ODOT contract 15571 bid tabulation
Or224: se 17th ave - se rusk road. Let by Oregon DOT on January 9, 2025, Region 1. 5 bids received.
- Owner
- Oregon DOT
- Letting
- 09 JAN 2025
- Pay items
- 172
- Data through
- 13 AUG 2026
Bidders
| Rank | Total bid | Against the low bid |
|---|---|---|
| 1 | Low | |
| 2 | ||
| 3 | ||
| 4 | ||
| 5 |
Bid tabulation
| Line | Pay item | Unit | Quantity | Rank 1 | Rank 2 | Rank 3 | Rank 4 | Rank 5 |
|---|---|---|---|---|---|---|---|---|
| 1 | Level 3, 1/2 inch ACP (0745-0302000M) | TON | 8,230 | $160.00 | $148.00 | $125.00 | $160.00 | $160.00 |
| 2 | Filling abandoned structures (0490-0117000E) | EACH | 2 | $3,000.00 | $1,800.00 | $9,220.00 | $630.00 | $2,050.00 |
| 3 | 42 inch diameter signal support drilled shaft (0963-0102000F) | LF | 86 | $1,200.00 | $925.00 | $890.00 | $1,010.00 | $1,120.00 |
| 4 | Removal of curbs (0310-0101000F) | LF | 1,586 | $10.00 | $7.00 | $35.00 | $17.00 | $9.00 |
| 5 | Temporary traffic signal, clackamas hwy (OR224) at SE monroe ST (0227-0158000A) | LS | 1 | $25,000 | $25,000 | $20,000 | $22,600 | $36,000 |
| 6 | Radar speed trailer (0222-0167500E) | EACH | 2 | $4,000.00 | $12,950 | $17,700 | $5,650.00 | $17,400 |
| 7 | Temporary plastic drums (0224-0145000E) | EACH | 470 | $40.00 | $65.00 | $70.00 | $57.00 | $65.00 |
| 8 | Traffic signal installation, clackamas hwy (OR224) at monroe (0990-0101000A) | EACH | 1 | $300,000 | $255,000 | $235,000 | $265,600 | $296,000 |
| 9 | Removal of impact attenuator (0310-0105000E) | EACH | 1 | $4,000.00 | $2,400.00 | $11,800 | $1,620.00 | $3,200.00 |
| 10 | Adjusting boxes (0490-0100000E) | EACH | 13 | $200.00 | $275.00 | $551.00 | $49.50 | $650.00 |
| 11 | Removal of surfacings for curb ramp construction (0310-0106101J) | SY | 2,417 | $40.00 | $35.00 | $157.00 | $55.00 | $25.00 |
| 12 | Sediment barrier, type 3 (0280-0115030F) | LF | 100 | $4.00 | $11.00 | $8.10 | $5.40 | $7.50 |
| 13 | Temporary reflective pavement markers (0225-0148000E) | EACH | 50 | $25.00 | $20.00 | $20.00 | $22.50 | $25.00 |
| 14 | Sequential arrow signs (0222-0162000E) | EACH | 6 | $500.00 | $5,000.00 | $8,360.00 | $5,830.00 | $3,900.00 |
| 15 | Replace surface mounted tubular markers (0224-0143000E) | EACH | 6 | $125.00 | $225.00 | $1,560.00 | $57.00 | $235.00 |
| 16 | Temporary flexible pavement markers (0225-0149000E) | EACH | 9,540 | $0.75 | $0.75 | $7.00 | $2.80 | $3.50 |
| 17 | Structural steel maintenance (0560-0109000A) | LB | 70 | $71.43 | $142.86 | $92.86 | $64.29 | $133.00 |
| 18 | 6 inch concrete surfacing (0759-0140000J) | SF | 640 | $30.00 | $24.00 | $14.20 | $17.25 | $19.50 |
| 19 | Concrete islands (0759-0122000J) | SF | 2,577 | $30.00 | $30.00 | $13.68 | $21.00 | $37.25 |
