ODOT letting results, August 11, 2022
17 contracts let by Ohio DOT on August 11, 2022, $32,398,086 in low bids, a median of 4 bidders per contract. On the 17 with an engineer's estimate, the low bid came in under it 11 times; median low bid -3.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 17
- Low bids, total
- $32,398,086
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 220464 | FRA-IR 270-37.00 (FOUR LANE RESURFACING) | FRA | 2 | Shelly & Sands Inc | $10,263,853 | $13,921,222 | +36% | -5.0% | ODOT |
| 220409 | SUM-SR 241/SR 764-07.78/VAR (FOUR LANE RESURFACING) | SUM | 5 | Shelly & Sands Inc | $3,663,806 | $3,710,224 | +1.0% | +11% | ODOT |
| 220463 | CLE-SR 743/SR 749-00.00/00.00 (TWO LANE RESURFACING) | CLE | 2 | Barrett Paving Materials Inc | $3,394,149 | $3,728,527 | +10% | -3.0% | ODOT |
| 220477 | D12-Lighting Optimization NE Ohio (LIGHTING) | District 12 | 5 | Cornerstone Electric Inc | $2,609,230 | $2,822,222 | +8.0% | -42% | ODOT |
| 220472 | SUM-SR 176/SR 303-00.23/00.00 (TWO LANE RESURFACING) | SUM | 6 | Shelly & Sands Inc | $2,381,589 | $2,522,498 | +6.0% | -11% | ODOT |
| 220474 | WAS-SR 7-09.45/09.60/09.78 (BRIDGE REPAIR) | WAS | 4 | Shelly & Sands Inc | $1,815,085 | $2,062,529 | +14% | -15% | ODOT |
| 220475 | D07-/D08-GR FY2023 (GUARDRAIL REBUILDING) | District 7 | 1 | Lake Erie Construction Company | $1,653,550 | +10% | ODOT | ||
| 220467 | MAH-Poland Signal Upgrade (SIGNALIZATION) | MAH | 3 | Cornerstone Electric Inc | $1,184,392 | $1,265,665 | +7.0% | -2.0% | ODOT |
| 220466 | KNO-SR 229-14.80 (MISCELLANEOUS) | KNO | 6 | Mark Haynes Construction Inc | $1,086,486 | $1,134,222 | +4.0% | -8.0% | ODOT |
| 220471 | SUM-CR 17-01.36 (Cleve-Mass) (TWO LANE RESURFACING) | SUM | 5 | Shelly & Sands Inc | $810,244 | $972,198 | +20% | -3.0% | ODOT |
| 220473 | WAR-/CLI-GCS FY2022 (CRACK SEALING) | WAR | 2 | Strawser Construction Inc | $731,232 | $749,701 | +3.0% | +16% | ODOT |
| 220468 | MUS-IR 70-25.90 (SLIDE REPAIR) | MUS | 10 | Shelly & Sands Inc | $642,215 | $653,210 | +2.0% | -28% | ODOT |
| 220470 | SCI-SR 73-11.95 (CHIP SEAL) | SCI | 4 | Shelly Company | $553,272 | $593,298 | +7.0% | +3.0% | ODOT |
| 220461 | ATB-SR 307-07.64/19.87 (BRIDGE REPAIR) | ATB | 5 | Chagrin Valley Paving Inc | $524,101 | $580,622 | +11% | -3.0% | ODOT |
| 220476 | D11-LG-FY2023 (LIGHTING) | District 11 | 1 | Cornerstone Electric Inc | $482,720 | +5.0% | ODOT | ||
| 220462 | ATH-SR 7-00.067 (CULVERT REPLACEMENT) | ATH | 4 | Turn-Key Tunneling Inc | $346,013 | $353,726 | +2.0% | -8.0% | ODOT |
| 220465 | JEF-SR 7-03.49 (CULVERT REPLACEMENT) | JEF | 5 | Axis Civil Construction LLC | $256,150 | $256,343 | 0.0% | +8.0% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.