ODOT contract 260403 bid tabulation
CUY-/GEA-US 422-18.17/00.00 (FOUR LANE RESURFACING). Let by Ohio DOT on September 17, 2026, CUY. 4 bids received; low bid $5,317,000 by Karvo Companies Inc, +3.3% against the engineer's estimate of $5,147,000.
- Owner
- Ohio DOT
- Letting
- 17 SEP 2026
- Pay items
- 57
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Karvo Companies Inc | $5,317,000 | Low | +3.0% |
| 2 | Shelly Company | $5,397,458 | +2.0% | +5.0% |
| 3 | Kokosing Construction Company Inc | $5,726,358 | +8.0% | +11% |
| 4 | Ronyak Paving Inc | $5,789,690 | +9.0% | +12% |
Engineer's estimate: $5,147,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Karvo Companies Inc | 2. Shelly Company | 3. Kokosing Construction Company Inc | 4. Ronyak Paving Inc |
|---|---|---|---|---|---|---|---|
| 1 | Linear grading, as per plan (209E60201) | STA | 200 | $25.00 | $55.00 | $125.00 | $10.00 |
| 2 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 4 | Partial depth pavement repair (441), as per plan (251E01001) | SY | 450 | $75.00 | $65.00 | $112.00 | $70.00 |
| 5 | Partial depth pavement repair (441), as per plan (251E01001) | SY | 1,820 | $100.00 | $80.00 | $124.00 | $125.00 |
| 6 | Pavement repair, as per plan (253E02001) | CY | 50 | $500.00 | $875.00 | $1,150.00 | $950.00 |
| 7 | Pavement planing, asphalt concrete, as per plan, 1 (254E01001) | SY | 252,831 | $2.45 | $1.80 | $2.00 | $2.25 |
| 8 | Non-tracking tack coat (407E20000) | GAL | 21,498 | $3.00 | $3.00 | $3.00 | $2.00 |
| 9 | Anti-segregation equipment (442E00100) | CY | 6,792 | $10.00 | $6.00 | $1.00 | $4.00 |
| 10 | Asphalt concrete surface course, 12.5 MM, type A (446), as per plan (442E10001) | CY | 556 | $325.00 | $275.00 | $335.00 | $360.00 |
| 11 | Asphalt concrete surface course, 12.5 MM, type A (447), as per plan (442E10301) | CY | 9,979 | $250.00 | $240.00 | $297.00 | $265.00 |
| 12 | Compacted aggregate, as per plan (617E10101) | CY | 300 | $100.00 | $100.00 | $40.00 | $150.00 |
| 13 | Rumble strips, shoulder (asphalt concrete), as per plan (618E40601) | MI | 22 | $635.00 | $1,350.00 | $635.00 | $635.00 |
| 14 | Grooving for 6" recessed pavement marking, (asphalt) (850E10010) | MI | 32.72 | $1,350.00 | $1,350.00 | $1,350.00 | $1,350.00 |
| 15 | Grooving for 6" recessed pavement marking, (asphalt) (850E10110) | FT | 4,065 | $1.25 | $1.25 | $1.25 | $1.25 |
| 16 | Grooving for 12" recessed pavement marking, (asphalt) (850E10130) | FT | 3,775 | $1.60 | $1.60 | $1.60 | $1.60 |
| 17 | Grooving for 6" recessed pavement marking, (concrete) (850E20110) | FT | 8,680 | $1.55 | $1.55 | $1.55 | $1.55 |
| 18 | Void reducing asphalt membrane (vram) (872E10000) | FT | 3,414 | $4.50 | $4.50 | $4.70 | $4.50 |
| 19 | Delineator, post ground mounted (620E00500) | EACH | 224 | $86.00 | $100.00 | $100.00 | $100.00 |
| 20 | Removal of delineator (620E31200) | EACH | 224 | $6.50 | $25.00 | $25.00 | $25.00 |
| 21 | RPM (621E00100) | EACH | 649 | $47.00 | $47.00 | $47.00 | $47.00 |
| 22 | Raised pavement marker removed (621E54000) | EACH | 483 | $1.00 | $3.00 | $3.00 | $1.00 |
| 23 | Signing, misc.: additional signs, ground mounted, (630E97800) | SF | 300 | $12.50 | $12.50 | $12.50 | $12.50 |
| 25 | Stop line (646E10400) | FT | 96 | $13.00 | $13.00 | $13.00 | $13.00 |
| 26 | Lane arrow (646E20300) | EACH | 15 | $155.00 | $155.00 | $155.00 | $155.00 |
| 27 | Wrong way arrow (646E20320) | EACH | 2 | $225.00 | $225.00 | $225.00 | $225.00 |
| 28 | Wet reflective epoxy pavement marking, edge line, 6" (807E12010) | MI | 11.72 | $3,955.00 | $3,955.00 | $3,955.00 | $3,955.00 |
