ODOT contract 260434 bid tabulation
RIC-SR 314/SR 545-00.00/02.111 (TWO LANE RESURFACING). Let by Ohio DOT on October 1, 2026, RIC. 2 bids received; low bid $5,013,495 by Kokosing Construction Company Inc, -7.6% against the engineer's estimate of $5,426,000.
- Owner
- Ohio DOT
- Letting
- 01 OCT 2026
- Pay items
- 79
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Kokosing Construction Company Inc | $5,013,495 | Low | -8.0% |
| 2 | Shelly & Sands Inc | $5,046,052 | +1.0% | -7.0% |
Engineer's estimate: $5,426,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Kokosing Construction Company Inc | 2. Shelly & Sands Inc |
|---|---|---|---|---|---|
| 1 | Guardrail removed (202E38000) | FT | 1,987.75 | $2.00 | $2.00 |
| 2 | Anchor assembly removed, type E (202E42010) | EACH | 22 | $200.00 | $200.00 |
| 3 | Anchor assembly removed, type T (202E42040) | EACH | 8 | $200.00 | $200.00 |
| 4 | Bridge terminal assembly removed (202E47000) | EACH | 12 | $200.00 | $200.00 |
| 5 | Embankment, as per plan (203E20001) | CY | 83 | $65.00 | $65.00 |
| 6 | Reshaping under guardrail, as per plan (209E15001) | STA | 9.13 | $65.00 | $65.00 |
| 7 | Linear grading (209E60500) | MI | 6.04 | $1,200.00 | $1,800.00 |
| 8 | Preparing subgrade for shoulder paving, as per plan (209E72051) | MI | 16.64 | $1,500.00 | $1,800.00 |
| 9 | Grading mailbox approaches (209E80000) | EACH | 66 | $20.00 | $153.70 |
| 10 | Guardrail, type 5 (606E13000) | FT | 169 | $19.00 | $19.00 |
| 11 | Guardrail, type MGS (606E15050) | FT | 1,743.75 | $19.00 | $19.00 |
| 12 | Guardrail, type MGS with long posts (606E15100) | FT | 75 | $21.50 | $21.50 |
| 13 | Guardrail rebuilt, type 5 (606E16500) | FT | 200 | $12.00 | $12.00 |
| 14 | Raising type MGS guardrail (606E17050) | FT | 187.50 | $9.00 | $9.00 |
| 15 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 20 | $2,400.00 | $2,400.00 |
| 16 | Anchor assembly, type T (606E26500) | EACH | 2 | $1,400.00 | $1,400.00 |
| 17 | Anchor assembly, MGS type T (606E26550) | EACH | 8 | $1,400.00 | $1,400.00 |
| 18 | Anchor assembly rebuilt, type E (606E27850) | EACH | 1 | $875.00 | $875.00 |
| 19 | Anchor assembly rebuilt, MGS type E (606E27860) | EACH | 4 | $875.00 | $875.00 |
| 20 | Bridge terminal assembly, type TST (606E32160) | EACH | 4 | $2,375.00 | $2,375.00 |
| 21 | Bridge terminal assembly, type 4 (606E35140) | EACH | 8 | $1,100.00 | $1,100.00 |
| 22 | Monument assembly adjusted to grade, as per plan (623E39501) | EACH | 4 | $700.00 | $1,200.00 |
| 23 | Monument assembly reconstructed to grade, as per plan (623E39601) | EACH | 4 | $1,100.00 | $1,800.00 |
| 24 | Post construction survey monument verification and report (623E51000) | LS | 1 | $2,000.00 | $8,000.00 |
| 25 | Special - mailbox support system, single (690E50100) | EACH | 7 | $150.00 | $220.00 |
| 26 | Special - mailbox support system, double (690E50200) | EACH | 1 | $250.00 | $325.00 |
| 27 | Erosion control (832E30000) | EACH | 3,000 | $1.00 | $1.00 |
| 28 | Catch basin adjusted to grade (611E98630) | EACH | 4 | $700.00 | $800.00 |
| 29 | Partial depth pavement repair (asphalt concrete base), as per plan (251E01043) | CY | 1,941 | $255.00 | $325.00 |
| 30 | Partial depth pavement repair (asphalt concrete base), as per plan (251E01043) | CY | 342 | $260.00 | $375.00 |
| 31 | Pavement repair, as per plan (253E02001) | CY | 195 | $260.00 | $350.00 |
| 32 | Pavement repair, as per plan (253E02001) | CY | 33 | $280.00 | $400.00 |
| 33 | Pavement planing, asphalt concrete (1.5") (254E01000) | SY | 46,542 | $0.60 | $1.00 |
| 34 | Pavement planing, asphalt concrete (2.25") (254E01000) | SY | 115,135 | $0.68 | $1.10 |
| 35 | Pavement planing, asphalt concrete (taper 1.5" to (254E01000) | SY | 1,976 | $5.00 | $4.00 |
