Lighting, misc.: tower lighting connectors (625E98000) | EACH | 10 | $500.00 |
| 79 | Lighting, misc.: removing cable in existing duct O (625E98100) | FT | 1,500 | $1.00 |
| 80 | Lighting, misc.: locating and marking underground (625E98700) | HR | 100 | $250.00 |
| 81 | Lighting, misc.: troubleshooting underground and A (625E98700) | HR | 200 | $200.00 |
| 82 | Disconnect switch, 30 amp (631E85000) | EACH | 1 | $200.00 |
| 83 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 50 | $75.00 |
| 84 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $7,500.00 |
| 85 | Maintaining traffic (614E11000) | LS | 1 | $60,000 |
| 86 | Mobilization (624E10000) | LS | 1 | $90,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of July 16, 2026. Compiled by Mirage Metrics.