| 29 | Wet reflective epoxy pavement marking, edge line, 6" (807E12010) | MI | 11.72 | $3,955.00 | $3,955.00 | $3,955.00 | $3,955.00 |
| 30 | Wet reflective epoxy pavement marking, lane line, 6" (807E12110) | MI | 10.93 | $1,995.00 | $1,995.00 | $1,995.00 | $1,995.00 |
| 31 | Wet reflective epoxy pavement marking, channelizing line, 12" (807E12310) | FT | 3,775 | $2.10 | $2.10 | $2.10 | $2.10 |
| 32 | Wet reflective epoxy pavement marking, dotted line, 6" (807E12410) | FT | 4,065 | $1.40 | $1.40 | $1.40 | $1.40 |
| 33 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 100 | $150.00 | $100.00 | $130.00 | $125.00 |
| 34 | Work zone increased penalties sign (614E12484) | EACH | 6 | $225.00 | $225.00 | $225.00 | $225.00 |
| 35 | Asphalt concrete for maintaining traffic, as per plan (614E13001) | CY | 100 | $275.00 | $175.00 | $125.00 | $100.00 |
| 36 | Portable changeable message sign, as per plan (614E18601) | SNMT | 6 | $1,000.00 | $1,000.00 | $1,000.00 | $1,250.00 |
| 37 | Work zone lane line, class I, 6", 642 paint (614E20110) | MI | 11.02 | $500.00 | $500.00 | $500.00 | $500.00 |
| 38 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 11.02 | $500.00 | $500.00 | $500.00 | $500.00 |
| 39 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 23.62 | $650.00 | $650.00 | $650.00 | $650.00 |
| 40 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 23.62 | $625.00 | $625.00 | $625.00 | $625.00 |
| 41 | Work zone channelizing line, class I, 12", 642 paint (614E23210) | FT | 4,671 | $0.69 | $0.70 | $0.69 | $0.69 |
| 42 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 4,671 | $0.69 | $0.70 | $0.69 | $0.69 |
| 43 | Work zone dotted line, class I, 6", 642 paint (614E24202) | FT | 4,065 | $0.55 | $0.55 | $0.55 | $0.55 |
| 44 | Work zone dotted line, class III, 6", 642 paint (614E24612) | FT | 4,065 | $0.55 | $0.55 | $0.55 | $0.55 |
| 45 | Work zone stop line, class I, 642 paint (614E26200) | FT | 96 | $3.20 | $3.20 | $3.20 | $3.20 |
| 46 | Work zone stop line, class III, 642 paint (614E26610) | FT | 96 | $3.00 | $3.00 | $3.00 | $3.00 |
| 47 | Work zone arrow, class I, 642 paint (614E30200) | EACH | 15 | $55.00 | $55.00 | $55.00 | $55.00 |
| 48 | Work zone arrow, class III, 642 paint (614E30650) | EACH | 15 | $55.00 | $55.00 | $55.00 | $55.00 |
| 49 | Digital speed limit (DSL) sign assembly (808E18700) | SNMT | 6 | $650.00 | $650.00 | $650.00 | $650.00 |
| 50 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $43,200 | $47,150 | $23,015 | $34,995 |
| 51 | Maintaining traffic (614E11000) | LS | 1 | $349,941 | $675,000 | $344,084 | $350,000 |
| 52 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $35,000 | $50,000 | $8,000.00 | $15,650 |
| 53 | Mobilization (624E10000) | LS | 1 | $334,673 | $200,000 | $282,343 | $365,000 |
| 100 | Excavation (203E10000) | CY | 35 | $15.00 | $50.00 | $55.00 | $55.00 |
| 101 | Aggregate base (304E20000) | CY | 35 | $25.00 | $70.00 | $125.00 | $125.00 |
| 102 | Special - paver mounted thermal profiling (400E10000) | LS | 1 | $75,000 | $32,000 | $3,400.00 | $100,000 |
| 103 | Special - intelligent compaction (690E98400) | LS | 1 | $65,000 | $75,000 | $30,000 | $150,000 |
| 104 | Full depth pavement removal and rigid replacement, type 1, class QC MS, as per plan (255E15001) | SY | 2,000 | $150.00 | $260.00 | $260.50 | $261.00 |
| 105 | Full depth pavement removal and rigid replacement, type 1, class QC MS, as per plan (255E15001) | SY | 100 | $150.00 | $225.00 | $240.00 | $251.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of September 17, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.