6" yellow solid lines(PVT.edge lines) thermo- 90 mil., SCDOT 6271076

Low bidders on SCDOT contracts carried a median of $0.90 per LF for this item, over the 24 months to 13 OCT 2026, across 66 low bids. Half of all 188 bids fell between $0.80 and $1.00.

Owner
South Carolina DOT
Item
6271076
Unit
LF
Data through
13 OCT 2026

SCDOT prints this item as “6" YELLOW SOLID LINES(PVT.EDGE LINES) THERMO- 90 MIL.”.

$0.90Low bidder's median, per LF
$0.90Median of all bids, per LF
66Contracts in the window

By year of letting

6" yellow solid lines(PVT.edge lines) thermo- 90 mil., SCDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20224242$0.76125$0.79
20232323$1.0060$1.08
20241111$0.9033$0.92
20253232$0.9091$0.91
20263030$0.8585$0.88

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
District 215$0.6541$0.66
District 511$0.9034$0.90
District 48$0.8024$0.84
District 610$0.9024$0.90
District 79$0.9524$0.90
District 37$0.9522$0.95
District 14$0.9712$0.96
6" yellow solid lines(PVT.edge lines) thermo- 90 mil., SCDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Quantity (LF)Low bidsLow-bid median
183 to 15,45616$0.93
15,700 to 35,31017$0.96
36,749 to 82,80016$0.92
90,547 to 414,34317$0.80
6" yellow solid lines(PVT.edge lines) thermo- 90 mil., SCDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Palmetto Corp. of Conway7063 (90%)
C.R. Jackson, Inc.4437 (84%)
King Asphalt, Inc.4717 (36%)
Banks Construction Company1715 (88%)
Lynches River Contracting, Inc.1413 (93%)
Coastal Asphalt, LLC1311 (85%)
6" yellow solid lines(PVT.edge lines) thermo- 90 mil., SCDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
13 OCT 20260276070District 7172,350$0.80$0.822C.R. Jackson, Inc.SCDOT
13 OCT 20264276560District 344,656$0.85$0.904Palmetto Corp. of ConwaySCDOT
13 OCT 20264676540District 4109,718$0.95$0.952King Asphalt, Inc.SCDOT
13 OCT 20265578320District 578,313$0.93$0.932Palmetto Corp. of ConwaySCDOT
13 OCT 20268876550District 2, District 364,565$0.85$0.904Palmetto Corp. of ConwaySCDOT
13 OCT 20268876840District 1, District 7113,353$0.80$0.893C.R. Jackson, Inc.SCDOT
09 SEP 20264376690District 125,351$0.96$0.963C.R. Jackson, Inc.SCDOT
09 SEP 20265777540District 73,700$1.10$1.052Blythe Construction, Inc.SCDOT
09 SEP 20265777760District 713,250$0.85$0.853C.R. Jackson, Inc.SCDOT
11 AUG 20268876590District 113,458$0.95$0.953Blythe Construction, Inc.SCDOT
11 AUG 20268876600District 720,903$0.95$0.905Blythe Construction, Inc.SCDOT
09 JUN 20262163100District 5310$1.10$1.055Cherokee, Inc.SCDOT
09 JUN 20265177180District 2414,343$0.47$0.564Alpha Space Control, LLCSCDOT
09 JUN 20265277190District 2226,410$0.54$0.553TRP Construction Group, LLCSCDOT
09 JUN 20265377200District 2325,466$0.62$0.662TRP Construction Group, LLCSCDOT
Latest SCDOT contracts carrying 6" yellow solid lines(PVT.edge lines) thermo- 90 mil.

Filter this item by your own quantity, district and period, or check your price against it, in the SCDOT explorer.

How these prices were read

SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are SCDOT's own: this item is compared with SCDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the SCDOT letting of 13 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy