SCDOT contract 0962450 bid tabulation
SC 172 (Bull Swamp Rd) Bridge Replacement over Caw Caw Swamp. Let by South Carolina DOT on December 9, 2025, Calhoun, District 7. 6 bids received; low bid $2,685,000 by Lowcountry Sitework, LLC.
- Owner
- South Carolina DOT
- Letting
- 09 DEC 2025
- Pay items
- 66
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Lowcountry Sitework, LLC | $2,685,000 | Low |
| 2 | Dellinger, Inc. | $2,768,438 | +3.0% |
| 3 | Aos Specialty Contractors, Inc. | $2,770,567 | +3.0% |
| 4 | United Infrastructure Group, Inc. | $2,777,622 | +3.0% |
| 5 | Dane Construction, LLC | $2,816,541 | +5.0% |
| 6 | Coogler Construction, Inc. | $2,829,917 | +5.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lowcountry Sitework, LLC | 2. Dellinger, Inc. | 3. Aos Specialty Contractors, Inc. | 4. United Infrastructure Group, Inc. | 5. Dane Construction, LLC | 6. Coogler Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $216,281 | $138,250 | $145,865 | $138,872 | $140,825 | $47,000 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $75,000 | $40,000 | $31,444 | $83,324 | $84,495 | $28,019 |
| 0030 | Construction stakes, lines & grades (1050800) | EACH | 1 | $50,000 | $35,000 | $48,290 | $50,000 | $35,500 | $10,000 |
| 0040 | CPM progress schedule (1080300) | LS | 1 | $15,000 | $15,000 | $25,487 | $5,000.00 | $25,000 | $20,000 |
| 0050 | Clearing & grubbing within roadway (2012000) | LS | 1 | $100,000 | $150,000 | $55,265 | $200,000 | $100,000 | $70,500 |
| 0060 | Removal & disposal of existing asphalt pavement (2025000) | SY | 4,497 | $20.00 | $14.00 | $16.00 | $14.00 | $14.00 | $10.50 |
| 0070 | Removal & disposal of existing bridge (2028100) | LS | 1 | $100,000 | $175,000 | $199,233 | $150,000 | $118,540 | $73,500 |
| 0080 | Unclassified excavation (2031000) | CY | 3,766 | $10.00 | $24.00 | $35.00 | $24.00 | $24.00 | $26.00 |
| 0090 | Borrow excavation (2033000) | CY | 10,144 | $12.50 | $26.00 | $29.00 | $26.00 | $26.00 | $26.00 |
| 0100 | Geogrid reinforcement (uniaxial) (2037000) | SY | 621 | $15.00 | $12.00 | $22.00 | $12.00 | $12.00 | $18.00 |
| 0110 | Fine grading (2081001) | SY | 4,647 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 | $7.50 |
| 0120 | Flowable fill (2103000) | CY | 80 | $300.00 | $328.42 | $342.00 | $266.30 | $300.00 | $350.00 |
| 0130 | Liquid asphalt binder PG64-22 (4011004) | TON | 129 | $660.00 | $659.00 | $912.00 | $665.59 | $659.00 | $659.00 |
| 0140 | Full depth asph. pav. patching 10"unif (4012100) | SY | 150 | $150.00 | $150.00 | $140.00 | $151.50 | $150.00 | $150.00 |
| 0150 | Asphalt base course - type B (4020320) | TON | 1,820 | $115.00 | $114.00 | $121.00 | $115.14 | $114.00 | $114.00 |
| 0160 | Asphalt intermediate course type C (4030330) | TON | 410 | $150.00 | $149.00 | $120.00 | $150.49 | $149.00 | $149.00 |
| 0170 | Asphalt surface course type C (4040340) | TON | 401 | $120.00 | $120.00 | $120.00 | $121.20 | $120.00 | $120.00 |