| 36 | Pavement planing, asphalt concrete (taper 2.25" to (254E01000) | SY | 4,858 | $5.00 | $5.00 |
| 37 | Patching planed surface (254E01600) | SY | 877 | $1.25 | $4.00 |
| 38 | Tack coat (407E10000) | GAL | 21,929 | $2.90 | $2.25 |
| 39 | Tack coat, 702.13 (407E13900) | GAL | 72 | $5.00 | $3.50 |
| 40 | Prime coat, as per plan (408E10001) | GAL | 10,649 | $5.25 | $4.25 |
| 41 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E00201) | CY | 4,199 | $213.00 | $198.00 |
| 42 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E00201) | CY | 2,045 | $217.00 | $198.00 |
| 43 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E00201) | CY | 504 | $213.00 | $198.00 |
| 44 | Asphalt concrete intermediate course, 9.5 MM, type A (448) (442E20100) | CY | 1,333 | $230.00 | $198.00 |
| 45 | Asphalt concrete intermediate course, 12.5 MM, type A (448) (442E20170) | CY | 5,876 | $206.00 | $185.00 |
| 46 | Compacted aggregate (617E10100) | CY | 1,752 | $40.00 | $52.00 |
| 47 | Shoulder preparation (617E20000) | SY | 7,089 | $0.10 | $0.25 |
| 48 | RPM (621E00100) | EACH | 1,047 | $29.00 | $29.77 |
| 49 | Raised pavement marker removed (621E54000) | EACH | 1,047 | $3.00 | $8.00 |
| 50 | Barrier reflector, type 2 (bidirectional) (626E00110) | EACH | 81 | $13.00 | $13.00 |
| 51 | Edge line, 6", type 1 (642E00104) | MI | 22.71 | $900.00 | $900.00 |
| 52 | Center line, type 1 (642E00300) | MI | 11.36 | $900.00 | $900.00 |
| 53 | Removal of pavement marking (642E30030) | MI | 0.05 | $25,000 | $25,000 |
| 54 | Removal of pavement marking (642E30030) | MI | 0.09 | $25,000 | $25,000 |
| 55 | Stop line (644E00500) | FT | 665 | $10.00 | $10.00 |
| 56 | Railroad symbol marking (644E01000) | EACH | 2 | $700.00 | $700.00 |
| 57 | Edge line, 6" (646E10010) | MI | 0.12 | $27,000 | $27,000 |
| 58 | Center line (646E10200) | MI | 0.06 | $46,000 | $46,000 |
| 59 | Work zone marking sign (614E12460) | EACH | 105 | $80.00 | $80.00 |
| 60 | Asphalt concrete for maintaining traffic (614E13000) | CY | 45 | $125.00 | $500.00 |
| 61 | Portable changeable message sign, as per plan (614E18601) | SNMT | 12 | $1,000.00 | $1,000.00 |
| 62 | Work zone center line, class III, 642 paint (614E21550) | MI | 34.25 | $900.00 | $900.00 |
| 63 | Work zone stop line, class III, 642 paint (614E26610) | FT | 1,995 | $2.00 | $4.00 |
| 64 | Work zone railroad symbol marking, class III, 642 paint (614E32210) | EACH | 6 | $100.00 | $400.00 |
| 65 | Special - sawing and sealing bituminous concrete joints (516E31200) | FT | 104 | $30.00 | $28.44 |
| 66 | Deep beam bridge retrofit railing (517E75600) | FT | 112.50 | $144.00 | $140.00 |
| 67 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 590 | $11.70 | $11.70 |
| 68 | Special - sawing and sealing bituminous concrete joints (516E31200) | FT | 84 | $30.00 | $28.44 |
| 69 | Special - patching concrete bridge deck (519E12510) | SY | 1 | $3,528.00 | $3,528.00 |
| 70 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 476 | $11.70 | $11.70 |
| 71 | Special - sawing and sealing bituminous concrete joints (516E31200) | FT | 178 | $30.00 | $28.44 |
| 72 | Deep beam bridge retrofit railing (517E75600) | FT | 250 | $144.00 | $140.00 |
| 73 | Special - railroad coordination (900E17000) | LS | 1 | $250.00 | $4,000.00 |
| 74 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $2,800.00 | $3,500.00 |
| 75 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $20,000 | $25,000 |
| 76 | Maintaining traffic (614E11000) | LS | 1 | $364,647 | $375,620 |
| 77 | Field office, type B (619E16010) | MNTH | 7 | $2,200.00 | $3,500.00 |
| 78 | Construction layout stakes and surveying (623E10000) | LS | 1 | $3,600.00 | $15,000 |
| 79 | Mobilization (624E10000) | LS | 1 | $250,000 | $200,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 1, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.