ODOT contract 260516 bid tabulation
D07-Lighting RPL FY 2027 (LIGHTING). Let by Ohio DOT on November 12, 2026, District 7. 4 bids received; low bid $2,090,731 by Danbert Electrical Corp, +9.1% against the engineer's estimate of $1,917,000.
- Owner
- Ohio DOT
- Letting
- 12 NOV 2026
- Pay items
- 46
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Danbert Electrical Corp | $2,090,731 | Low | +9.0% |
| 2 | Complete General Construction Company | $2,218,654 | +6.0% | +16% |
| 3 | Miller Cable Company | $2,244,233 | +7.0% | +17% |
| 4 | Perram Electric Inc | $2,449,110 | +17% | +28% |
Engineer's estimate: $1,917,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Danbert Electrical Corp | 2. Complete General Construction Company | 3. Miller Cable Company | 4. Perram Electric Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $5,500.00 | $6,000.00 | $500.00 | $1,352.00 |
| 2 | Seeding and mulching (659E10000) | SY | 2,223 | $1.80 | $3.95 | $3.95 | $1.35 |
| 3 | Repair seeding and mulching (659E14000) | SY | 112 | $1.80 | $3.50 | $3.50 | $4.45 |
| 4 | Inter-seeding (659E15000) | SY | 112 | $1.50 | $0.20 | $0.20 | $4.45 |
| 5 | Commercial fertilizer (659E20000) | TON | 0.31 | $850.00 | $1,125.00 | $1,125.00 | $1,000.00 |
| 6 | Lime (659E31000) | ACRE | 0.46 | $35.00 | $50.00 | $50.00 | $1,000.00 |
| 7 | Water (659E35000) | MGAL | 13 | $82.00 | $1.00 | $1.00 | $100.00 |
| 8 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 9 | Connection, fused pull apart (625E00450) | EACH | 210 | $159.50 | $155.00 | $120.00 | $181.45 |
| 10 | Connection, unfused pull apart (625E00460) | EACH | 107 | $143.00 | $150.00 | $120.00 | $177.50 |
| 11 | Connection, unfused permanent (625E00480) | EACH | 114 | $126.00 | $125.00 | $120.00 | $127.50 |
| 12 | Light pole, conventional, AT15B40 (625E10490) | EACH | 78 | $3,437.50 | $3,000.00 | $4,300.00 | $3,339.00 |
| 13 | Light pole, conventional, AT20B40 (625E10490) | EACH | 19 | $4,939.00 | $4,200.00 | $4,800.00 | $3,850.00 |
| 14 | Light pole, conventional, AT25B40 (625E10490) | EACH | 10 | $5,186.50 | $4,300.00 | $5,600.00 | $3,997.00 |
| 15 | Light pole foundation, 24" X 8' deep (625E14100) | EACH | 107 | $1,628.00 | $2,525.00 | $1,950.00 | $2,216.00 |
| 16 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 10 | $15.95 | $4.10 | $5.00 | $26.00 |
| 17 | No. 10 AWG pole and bracket cable (625E23400) | FT | 13,910 | $1.56 | $2.20 | $2.00 | $1.47 |
| 18 | 1-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320) | FT | 29,432 | $16.96 | $13.50 | $15.00 | $15.99 |
| 19 | Conduit, 3", 725.04 (625E25500) | FT | 337 | $40.34 | $39.00 | $39.00 | $44.83 |
| 20 | Conduit, jacked or drilled, 725.04, 3" (625E25902) | FT | 4,217 | $44.44 | $51.00 | $55.00 | $78.82 |
| 21 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 108 | $665.50 | $500.00 | $525.00 | $550.00 |
| 22 | Glare shield (625E28000) | EACH | 14 | $88.00 | $120.00 | $125.00 | $83.25 |
| 23 | Trench, 24" deep (625E29002) | FT | 24,315 | $7.15 | $9.00 | $9.00 | $8.52 |
| 24 | Pull box, 725.08, 18" (625E30700) | EACH | 84 | $1,111.00 | $1,375.00 | $1,100.00 | $1,919.00 |
| 25 | Pull box, 725.08, 24" (625E30706) | EACH | 1 | $1,221.00 | $1,625.00 | $1,325.00 | $1,665.00 |
| 26 | Pull box removed (625E31510) | EACH | 55 | $121.00 | $185.00 | $300.00 | $238.00 |
| 27 | Ground rod (625E32000) | EACH | 107 | $363.00 | $350.00 | $275.00 | $340.80 |
| 28 | Power service, as per plan (625E34001) | EACH | 5 | $14,718 | $14,675 | $10,200 | $11,527 |
| 29 | Underground warning marking tape (625E36010) | FT | 20,900 | $0.11 | $1.00 | $2.25 | $1.68 |
| 30 | Special - maintain existing lighting (625E40000) | LS | 1 | $48,345 | $37,000 | $18,500 | $1,352.00 |
| 31 | Special - replacement of existing lighting unit (625E40010) | EACH | 1 | $4,983.00 | $5,100.00 | $2,085.00 | $1,352.00 |
| 32 | Light pole removed (625E75400) | EACH | 76 | $220.00 | $400.00 | $350.00 | $895.00 |
| 33 | Light pole foundation removed (625E75500) | EACH | 76 | $248.00 | $700.00 | $200.00 | $664.00 |
| 34 | Luminaire removed (625E75506) | EACH | 76 | $110.00 | $42.00 | $50.00 | $53.25 |
| 35 | Power service removed (625E75510) | EACH | 3 | $440.00 | $950.00 | $600.00 | $852.00 |
| 36 | Arc flash calculations and label cca SR 29 (625E76000) | EACH | 1 | $3,355.00 | $3,635.00 | $1,500.00 | $1,800.00 |
| 37 | Arc flash calculations and label CCB SR 29 (625E76000) | EACH | 1 | $3,355.00 | $3,635.00 | $1,500.00 | $1,800.00 |
| 38 | Arc flash calculations and label, CC US 68 (625E76000) | EACH | 1 | $3,355.00 | $3,635.00 | $1,500.00 | $1,800.00 |
| 39 | Arc flash calculations and label, cca SR 66 (625E76000) | EACH | 1 | $3,355.00 | $3,635.00 | $1,500.00 | $1,800.00 |
| 40 | Arc flash calculations and label, CCB SR 66 (625E76000) | EACH | 1 | $3,355.00 | $3,635.00 | $1,500.00 | $1,800.00 |
| 41 | Service cable, 3 conductor, no. 4 AWG (632E69900) | FT | 138 | $6.38 | $4.40 | $15.00 | $11.85 |
| 42 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 40 | $110.00 | $110.00 | $75.00 | $100.00 |
| 43 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $11,000 | $10,850 | $8,500.00 | $16,118 |
| 44 | Maintaining traffic (614E11000) | LS | 1 | $25,894 | $34,000 | $32,500 | $51,130 |
| 45 | Construction layout stakes and surveying (623E10000) | LS | 1 | $30,240 | $13,750 | $30,240 | $18,000 |
| 46 | Mobilization (624E10000) | LS | 1 | $45,650 | $100,000 | $100,000 | $110,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of November 12, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.