ODOT contract 264010 bid tabulation
JEF-Wintersville Sidewalk Improv (SIDEWALK). Let by Ohio DOT on April 23, 2026, JEF. 3 bids received; low bid $291,808 by Bog Construction Inc, -8.2% against the engineer's estimate of $318,000.
- Owner
- Ohio DOT
- Letting
- 23 APR 2026
- Pay items
- 49
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Bog Construction Inc | $291,808 | Low | -8.0% |
| 2 | Madex Construction Co | $399,862 | +37% | +26% |
| 3 | Craig Edward Susany Inc | $487,966 | +67% | +53% |
Engineer's estimate: $318,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Bog Construction Inc | 2. Madex Construction Co | 3. Craig Edward Susany Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $2,500.00 | $2,218.70 | $100.00 |
| 2 | Pavement removed (202E23000) | SY | 528 | $35.00 | $32.94 | $45.00 |
| 3 | Walk removed, as per plan (202E30001) | SF | 5,219 | $4.00 | $2.14 | $10.00 |
| 4 | Curb removed (202E32000) | FT | 285 | $8.00 | $17.37 | $50.00 |
| 5 | Excavation (203E10000) | CY | 4 | $500.00 | $70.53 | $50.00 |
| 6 | Embankment (203E20000) | CY | 2 | $500.00 | $86.84 | $500.00 |
| 7 | Subgrade compaction (204E10000) | SY | 852 | $4.00 | $5.79 | $9.00 |
| 8 | 4" concrete walk, as per plan (608E10001) | SF | 4,829 | $8.00 | $18.53 | $21.00 |
| 9 | 8" concrete walk, as per plan (608E15001) | SF | 339 | $16.00 | $23.16 | $46.00 |
| 10 | Curb ramp, as per plan (608E52001) | SF | 1,142 | $11.00 | $28.95 | $36.00 |
| 11 | Dumped rock fill, as per plan (601E28101) | CY | 4 | $150.00 | $578.95 | $190.00 |
| 12 | Soil analysis test (659E00100) | EACH | 2 | $50.00 | $89.47 | $150.00 |
| 13 | Topsoil (659E00300) | CY | 20 | $40.00 | $86.84 | $200.00 |
| 14 | Seeding and mulching, class 1 (659E00500) | SY | 179 | $25.00 | $1.58 | $20.00 |
| 15 | Repair seeding and mulching (659E14000) | SY | 9 | $10.00 | $1.58 | $19.00 |
| 16 | Commercial fertilizer (659E20000) | TON | 0.02 | $1,000.00 | $2,316.00 | $2,000.00 |
| 17 | Lime (659E31000) | ACRE | 0.04 | $100.00 | $579.00 | $700.00 |
| 18 | Water (659E35000) | MGAL | 1 | $1.00 | $7.53 | $1.00 |
| 19 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 |
| 20 | Manhole adjusted to grade (611E99654) | EACH | 1 | $750.00 | $2,894.74 | $1,000.00 |
| 21 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 15 | $860.00 | $1,157.89 | $2,000.00 |
| 22 | Aggregate base (304E20000) | CY | 23 | $210.00 | $289.47 | $400.00 |
| 23 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 5 | $2,000.00 | $3,473.68 | $3,000.00 |
| 24 | Curb, type 4-C (609E24510) | FT | 464 | $37.00 | $78.74 | $76.00 |
| 25 | Ground mounted support, no. 2 post (630E02100) | FT | 36 | $25.00 | $28.95 | $13.00 |
| 26 | Ground mounted support, no. 3 post (630E03100) | FT | 13 | $27.00 | $31.26 | $14.00 |
| 27 | Ground mounted support, no. 4 post (630E04100) | FT | 20 | $40.00 | $46.32 | $17.00 |
| 28 | Street name sign support, no. 2 post (630E08510) | FT | 11 | $35.00 | $40.53 | $14.00 |
| 29 | Sign, flat sheet (630E80100) | SF | 37.50 | $35.00 | $37.05 | $20.00 |
| 30 | Sign, double faced, street name (630E80500) | EACH | 2 | $475.00 | $578.95 | $125.00 |
| 31 | Removal of ground mounted sign and disposal (630E84900) | EACH | 6 | $100.00 | $70.53 | $30.00 |
| 32 | Edge line, 6" (646E10010) | MI | 0.08 | $11,000 | $11,579 | $15,000 |
| 33 | Lane line, 6" (646E10110) | MI | 0.15 | $5,500.00 | $5,789.47 | $75,000 |
| 34 | Center line (646E10200) | MI | 0.03 | $12,000 | $13,895 | $20,000 |
| 35 | Channelizing line, 8" (646E10300) | FT | 241 | $4.00 | $3.47 | $5.00 |
| 36 | Stop line (646E10400) | FT | 23 | $25.00 | $18.53 | $20.00 |
| 37 | Crosswalk line, 12" (646E10510) | FT | 125 | $15.00 | $16.21 | $15.00 |
| 38 | Transverse/diagonal line (646E10600) | FT | 63 | $15.00 | $17.37 | $20.00 |
| 39 | Lane arrow (646E20300) | EACH | 9 | $350.00 | $405.26 | $200.00 |
| 40 | Asphalt concrete for maintaining traffic (614E13000) | CY | 10 | $200.00 | $278.95 | $1,000.00 |
| 41 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 0.30 | $9,000.00 | $18,526 | $17,000 |
| 42 | Work zone dotted line, class I, 6", 740.06, type I (614E24402) | FT | 310 | $3.00 | $2.32 | $6.00 |
| 43 | Work zone arrow, class I, 740.06, type I (614E30400) | EACH | 3 | $300.00 | $578.95 | $300.00 |
| 44 | Water (616E10000) | MGAL | 5 | $1.00 | $7.53 | $1.00 |
| 45 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $20,000 | $18,937 | $16,500 |
| 46 | Maintaining traffic (614E11000) | LS | 1 | $45,000 | $34,837 | $36,000 |
| 47 | Field office, type A (619E16000) | MNTH | 3 | $500.00 | $894.74 | $3,000.00 |
| 48 | Construction layout stakes and surveying (623E10000) | LS | 1 | $15,000 | $14,595 | $10,000 |
| 49 | Mobilization (624E10000) | LS | 1 | $20,000 | $34,992 | $10,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 23, 2026. Compiled by Mirage Metrics.