| 20 | Asphalt pavement sawcutting (0310-0119000F) | LF | 3,516 | $10.00 | $5.00 | $5.00 | $4.50 | $8.00 |
| 21 | Aggregate base (0641-0102000M) | TON | 1,385 | $25.00 | $110.00 | $206.00 | $120.00 | $115.00 |
| 22 | General structural concrete, class 3300 (0540-0311000K) | CY | 0.34 | $40,000 | $4,600.00 | $25,000 | $3,490.00 | $12,500 |
| 23 | Guardrail posts (0812-0106000E) | EACH | 268 | $175.00 | $80.00 | $135.00 | $190.00 | $93.75 |
| 24 | Traffic signal modification, clackamas hwy (OR224) at SE 37TH ave (0990-0102000A) | EACH | 1 | $40,000 | $40,000 | $35,000 | $39,600 | $44,100 |
| 25 | Perforated steel square tube anchor sign supports (0930-0117000A) | LB | 1,021 | $14.69 | $11.75 | $10.87 | $12.24 | $13.42 |
| 26 | Signs, wide angle sheeting, sheet aluminum (0940-0205100J) | SF | 106 | $32.00 | $34.00 | $36.00 | $40.75 | $44.00 |
| 27 | Traffic signal modification, clackamas hwy (OR224) at SE harrison ST (0990-0102000A) | EACH | 1 | $70,000 | $70,000 | $63,000 | $71,200 | $79,400 |
| 28 | Stripe removal (0225-0154000F) | LF | 2,868 | $0.87 | $0.90 | $0.85 | $0.95 | $1.10 |
| 29 | Inlet protection, type 3 (0280-0114030E) | EACH | 58 | $35.00 | $125.00 | $108.00 | $62.00 | $100.00 |
| 30 | Concrete manholes, shallow (0470-0105000E) | EACH | 5 | $11,000 | $8,000.00 | $6,500.00 | $7,650.00 | $1,900.00 |
| 31 | Bridge approach slab cold plane pavement removal, 2 inches deep (0503-0103100J) | SY | 520 | $5.00 | $30.00 | $3.40 | $30.75 | $31.00 |
| 32 | Temporary pavement bars (0225-0153200J) | SF | 9,600 | $1.50 | $3.25 | $3.15 | $3.60 | $4.00 |
| 33 | Midwest guardrail system, type 3 (0810-0146100F) | LF | 25 | $85.00 | $85.00 | $65.00 | $89.00 | $99.00 |
| 34 | Compost erosion blanket (0280-0105100J) | SY | 522 | $4.00 | $5.00 | $8.10 | $6.80 | $7.50 |
| 35 | Concrete inlets, type G-1 (0470-0313000E) | EACH | 1 | $6,000.00 | $5,000.00 | $4,033.91 | $2,870.00 | $4,000.00 |
| 36 | Traffic signal modification, clackamas hwy (OR224) at SE rusk RD (0990-0102000A) | EACH | 1 | $30,000 | $30,000 | $23,000 | $26,000 | $29,000 |
| 37 | Traffic signal modification, clackamas hwy (OR224) WB off ramp at SE lake RD (0990-0102000A) | EACH | 1 | $2,000.00 | $5,000.00 | $500.00 | $570.00 | $630.00 |
| 38 | Signs, wide angle sheeting, extruded aluminum (0940-0204100J) | SF | 455 | $40.00 | $42.00 | $40.00 | $45.25 | $49.00 |
| 39 | Core correlation of nuclear gauge readings (0745-0900000E) | EACH | 4 | $3,000.00 | $3,000.00 | $2,900.00 | $1,130.00 | $2,000.00 |
| 40 | Guardrail height conversion, type 2A (0810-0147000E) | EACH | 1 | $3,000.00 | $1,300.00 | $1,500.00 | $1,550.00 | $1,485.00 |