| 0180 | Traffic control (6011000) | LS | 1 | $15,000 | $35,000 | $25,218 | $55,000 | $10,000 | $10,000 |
| 0190 | Barricade - type III (6041200) | LF | 84 | $25.00 | $24.00 | $23.00 | $25.92 | $25.00 | $44.00 |
| 0200 | Permanent construction signs (ground mounted) (6051120) | SF | 128 | $12.00 | $7.85 | $8.00 | $8.48 | $8.00 | $39.19 |
| 0210 | Permanent construction signs (barricade mounted) (6051125) | SF | 70 | $12.00 | $8.95 | $8.00 | $9.67 | $8.25 | $8.95 |
| 0220 | Type B - flashing light (608100B) | EACH | 16 | $200.00 | $165.00 | $134.00 | $178.20 | $94.95 | $124.06 |
| 0230 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 2,750 | $0.50 | $1.00 | $1.10 | $1.00 | $1.00 | $3.00 |
| 0240 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 2,750 | $0.50 | $1.00 | $1.10 | $1.00 | $1.00 | $3.00 |
| 0250 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 17 | $50.00 | $7.50 | $8.00 | $7.50 | $7.50 | $82.59 |
| 0260 | Milled-in rumble strip (6321000) | MI | 1 | $13,000 | $2,500.00 | $2,683.00 | $2,500.00 | $2,500.00 | $209,674 |
| 0270 | Furnish & install 2.0" schedule 80 PVC conduit (6750278) | LF | 484 | $15.00 | $38.12 | $21.00 | $12.00 | $21.00 | $12.60 |
| 0280 | Conc. for structures - class 4000 (7011400) | CY | 250.50 | $2,000.00 | $1,861.66 | $1,145.00 | $1,894.00 | $1,850.00 | $2,100.00 |
| 0290 | Grooved surface finish (7023200) | SY | 337 | $20.00 | $18.35 | $20.00 | $25.00 | $18.40 | $21.00 |
| 0300 | Reinf. steel for structures (bridge) (7031200) | LB | 60,837 | $1.40 | $1.30 | $2.36 | $1.50 | $2.50 | $1.47 |
| 0310 | Prestressed conc. beam (type III) (7043000) | LF | 475 | $400.00 | $475.00 | $481.00 | $275.00 | $675.00 | $420.00 |
| 0320 | 42" MASH concrete barrier parapet/railing wall (7051050) | LF | 240 | $155.00 | $138.00 | $159.00 | $130.00 | $140.00 | $168.00 |
| 0330 | Pile driving set-UP (7110010) | EACH | 12 | $8,500.00 | $7,500.00 | $6,402.00 | $7,500.00 | $5,250.00 | $8,820.00 |
| 0340 | Steel H bearing piling (HP14 X 73) (7112220) | LF | 794 | $78.00 | $62.62 | $65.00 | $56.00 | $62.75 | $84.00 |
| 0350 | 18" smooth wall pipe (7143618) | LF | 48 | $100.00 | $140.00 | $232.00 | $140.00 | $140.00 | $122.00 |
| 0360 | Beveling of pipe end (7199100) | EACH | 4 | $1,250.00 | $500.00 | $483.00 | $500.00 | $500.00 | $2,200.00 |
| 0370 | 4' slope flume (6" curb style with cutoffs) (7199200) | LF | 84 | $400.00 | $220.00 | $213.00 | $200.00 | $200.00 | $110.00 |
| 0380 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 107 | $175.00 | $66.00 | $80.00 | $46.00 | $46.00 | $40.00 |
| 0390 | Elastomeric bearing (7243100) | EACH | 12 | $1,500.00 | $100.00 | $1,112.00 | $1,200.00 | $350.00 | $1,470.00 |
| 0400 | Waterproofing (7282000) | SY | 30 | $80.00 | $60.32 | $95.00 | $150.00 | $100.00 | $89.25 |
| 0410 | Aggregate underdrain(agg#789)with 4"perf.pipe for struc (8011210) | TON | 125 | $100.00 | $100.00 | $138.00 | $135.00 | $100.00 | $175.00 |
| 0420 | Rip-rap (class B) (8041020) | TON | 705 | $85.00 | $90.00 | $93.00 | $90.00 | $90.00 | $95.00 |
| 0430 | Geotextile for erosion control under riprap(class 2)type B (8048205) | SY | 885 | $2.50 | $8.00 | $3.50 | $8.00 | $8.00 | $9.50 |
| 0440 | MT3 leading end treatment TL3 (8051151) | EACH | 4 | $3,500.00 | $3,700.00 | $3,971.00 | $3,700.00 | $3,000.00 | $4,080.38 |
| 0450 | MGS3 GR standard shoulder (8052100) | LF | 450 | $30.00 | $20.00 | $21.50 | $20.00 | $23.00 | $33.25 |
| 0460 | MTBBC3 MASH thrie-beam barrier connector TL3 (8053253) | EACH | 4 | $4,000.00 | $2,500.00 | $2,683.00 | $2,500.00 | $3,000.00 | $4,462.94 |
| 0470 | Flume inlet at guardrail (handwork) (8053257) | EACH | 4 | $4,000.00 | $5,500.00 | $3,898.00 | $5,000.00 | $5,000.00 | $1,800.00 |
| 0480 | Non-mow strip under guardrail (8055250) | SY | 100 | $135.00 | $160.00 | $172.00 | $120.00 | $120.00 | $160.00 |
| 0490 | Right of way marker(rebar and cap) (8091010) | EACH | 24 | $200.00 | $300.00 | $215.00 | $150.00 | $300.00 | $150.00 |
| 0500 | Right of way plat (8091050) | LS | 1 | $2,000.00 | $2,500.00 | $8,048.00 | $5,000.00 | $2,500.00 | $5,500.00 |
| 0510 | Permanent cover (8100100) | ACRE | 1.82 | $1,500.00 | $1,436.00 | $2,254.00 | $1,436.00 | $1,436.00 | $3,500.00 |
| 0520 | Temporary cover (8100200) | ACRE | 0.91 | $1,250.00 | $906.00 | $1,986.00 | $906.00 | $906.00 | $2,000.00 |
| 0530 | Compost (8101105) | CY | 489 | $40.00 | $5.00 | $84.00 | $5.00 | $5.00 | $85.50 |
| 0540 | Fertilizer (nitrogen) (8104005) | LB | 182 | $4.00 | $1.94 | $3.76 | $1.94 | $1.94 | $24.00 |
| 0550 | Fertilizer (phosphoric acid) (8104010) | LB | 182 | $4.00 | $1.94 | $3.76 | $1.94 | $1.94 | $24.00 |
| 0560 | Fertilizer (potash) (8104015) | LB | 182 | $4.00 | $1.94 | $3.76 | $1.94 | $1.94 | $24.00 |
| 0570 | Agricultural granular lime (8105005) | LB | 3,640 | $0.50 | $1.94 | $0.48 | $1.94 | $1.94 | $1.50 |
| 0580 | Selective watering (8109050) | GAL | 54,300 | $0.10 | $0.10 | $0.16 | $0.10 | $0.10 | $0.25 |
| 0590 | Mowing (8109901) | ACRE | 5.46 | $500.00 | $422.00 | $590.00 | $422.00 | $422.00 | $1,500.00 |
| 0600 | Turf reinforcement matting (TRM) type 2 (8151102) | MSY | 2.98 | $4,000.00 | $3,340.00 | $3,911.00 | $3,340.00 | $3,340.00 | $3,800.00 |
| 0610 | Hydraulic erosion control product (hecp) - type 1 (8151201) | ACRE | 3.73 | $1,450.00 | $1,560.00 | $2,575.00 | $1,560.00 | $1,560.00 | $4,500.00 |
| 0620 | Hydraulic erosion control product (hecp) - type 3 (8151203) | ACRE | 1.73 | $3,000.00 | $3,400.00 | $3,431.00 | $3,400.00 | $3,400.00 | $4,500.00 |
| 0630 | Sediment tubes for ditch checks (8152007) | LF | 460 | $13.00 | $15.00 | $13.00 | $15.00 | $15.00 | $20.00 |
| 0640 | Silt fence (8153000) | LF | 1,574 | $5.00 | $4.24 | $3.65 | $3.24 | $4.25 | $4.75 |
| 0650 | Cleaning silt basins (8154010) | CY | 92 | $100.00 | $35.00 | $45.00 | $35.00 | $35.00 | $30.00 |
| 0660 | Stabilized construction entrance (8156490) | SY | 550 | $35.00 | $25.00 | $21.00 | $25.00 | $25.00 | $20.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of December 9, 2025. Compiled by Mirage Metrics.