SCDOT contract 0864370 bid tabulation
Safety Improvements - SC 6. Let by South Carolina DOT on December 9, 2025, Berkeley, District 6. 3 bids received; low bid $9,852,965 by L. Dean Weaver Company LLC.
- Owner
- South Carolina DOT
- Letting
- 09 DEC 2025
- Pay items
- 80
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | L. Dean Weaver Company LLC | $9,852,965 | Low |
| 2 | Banks Construction Company | $12,400,157 | +26% |
| 3 | Sanders Brothers Construction Company, | $13,286,824 | +35% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. L. Dean Weaver Company LLC | 2. Banks Construction Company | 3. Sanders Brothers Construction Company, |
|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $385,390 | $550,000 | $600,000 |
| 0020 | Mobilization - subcontractor (1031100) | LS | 1 | $59,000 | $150,000 | $550,000 |
| 0030 | Bonds and insurance (1032010) | LS | 1 | $65,000 | $145,000 | $200,000 |
| 0040 | Construction stakes, lines & grades (1050800) | EACH | 1 | $110,000 | $243,300 | $125,000 |
| 0050 | Utility staking (1052001) | LS | 1 | $5,083.92 | $25,000 | $90,000 |
| 0060 | CPM progress schedule (1080300) | LS | 1 | $6,500.00 | $20,000 | $25,000 |
| 0070 | Clearing & grubbing within right of way (2011001) | ACRE | 25 | $16,900 | $16,000 | $16,000 |
| 0080 | Removal of exist. guardrail (2027801) | LF | 538 | $2.75 | $1.00 | $2.20 |
| 0090 | Unclassified excavation (2031000) | CY | 24,005 | $27.65 | $25.00 | $27.50 |
| 0100 | Borrow excavation (2033000) | CY | 3,940 | $36.00 | $70.00 | $73.60 |
| 0110 | Muck excavation (2034000) | CY | 2,190 | $23.30 | $20.00 | $68.75 |
| 0120 | Excavation for shoulder paving (2036000) | STA | 742 | $66.50 | $170.00 | $175.00 |
| 0130 | Hauling of excavated shoulder material (2072000) | STA | 742 | $95.60 | $90.00 | $150.00 |
| 0140 | Fine grading (2081001) | SY | 36,213 | $2.55 | $1.00 | $6.50 |
| 0150 | Liquid asphalt binder PG64-22 (4011004) | TON | 1,605 | $625.00 | $640.00 | $685.00 |
| 0160 | Full depth asph. pav. patching 8" unif (4012080) | SY | 3,613 | $68.45 | $80.00 | $75.00 |
| 0170 | Milling existing asphalt pavement 1.0" (4013110) | SY | 180,659 | $1.20 | $1.25 | $1.55 |
| 0180 | Asphalt base course - type A (4020310) | TON | 8,780 | $92.00 | $96.00 | $106.50 |
| 0190 | Asphalt intermediate course type B (4030320) | TON | 2,470 | $99.85 | $115.00 | $155.00 |
| 0200 | Asphalt surface course type B (4040320) | TON | 20,410 | $84.00 | $93.00 | $100.00 |
| 0210 | Asphalt surface course type C (4040340) | TON | 390 | $84.00 | $175.00 | $150.00 |
| 0220 | Driveway paving-surface type C (4047220) | TON | 1,320 | $218.00 | $275.00 | $215.00 |
| 0230 | Traffic control (6011000) | LS | 1 | $507,490 | $1,100,000 | $950,000 |
| 0240 | Permanent construction signs (ground mounted) (6051120) | SF | 1,064 | $6.00 | $7.00 | $6.55 |
| 0241 | 6" white broken lines -(gaps excluded)-fast dry paint (6240007) | LF | 320 | $0.15 | $0.15 | $0.17 |
| 0242 | 6" white solid lines (PVT. edge lines)-fast dry paint (6240012) | LF | 467,000 | $0.15 | $0.15 | $0.17 |
| 0243 | 24" white solid lines (stop/diagonal lines)-fast dry paint (6240025) | LF | 300 | $0.50 | $0.50 | $0.55 |
| 0244 | 6"yellow solid line(PVT.edge&no passing zone)-fast dry paint (6240111) | LF | 13,000 | $0.25 | $0.25 | $0.28 |
| 0245 | 24" yellow diagonal lines - fast dry paint (6240115) | LF | 2,160 | $1.00 | $1.00 | $1.10 |
| 0250 | 6" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271007) | LF | 160 | $1.50 | $1.50 | $1.65 |
| 0260 | 6" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271012) | LF | 233,500 | $0.80 | $0.80 | $0.88 |
| 0270 | 24" white solid lines (stop/diag lines)-thermo.-125 mil (6271025) | LF | 150 | $15.00 | $15.00 | $16.50 |
| 0280 | 6" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271076) | LF | 6,500 | $0.95 | $0.95 | $1.05 |
| 0290 | 24" yellow solid lines - thermoplastic - 125 mil. (6271080) | LF | 1,080 | $7.50 | $7.50 | $8.25 |
| 0291 | Evaluation of pavement marking retroreflectivity (6290001) | LS | 1 | $12,500 | $12,500 | $13,750 |
| 0300 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 724 | $6.50 | $6.50 | $7.15 |
| 0310 | Milled-in rumble strip (6321000) | MI | 30 | $475.00 | $500.00 | $750.00 |
| 0320 | Flat sheet, type III, fixed SZ. & MSG. sign (6510105) | SF | 435 | $24.00 | $18.00 | $26.40 |
| 0330 | Flat sheet,type-VIII,IX, or XI, fluor fixed size & MSG. (6510109) | SF | 160 | $28.00 | $22.00 | $30.80 |
| 0340 | U-section post for sign supports - 3P (6531210) | LF | 1,854 | $7.25 | $14.00 | $7.98 |
| 0350 | Reflective sign post panels (6531500) | LF | 107 | $7.35 | $11.00 | $8.09 |
| 0360 | 15" RC pipe cul.-class III (7141112) | LF | 96 | $73.40 | $200.00 | $132.00 |
| 0370 | 18" RC pipe cul.-class III (7141113) | LF | 5,404 | $83.95 | $200.00 | $126.50 |
| 0380 | 24" RC pipe cul.-class III (7141114) | LF | 2,448 | $118.00 | $180.00 | $148.50 |
| 0390 | 30" RC pipe cul.-class III (7141115) | LF | 1,476 | $165.00 | $220.00 | $170.50 |
| 0400 | 36" RC pipe cul.-class III (7141116) | LF | 88 | $235.00 | $330.00 | $258.50 |
| 0410 | 42" RC pipe cul.-class III (7141117) | LF | 20 | $285.00 | $560.00 | $330.00 |
| 0420 | 60" RC pipe cul.-class III (714111A) | LF | 56 | $545.00 | $800.00 | $489.50 |
| 0430 | 15" R. C. pipe cul. beveled end sectn-CL 3 (7142512) | EACH | 12 | $585.00 | $1,050.00 | $1,155.00 |
| 0440 | 18" R. C. pipe cul. beveled end sectn-CL 3 (7142513) | EACH | 245 | $690.00 | $1,100.00 | $1,265.00 |
| 0450 | 24" R. C. pipe cul. beveled end sectn-CL 3 (7142514) | EACH | 31 | $900.00 | $1,150.00 | $1,595.00 |
| 0460 | 30" R. C. pipe cul. beveled end sectn-CL 3 (7142515) | EACH | 8 | $1,115.00 | $1,400.00 | $2,090.00 |
| 0470 | 36" R. C. pipe cul. beveled end sectn-CL 3 (7142516) | EACH | 5 | $1,700.00 | $2,200.00 | $2,860.00 |
| 0480 | 42" R. C. pipe cul. beveled end sectn-CL 3 (7142517) | EACH | 2 | $2,550.00 | $3,300.00 | $3,960.00 |
| 0490 | 60" R. C. pipe cul. flared end sectn -CL 3 (7142539) | EACH | 1 | $4,040.00 | $6,200.00 | $6,820.00 |
| 0500 | Drop inlet (24" X 24") with standard 4' X 4' box (7192011) | EACH | 15 | $7,775.00 | $6,000.00 | $6,380.00 |
| 0510 | 24" X 24" junction box (7192205) | EACH | 3 | $5,300.00 | $7,000.00 | $5,610.00 |
| 0520 | Beveling of pipe end (7199100) | EACH | 180 | $265.00 | $450.00 | $495.00 |
| 0530 | Rip-rap (class B) (8041020) | TON | 65 | $205.00 | $275.00 | $148.50 |
| 0540 | Geotextile for erosion control under riprap(class 2)type C (8048210) | SY | 200 | $7.50 | $10.00 | $3.03 |
| 0550 | MT3 leading end treatment TL3 (8051151) | EACH | 22 | $3,465.00 | $3,300.00 | $3,410.00 |
| 0560 | MT2 leading end treatment TL2 (8051155) | EACH | 4 | $3,125.00 | $3,200.00 | $3,190.00 |
| 0570 | MGS3CS GR compressed shoulder (8052150) | LF | 1,675 | $35.00 | $25.00 | $33.00 |
| 0580 | Right of way marker(rebar and cap) (8091010) | EACH | 67 | $150.00 | $140.00 | $250.00 |
| 0590 | Right of way plat (8091050) | LS | 1 | $5,000.00 | $3,750.00 | $15,000 |
| 0600 | Permanent cover (8100100) | ACRE | 29 | $1,400.00 | $1,400.00 | $1,538.58 |
| 0610 | Temporary cover (8100200) | ACRE | 15 | $900.00 | $900.00 | $971.28 |
| 0620 | Compost (8101105) | CY | 7,938 | $5.00 | $5.00 | $7.70 |
| 0630 | Straw or hay mulch with tackifier (8101110) | ACRE | 53 | $1,400.00 | $1,389.00 | $3,067.90 |
| 0640 | Fertilizer (nitrogen) (8104005) | LB | 2,940 | $1.94 | $1.94 | $2.15 |
| 0650 | Fertilizer (phosphoric acid) (8104010) | LB | 2,940 | $1.94 | $1.94 | $2.15 |
| 0660 | Fertilizer (potash) (8104015) | LB | 2,940 | $1.94 | $1.94 | $2.15 |
| 0670 | Agricultural granular lime (8105005) | LB | 58,800 | $1.50 | $1.50 | $2.15 |
| 0680 | Selective watering (8109050) | GAL | 271,500 | $0.10 | $0.10 | $0.11 |
| 0690 | Mowing (8109901) | ACRE | 88 | $425.00 | $411.00 | $452.10 |
| 0700 | Temporary erosion control blanket (ecb) (8151110) | MSY | 37.73 | $2,230.00 | $2,246.00 | $2,470.60 |
| 0710 | Sediment tubes for ditch checks (8152007) | LF | 5,208 | $10.65 | $10.65 | $11.72 |
| 0720 | Silt fence (8153000) | LF | 20,419 | $2.85 | $3.85 | $4.24 |
| 0730 | Replace/repair silt fence (8153090) | LF | 2,042 | $3.60 | $3.64 | $4.00 |
| 0740 | Stabilized construction entrance (8156490) | SY | 5,500 | $25.00 | $8.00 | $19.25 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of December 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.