| 41 | Green bicycle lane, preformed thermoplastic film (0868-0100000J) | SF | 140 | $18.00 | $24.00 | $18.00 | $20.25 | $22.25 |
| 42 | Remove and reinstall existing signs (0905-0101000A) | LS | 1 | $3,000.00 | $5,000.00 | $960.00 | $1,080.00 | $1,190.00 |
| 43 | Portable changeable message signs (0222-0164000E) | EACH | 4 | $10,000 | $12,000 | $24,200 | $15,900 | $14,700 |
| 44 | Removal of surfacings (0310-0103000J) | SY | 561 | $45.00 | $22.00 | $108.00 | $55.00 | $17.00 |
| 45 | Traffic signal modification, clackamas hwy (OR224) at SE oak ST (0990-0102000A) | EACH | 1 | $90,000 | $85,000 | $78,000 | $88,100 | $98,300 |
| 46 | Signs, standard sheeting, sheet aluminum (0940-0202000J) | SF | 421 | $30.00 | $32.00 | $31.00 | $35.00 | $38.00 |
| 47 | Repair temporary impact attenuator, truck mounted (0226-0141400E) | EACH | 10 | $0.01 | $1.00 | $1.00 | $1,700.00 | $12,500 |
| 48 | Lawn seeding (1030-0138000J) | SY | 522 | $3.50 | $4.00 | $4.70 | $4.00 | $4.30 |
| 49 | Longitudinal pavement markings - paint (0860-0200000F) | LF | 400 | $6.00 | $6.00 | $6.00 | $6.80 | $7.50 |
| 50 | Bridge identification markers (0842-0401000E) | EACH | 4 | $500.00 | $275.00 | $650.00 | $230.00 | $375.00 |
| 51 | Extra for hand dug guardrail post holes (0810-0145000E) | EACH | 20 | $200.00 | $350.00 | $250.00 | $200.00 | $422.00 |
| 52 | Cold plane pavement removal, 2 inches deep (0620-0120000J) | SY | 18,408 | $3.50 | $6.00 | $4.50 | $6.70 | $3.70 |
| 53 | General structural concrete, class 3300 (0540-0311000K) | CY | 0.29 | $40,000 | $5,000.00 | $25,000 | $71,000 | $12,500 |
| 54 | Adjusting guardrail (0812-0101000F) | LF | 3,350 | $7.00 | $6.50 | $12.00 | $6.80 | $7.75 |
| 55 | Emulsified asphalt for tack coat (0730-0100000M) | TON | 50 | $0.01 | $1.00 | $0.02 | $1.10 | $780.00 |
| 56 | Traffic control supervisor (0223-0169000E) | EACH | 381 | $0.01 | $950.00 | $700.00 | $250.00 | $500.00 |
| 57 | Mainline video inspection (0415-0100000F) | LF | 850 | $15.00 | $25.00 | $29.00 | $15.50 | $35.00 |
| 58 | Reinforcement, grade 60 (0530-0104000O) | LB | 159 | $7.00 | $12.00 | $25.00 | $18.00 | $31.00 |
| 59 | Pollution control plan (0290-0100000A) | LS | 1 | $2,000.00 | $2,000.00 | $15,000 | $1,300.00 | $1,250.00 |
| 60 | Temporary traffic signal, clackamas hwy (OR224) SB off ramp at SE lake RD (0227-0158000A) | LS | 1 | $5,000.00 | $10,000 | $2,200.00 | $2,490.00 | $10,000 |
| 61 | Temporary traffic signal, clackamas hwy (OR224) at SE rusk RD (0227-0158000A) | LS | 1 | $5,000.00 | $8,000.00 | $2,200.00 | $2,490.00 | $10,000 |
| 62 | Thermoplastic, extruded, surface, profiled (0865-0116600F) | LF | 53,430 | $1.85 | $2.10 | $1.85 | $2.10 | $2.30 |
| 63 | Securing concrete barrier (0820-0400000F) | LF | 12.50 | $55.00 | $135.00 | $125.00 | $140.00 | $155.00 |
| 64 | Railroad flagger services (0223-0170000E) | EACH | 22 | $250.00 | $2,000.00 | $3,600.00 | $1,700.00 | $1,800.00 |
| 65 | 12 inch storm sewer pipe, 5 FT depth (0445-035012AF) | LF | 341 | $250.00 | $300.00 | $173.00 | $250.00 | $240.00 |
| 66 | Cold plane pavement removal, 4 - 5 inches deep (0620-0114000J) | SY | 1,347 | $3.50 | $11.00 | $30.00 | $9.60 | $15.00 |
| 67 | Removal of guardrail (0310-0113000A) | LF | 1,925 | $6.23 | $4.68 | $5.19 | $5.87 | $5.19 |
| 68 | Wood sign posts (0910-0100000K) | FBM | 188 | $20.00 | $22.00 | $26.00 | $29.50 | $32.25 |
| 69 | Concrete driveways (0759-0126000J) | SF | 468 | $30.00 | $30.00 | $15.61 | $21.00 | $18.70 |
| 70 | Cold plane pavement removal, 4 inches deep (0620-0123000J) | SY | 22,286 | $3.50 | $8.50 | $6.17 | $8.50 | $7.10 |
| 71 | Concrete inlets, type G-2 (0470-0315000E) | EACH | 15 | $6,000.00 | $5,400.00 | $6,210.00 | $3,060.00 | $4,225.00 |
| 72 | Lead compliance plan (0294-0500000A) | LS | 1 | $2,000.00 | $3,000.00 | $9,500.00 | $1,080.00 | $1,250.00 |
| 73 | Removal of inlets (0310-0104000E) | EACH | 4 | $1,000.00 | $900.00 | $5,600.00 | $1,340.00 | $700.00 |
| 74 | Erosion and sediment control manager (0280-0110000A) | LS | 1 | $3,000.00 | $5,000.00 | $15,000 | $8,310.00 | $172,000 |
| 75 | Connection to existing structures (0490-0104000E) | EACH | 17 | $1,750.00 | $2,750.00 | $2,800.00 | $1,320.00 | $2,300.00 |
| 76 | Temporary traffic signal, clackamas hwy (OR224) at SE freeman WY (0227-0158000A) | LS | 1 | $5,000.00 | $8,000.00 | $2,200.00 | $2,490.00 | $10,000 |
| 77 | Bark mulch (1040-0190000K) | CY | 2.40 | $350.00 | $75.00 | $364.00 | $310.00 | $335.00 |
| 78 | Remove existing signs (0905-0100000A) | LS | 1 | $10,000 | $10,000 | $425.00 | $480.00 | $525.00 |
| 79 | Traffic signal modification, clackamas hwy (OR224) at SE freeman WY (0990-0102000A) | EACH | 1 | $80,000 | $75,000 | $70,000 | $79,100 | $88,200 |
| 80 | Traffic signal modification, clackamas hwy (OR224) at SE 17TH ave (0990-0102000A) | EACH | 1 | $20,000 | $20,000 | $13,800 | $15,600 | $17,395 |
| 81 | Signs, standard sheeting, extruded aluminum (0940-0201000J) | SF | 130 | $45.00 | $50.00 | $38.00 | $43.00 | $47.00 |
| 82 | Bar removal (0225-0156000J) | SF | 1,692 | $4.00 | $7.50 | $7.50 | $8.50 | $9.50 |
| 83 | Removal of pipes (0310-0100000F) | LF | 93 | $110.00 | $45.00 | $105.00 | $30.00 | $70.00 |
| 84 | Repair temporary impact attenuator, narrow site system (0226-0141300E) | EACH | 1 | $0.01 | $4,200.00 | $4,000.00 | $4,520.00 | $5,000.00 |
| 85 | 4 inch concrete surfacing (0759-0138000J) | SF | 302 | $25.00 | $14.00 | $13.45 | $16.00 | $17.00 |
| 86 | Cold plane pavement removal, 4.5 inches deep (0620-0124000J) | SY | 15,553 | $3.50 | $9.00 | $7.35 | $9.00 | $8.10 |
| 87 | Level 4, 1/2 inch ACP (0745-0402000M) | TON | 7,906 | $140.00 | $143.00 | $135.00 | $150.00 | $169.00 |
| 88 | Delineators, type 1 (0840-0100000E) | EACH | 138 | $80.00 | $85.00 | $130.00 | $57.00 | $136.00 |
| 89 | Truncated domes on new surfaces (0759-0510000J) | SF | 681 | $60.00 | $35.00 | $33.12 | $22.50 | $40.00 |
| 90 | Temporary barrier (0226-0126100F) | LF | 300 | $0.01 | $40.00 | $29.30 | $33.00 | $36.50 |
| 91 | Temporary impact attenuator, truck mounted (0226-0138000E) | EACH | 5 | $2,000.00 | $25,000 | $45,800 | $45,000 | $12,500 |
| 92 | Pavement legend, type B-HS: arrows (0867-0103100E) | EACH | 60 | $400.00 | $425.00 | $400.00 | $450.00 | $495.00 |
| 93 | Mono-directional white type iar markers (0855-0101100E) | EACH | 792 | $8.50 | $8.50 | $8.50 | $9.60 | $10.00 |
| 94 | Extra for new curb ramps (0759-0154100E) | EACH | 55 | $1,500.00 | $2,200.00 | $1,258.01 | $980.00 | $1,500.00 |
| 95 | Inlet protection, type 4 (0280-0114040E) | EACH | 5 | $50.00 | $125.00 | $175.00 | $62.00 | $162.00 |
| 96 | Concrete curbs, curb and gutter (0759-0103000F) | LF | 1,981 | $40.00 | $72.00 | $56.28 | $70.00 | $55.80 |
| 97 | Clearing and grubbing (0320-0100000R) | ACRE | 0.20 | $5,000.00 | $50,000 | $324,000 | $22,100 | $24,000 |
| 98 | Extra for manholes over existing sewers (0490-0123000E) | EACH | 3 | $8,000.00 | $4,500.00 | $5,000.00 | $3,000.00 | $2,050.00 |
| 99 | Precompressed foam silicone joint seal (0585-0215000A) | LF | 163 | $92.02 | $88.96 | $85.28 | $214.11 | $105.52 |
| 100 | PG 64-22ER asphalt in level 3 1/2 inch ACP (0745-0620100M) | TON | 496 | $0.01 | $1.00 | $0.01 | $1.10 | $1.00 |
| 101 | Guardrail terminals, non-flared (0810-0129000E) | EACH | 3 | $6,000.00 | $4,000.00 | $4,650.00 | $5,030.00 | $4,460.00 |
| 102 | Cold plane pavement removal, 1 - 2 inches deep (0620-0111000J) | SY | 1,600 | $3.50 | $7.00 | $22.80 | $7.10 | $7.00 |
| 103 | Adjusting inlets (0490-0105000E) | EACH | 20 | $400.00 | $2,000.00 | $1,040.00 | $890.00 | $1,170.00 |
| 104 | Commercial asphalt concrete pavement (0740-0100000M) | TON | 1 | $750.00 | $500.00 | $0.01 | $570.00 | $1,160.00 |
| 105 | Reinforcement, grade 60 (0530-0104000O) | LB | 161 | $7.00 | $12.00 | $25.00 | $20.00 | $31.00 |
| 106 | Removal of electrical systems (0950-0101000A) | LS | 1 | $10,000 | $20,000 | $3,500.00 | $3,960.00 | $4,400.00 |
| 107 | Temporary walks (0228-0167680J) | SF | 4,100 | $10.00 | $10.00 | $12.50 | $16.00 | $8.00 |
| 108 | Concrete barrier (0820-0100000F) | LF | 12.50 | $200.00 | $160.00 | $150.00 | $170.00 | $186.00 |
| 109 | Guardrail terminals, downstream anchor terminal (0810-0132200E) | EACH | 2 | $3,000.00 | $2,100.00 | $1,500.00 | $2,540.00 | $2,420.00 |
| 110 | Pavement legend, type B-HS: "only" (0867-0107100E) | EACH | 2 | $1,400.00 | $1,500.00 | $1,400.00 | $1,580.00 | $1,735.00 |
| 111 | Perforated steel square tube slip base sign supports (0930-0114000A) | LB | 2,240 | $13.39 | $15.63 | $10.18 | $11.52 | $12.63 |
| 112 | Cold plane pavement removal, 3 inches deep (0620-0122000J) | SY | 4,510 | $3.50 | $8.00 | $13.30 | $8.50 | $6.50 |
| 113 | Precompressed foam silicone joint seal (0585-0215000A) | LF | 155 | $96.77 | $93.55 | $85.16 | $174.19 | $105.81 |
| 114 | Temporary signs (0222-0102000J) | SF | 2,900 | $25.00 | $28.00 | $41.00 | $20.00 | $37.00 |
| 115 | Concrete curbs, modified (0759-0102000F) | LF | 20 | $110.00 | $75.00 | $50.95 | $45.00 | $62.00 |
| 116 | Pavement bar, type B-HS (0867-0145100J) | SF | 7,130 | $14.95 | $15.00 | $15.00 | $17.00 | $18.50 |
| 117 | Drainage curbs (0480-0100000F) | LF | 1,557 | $25.00 | $35.00 | $25.60 | $29.00 | $31.00 |
| 118 | Removal of concrete barrier (0310-0200000F) | LF | 12.50 | $100.00 | $210.00 | $945.00 | $40.00 | $38.00 |
| 119 | Pavement legend, type B-HS: shared lane marking (0867-0174000E) | EACH | 2 | $375.00 | $400.00 | $375.00 | $420.00 | $465.00 |
| 120 | Temporary traffic signal, clackamas hwy (OR224) at SE harrison ST (0227-0158000A) | LS | 1 | $5,000.00 | $8,000.00 | $2,200.00 | $2,490.00 | $10,000 |
| 121 | Temporary barricades, type II (0224-0104000E) | EACH | 70 | $50.00 | $75.00 | $67.00 | $57.00 | $50.00 |
| 122 | Flagger station lighting (0223-0168100E) | EACH | 5 | $500.00 | $7,500.00 | $3,200.00 | $1,130.00 | $2,500.00 |
| 123 | Legend removal (0225-0155100J) | SF | 214 | $4.00 | $8.00 | $7.50 | $8.50 | $9.50 |
| 124 | Bridge approach slab cold plane pavement removal, 2 inches deep (0503-0103100J) | SY | 506 | $5.00 | $30.00 | $3.40 | $30.75 | $31.00 |
| 125 | Impact attenuator, type K (0830-0124000E) | EACH | 1 | $75,000 | $68,000 | $54,500 | $79,100 | $83,175 |
| 126 | Contaminated soil disposal (0294-0200010M) | TON | 231 | $25.00 | $125.00 | $220.00 | $210.00 | $125.00 |
| 127 | Sediment barrier, type 8 (0280-0115080F) | LF | 280 | $5.00 | $9.00 | $10.80 | $3.50 | $10.00 |
| 128 | Bridge removal work (0501-0100000A) | SF | 11 | $909.09 | $1,090.91 | $6,818.18 | $681.82 | $2,818.18 |
| 129 | Concrete walks (0759-0128000J) | SF | 13,694 | $21.00 | $14.00 | $11.46 | $15.00 | $12.50 |
| 130 | Guardrail transition (0810-0126000E) | EACH | 5 | $6,000.00 | $4,000.00 | $4,850.00 | $5,420.00 | $4,715.00 |
| 131 | Pavement legend, type B-HS: bicycle lane stencil (0867-0131000E) | EACH | 6 | $375.00 | $400.00 | $375.00 | $420.00 | $465.00 |
| 132 | Sign support footings (0920-0100000A) | CY | 4.30 | $5,813.95 | $5,813.95 | $10,651 | $12,047 | $13,221 |
| 133 | Traffic signal modification, clackamas hwy (OR224) EB off ramp at SE lake RD (0990-0102000A) | EACH | 1 | $25,000 | $25,000 | $18,500 | $20,900 | $23,000 |
| 134 | Guardrail connections (0810-0128000E) | EACH | 17 | $1,000.00 | $900.00 | $500.00 | $650.00 | $1,030.00 |
| 135 | Crosswalk closure supports (0902-0101000E) | EACH | 3 | $2,000.00 | $1,350.00 | $1,350.00 | $1,530.00 | $1,675.00 |
| 136 | PG 70-22ER asphalt in level 4 1/2 inch ACP (0745-0640100M) | TON | 477 | $0.01 | $1.00 | $0.01 | $1.10 | $1.00 |
| 137 | Structural steel maintenance (0560-0109000A) | LB | 70 | $71.43 | $142.86 | $92.86 | $85.71 | $133.00 |
| 138 | 12 inch ductile iron pipe, 5 FT depth (0445-060012AF) | LF | 509 | $350.00 | $365.00 | $182.00 | $250.00 | $235.00 |
| 139 | Subgrade geotextile (0350-0105000J) | SY | 350 | $5.00 | $1.50 | $11.60 | $1.50 | $3.70 |
| 140 | Flaggers (0223-0168000T) | HR | 1,000 | $82.00 | $78.00 | $70.50 | $90.00 | $90.00 |
| 141 | Control joint (0585-0300000A) | LF | 151 | $59.60 | $52.98 | $51.32 | $178.81 | $63.74 |
| 142 | Concrete inlets, type CG-3 (0470-0309000E) | EACH | 2 | $6,000.00 | $5,000.00 | $5,667.82 | $3,500.00 | $3,900.00 |
| 143 | Removal of structures and obstructions (0310-0106000A) | LS | 1 | $350,000 | $75,000 | $95,000 | $570.00 | $225,000 |
| 144 | Straw bale (0280-0119000E) | EACH | 5 | $150.00 | $65.00 | $416.00 | $12.50 | $130.00 |
| 145 | Temporary pavement legends (0225-0153100E) | EACH | 76 | $75.00 | $150.00 | $150.00 | $170.00 | $187.00 |
| 146 | Temporary barricades, type III (0224-0105000E) | EACH | 30 | $50.00 | $225.00 | $166.00 | $57.00 | $170.00 |
| 147 | Temporary striping (0225-0153000F) | LF | 50,498 | $0.17 | $0.17 | $0.16 | $0.20 | $0.20 |
| 148 | Removal of walks and driveways (0310-0102000J) | SY | 270 | $50.00 | $36.00 | $125.00 | $55.00 | $18.00 |
| 149 | Concrete inlets, type CG-2 (0470-0307000E) | EACH | 1 | $6,000.00 | $5,500.00 | $5,083.91 | $3,410.00 | $3,750.00 |
| 150 | Moving temporary impact attenuators, narrow site system (0226-0137000E) | EACH | 2 | $0.01 | $1,750.00 | $1,500.00 | $1,700.00 | $1,900.00 |
| 151 | Temporary impact attenuator, narrow site system (0226-0134000E) | EACH | 2 | $0.01 | $4,000.00 | $3,500.00 | $3,960.00 | $4,400.00 |
| 152 | Concrete curbs, standard curb (0759-0110000F) | LF | 354 | $40.00 | $65.00 | $39.06 | $60.00 | $43.50 |
| 153 | Concrete repair (1999-9Z90000J) | SF | 27.13 | $200.00 | $250.00 | $450.00 | $630.00 | $3,150.00 |
| 154 | Concrete curbs, low profile mountable curb (0759-0106000F) | LF | 91 | $45.00 | $75.00 | $41.24 | $45.00 | $49.70 |
| 155 | Control joint (0585-0300000A) | LF | 159 | $56.60 | $55.35 | $51.26 | $78.62 | $64.15 |
| 156 | Remove and reinstall existing concrete barrier (0820-0500000F) | LF | 100 | $35.00 | $75.00 | $70.00 | $120.00 | $87.00 |
| 157 | Bridge removal work (0501-0100000A) | SF | 9.70 | $1,237.11 | $1,237.11 | $7,731.96 | $515.46 | $3,195.88 |
| 158 | Inlet protection, type 11 (0280-0114110E) | EACH | 3 | $65.00 | $225.00 | $256.00 | $62.00 | $236.00 |
| 159 | Continuous sinusoidal rumble strips (0857-0103000L) | MI | 0.68 | $2,650.00 | $2,950.00 | $2,650.00 | $2,990.00 | $3,280.00 |
| 160 | Signs, standard sheeting, plywood (0940-0203000J) | SF | 246 | $30.00 | $32.00 | $33.00 | $37.25 | $40.00 |
| 161 | Cold plane pavement removal, 6 inches deep (0620-0125000J) | SY | 4,257 | $3.50 | $12.00 | $15.10 | $11.50 | $12.80 |
| 162 | Guardrail blocks (0812-0108000E) | EACH | 268 | $60.00 | $30.00 | $25.00 | $57.00 | $33.50 |
| 163 | Bridge approach slab cold plane pavement removal, 2 inches deep (0503-0103100J) | SY | 106 | $5.00 | $140.00 | $44.60 | $80.00 | $66.00 |
| 164 | Midwest guardrail system, type 2A (0810-0146100F) | LF | 1,575 | $45.00 | $35.00 | $30.00 | $47.50 | $40.25 |
| 165 | Curb marking, paint (0869-0200000F) | LF | 40 | $20.00 | $10.00 | $8.00 | $9.00 | $10.00 |
| 166 | Mobile barrier (0226-0148000U) | DAY | 2 | $0.01 | $10,000 | $25,000 | $22,600 | $18,000 |
| 167 | Bicycle channelizing devices (0228-0141950F) | LF | 500 | $60.00 | $50.00 | $12.50 | $20.00 | $36.00 |
| 168 | BI-directional yellow type iar markers (0855-0103100E) | EACH | 598 | $8.50 | $8.50 | $8.50 | $9.60 | $10.00 |
| 169 | Pedestrian channelizing devices (0228-0141600F) | LF | 1,000 | $60.00 | $34.00 | $10.50 | $20.00 | $36.00 |
| 170 | Gap pattern sinusoidal rumble strips (0857-0104000L) | MI | 1.16 | $2,650.00 | $2,950.00 | $2,650.00 | $2,990.00 | $3,280.00 |
| 171 | Temporary curb ramp, parallel (0228-0167670E) | EACH | 21 | $500.00 | $2,500.00 | $1,500.00 | $600.00 | $3,320.00 |
| 172 | Minor adjustment of manholes (0490-0120000E) | EACH | 10 | $1,000.00 | $2,000.00 | $2,980.00 | $1,020.00 | $1,790.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Bid Data Program yearly workbooks. ODOT publishes rank and unit price only: no bidder names and no bid totals, so these bids cannot be checked against a total and Oregon is left out of the competitor views.
Every contract let that day: ODOT letting of January 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.