ODOT contract 260516 bid tabulation

D07-Lighting RPL FY 2027 (LIGHTING). Let by Ohio DOT on November 12, 2026, District 7. 4 bids received; low bid $2,090,731 by Danbert Electrical Corp, +9.1% against the engineer's estimate of $1,917,000.

Owner
Ohio DOT
Letting
12 NOV 2026
Pay items
46
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Danbert Electrical Corp$2,090,731Low+9.0%
2Complete General Construction Company$2,218,654+6.0%+16%
3Miller Cable Company$2,244,233+7.0%+17%
4Perram Electric Inc$2,449,110+17%+28%
ODOT contract 260516: bids by rank

Engineer's estimate: $1,917,000.

Bid tabulation

LinePay itemUnitQuantity1. Danbert Electrical Corp2. Complete General Construction Company3. Miller Cable Company4. Perram Electric Inc
1Clearing and grubbing (201E11000)LS1$5,500.00$6,000.00$500.00$1,352.00
2Seeding and mulching (659E10000)SY2,223$1.80$3.95$3.95$1.35
3Repair seeding and mulching (659E14000)SY112$1.80$3.50$3.50$4.45
4Inter-seeding (659E15000)SY112$1.50$0.20$0.20$4.45
5Commercial fertilizer (659E20000)TON0.31$850.00$1,125.00$1,125.00$1,000.00
6Lime (659E31000)ACRE0.46$35.00$50.00$50.00$1,000.00
7Water (659E35000)MGAL13$82.00$1.00$1.00$100.00
8Erosion control (832E30000)EACH10,000$1.00$1.00$1.00$1.00
9Connection, fused pull apart (625E00450)EACH210$159.50$155.00$120.00$181.45
10Connection, unfused pull apart (625E00460)EACH107$143.00$150.00$120.00$177.50
11Connection, unfused permanent (625E00480)EACH114$126.00$125.00$120.00$127.50
12Light pole, conventional, AT15B40 (625E10490)EACH78$3,437.50$3,000.00$4,300.00$3,339.00
13Light pole, conventional, AT20B40 (625E10490)EACH19$4,939.00$4,200.00$4,800.00$3,850.00
14Light pole, conventional, AT25B40 (625E10490)EACH10$5,186.50$4,300.00$5,600.00$3,997.00
15Light pole foundation, 24" X 8' deep (625E14100)EACH107$1,628.00$2,525.00$1,950.00$2,216.00
16No. 4 AWG 2400 volt distribution cable (625E23200)FT10$15.95$4.10$5.00$26.00
17No. 10 AWG pole and bracket cable (625E23400)FT13,910$1.56$2.20$2.00$1.47
181-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320)FT29,432$16.96$13.50$15.00$15.99
19Conduit, 3", 725.04 (625E25500)FT337$40.34$39.00$39.00$44.83
20Conduit, jacked or drilled, 725.04, 3" (625E25902)FT4,217$44.44$51.00$55.00$78.82
21Luminaire, conventional, solid state (LED), as per plan (625E26253)EACH108$665.50$500.00$525.00$550.00
22Glare shield (625E28000)EACH14$88.00$120.00$125.00$83.25
23Trench, 24" deep (625E29002)FT24,315$7.15$9.00$9.00$8.52
24Pull box, 725.08, 18" (625E30700)EACH84$1,111.00$1,375.00$1,100.00$1,919.00
25Pull box, 725.08, 24" (625E30706)EACH1$1,221.00$1,625.00$1,325.00$1,665.00
26Pull box removed (625E31510)EACH55$121.00$185.00$300.00$238.00
27Ground rod (625E32000)EACH107$363.00$350.00$275.00$340.80
28Power service, as per plan (625E34001)EACH5$14,718$14,675$10,200$11,527
29Underground warning marking tape (625E36010)FT20,900$0.11$1.00$2.25$1.68
30Special - maintain existing lighting (625E40000)LS1$48,345$37,000$18,500$1,352.00
31Special - replacement of existing lighting unit (625E40010)EACH1$4,983.00$5,100.00$2,085.00$1,352.00
32Light pole removed (625E75400)EACH76$220.00$400.00$350.00$895.00
33Light pole foundation removed (625E75500)EACH76$248.00$700.00$200.00$664.00
34Luminaire removed (625E75506)EACH76$110.00$42.00$50.00$53.25
35Power service removed (625E75510)EACH3$440.00$950.00$600.00$852.00
36Arc flash calculations and label cca SR 29 (625E76000)EACH1$3,355.00$3,635.00$1,500.00$1,800.00
37Arc flash calculations and label CCB SR 29 (625E76000)EACH1$3,355.00$3,635.00$1,500.00$1,800.00
38Arc flash calculations and label, CC US 68 (625E76000)EACH1$3,355.00$3,635.00$1,500.00$1,800.00
39Arc flash calculations and label, cca SR 66 (625E76000)EACH1$3,355.00$3,635.00$1,500.00$1,800.00
40Arc flash calculations and label, CCB SR 66 (625E76000)EACH1$3,355.00$3,635.00$1,500.00$1,800.00
41Service cable, 3 conductor, no. 4 AWG (632E69900)FT138$6.38$4.40$15.00$11.85
42Law enforcement officer with patrol car for assistance (614E11110)HR40$110.00$110.00$75.00$100.00
43Premium for contract performance bond and for payment bond (103E05000)LS1$11,000$10,850$8,500.00$16,118
44Maintaining traffic (614E11000)LS1$25,894$34,000$32,500$51,130
45Construction layout stakes and surveying (623E10000)LS1$30,240$13,750$30,240$18,000
46Mobilization (624E10000)LS1$45,650$100,000$100,000$110,000
ODOT contract 260516: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of November 12, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy