SCDOT contract 3265540 bid tabulation
Roundabout at S-279 and S-627. Let by South Carolina DOT on September 9, 2025, Lexington, District 1. 7 bids received; low bid $2,494,412 by Site-Prep, Inc. of NC.
- Owner
- South Carolina DOT
- Letting
- 09 SEP 2025
- Pay items
- 87
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Site-Prep, Inc. of NC | $2,494,412 | Low |
| 2 | Palmetto Sitework Services, LLC | $2,736,138 | +10% |
| 3 | Eagle Construction Company | $2,764,320 | +11% |
| 4 | Universal Civil Construction, LLC | $2,815,906 | +13% |
| 5 | Aos Specialty Contractors, Inc. | $2,894,466 | +16% |
| 6 | McClam & Associates, Inc. | $3,424,693 | +37% |
| 7 | Palmetto Corp. of Conway | $3,450,500 | +38% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Site-Prep, Inc. of NC | 2. Palmetto Sitework Services, LLC | 3. Eagle Construction Company | 4. Universal Civil Construction, LLC | 5. Aos Specialty Contractors, Inc. | 6. McClam & Associates, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization false (1031000) | LS | 1 | $78,273 | $136,000 | $125,000 | $140,000 | $235,000 | $244,453 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $27,500 | $88,000 | $52,000 | $84,000 | $40,000 | $119,769 |
| 0030 | Construction stakes, lines & grades (1050800) | EACH | 1 | $10,440 | $65,000 | $55,500 | $37,000 | $33,270 | $181,833 |
| 0040 | Large public water relocation no. ____ 001 (1052110) | EACH | 1 | $355,450 | $305,590 | $320,590 | $357,000 | $345,000 | $380,589 |
| 0050 | Clearing & grubbing within right of way (2011000) | LS | 1 | $44,000 | $78,000 | $91,200 | $45,000 | $56,580 | $157,593 |
| 0060 | Removal & disposal of existing pavement (2023000) | SY | 260 | $7.50 | $39.00 | $10.00 | $44.25 | $30.00 | $15.00 |
| 0070 | Unclassified excavation (2031000) | CY | 1,573 | $19.82 | $17.00 | $54.40 | $42.50 | $55.00 | $35.00 |
| 0080 | Borrow excavation (2033000) | CY | 1,550 | $39.50 | $25.00 | $36.50 | $33.50 | $35.75 | $47.00 |
| 0090 | Fine grading (2081001) | SY | 2,328 | $10.50 | $4.00 | $4.00 | $7.25 | $14.25 | $9.00 |
| 0100 | Flowable fill (2103000) | CY | 10 | $385.00 | $285.00 | $450.00 | $250.00 | $254.00 | $275.00 |
| 0110 | Maintenance stone (3059900) | TON | 100 | $72.50 | $70.50 | $47.00 | $52.00 | $60.00 | $80.00 |
| 0120 | Liquid asphalt binder PG64-22 (4011004) | TON | 167 | $609.00 | $800.00 | $710.00 | $700.00 | $950.00 | $675.00 |
| 0130 | Milling existing asphalt pavement (variable) (4013990) | SY | 1,140 | $5.78 | $9.50 | $22.00 | $22.00 | $11.50 | $8.95 |
| 0140 | Asphalt base course - type A (4020310) | TON | 1,372 | $134.40 | $125.00 | $114.00 | $121.25 | $111.00 | $118.95 |
| 0150 | Asphalt intermediate course type B (4030320) | TON | 220 | $134.40 | $194.00 | $250.00 | $250.00 | $111.00 | $185.05 |
| 0160 | Asphalt surface course type B (4040320) | TON | 1,462 | $134.40 | $134.00 | $114.00 | $118.00 | $111.00 | $127.20 |
| 0170 | Asphalt surface course type E (4040360) | TON | 195 | $157.50 | $190.00 | $230.00 | $208.00 | $111.00 | $182.50 |
| 0180 | Driveway paving-surface type C (4047220) | TON | 25 | $157.50 | $550.00 | $600.00 | $540.00 | $111.00 | $500.00 |
| 0190 | Stained concrete pavement (8" uniform) (5019010) | SY | 475 | $190.00 | $190.00 | $230.00 | $111.50 | $175.00 | $98.00 |
| 0200 | Traffic control (6011000) | LS | 1 | $133,000 | $315,000 | $200,000 | $318,000 | $275,000 | $306,525 |
| 0210 | Permanent construction signs (ground mounted) (6051120) | SF | 392 | $6.00 | $6.35 | $10.00 | $9.90 | $10.50 | $7.25 |
| 0220 | Pavement markings(temp- paint) 4" white broken lines (609105A) | LF | 200 | $0.16 | $0.15 | $0.18 | $0.14 | $0.20 | $0.14 |
| 0230 | Pavement markings(temporary-paint)-4" white solid lines (609115A) | LF | 19,500 | $0.16 | $0.15 | $0.18 | $0.14 | $0.20 | $0.14 |
| 0240 | Pavement markings(temporary-paint)-4" yellow solid lines (609115B) | LF | 19,500 | $0.16 | $0.15 | $0.18 | $0.14 | $0.20 | $0.14 |
| 0250 | Pavement markings(temporary-paint)- 24"white solid lines (609135A) | LF | 250 | $1.00 | $1.55 | $1.75 | $1.00 | $1.70 | $1.00 |
| 0260 | Pavement markings (temporary paint) 24"X36" white triangle yield bar (609138A) | LF | 200 | $2.75 | $1.55 | $1.75 | $2.50 | $1.70 | $2.50 |
| 0270 | Temporary yellow pavement markers BI-dir.- 4"X4" (6092155) | EACH | 250 | $7.50 | $6.19 | $7.00 | $7.00 | $6.80 | $7.00 |
| 0280 | 6" yellow solid line on curb/median - fast dry paint (6240112) | LF | 1,300 | $1.00 | $0.77 | $0.90 | $1.00 | $0.85 | $1.00 |
| 0290 | 8" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271008) | LF | 150 | $3.30 | $4.12 | $4.65 | $3.00 | $4.50 | $3.00 |
| 0300 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 2,100 | $0.95 | $0.77 | $0.90 | $0.85 | $0.85 | $0.85 |
| 0310 | 8" white solid lines thermoplastic - 125 mil. (6271015) | LF | 250 | $3.00 | $3.09 | $3.50 | $3.00 | $3.40 | $3.00 |
| 0320 | 24IN X 36IN white triang. yield bar (gaps exc)thermo-125MIL (6271024) | LF | 75 | $11.00 | $20.62 | $25.00 | $10.00 | $23.00 | $10.00 |
| 0330 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 3,900 | $0.95 | $0.77 | $0.90 | $0.85 | $0.85 | $0.85 |
| 0340 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 80 | $7.70 | $6.19 | $7.00 | $7.00 | $6.80 | $7.00 |
| 0350 | Flat sheet, type III, fixed SZ. & MSG. sign (6510105) | SF | 167.20 | $24.20 | $23.20 | $35.00 | $33.50 | $32.00 | $27.00 |
| 0360 | U-section post for sign supports - 3P (6531210) | LF | 300 | $17.60 | $10.30 | $20.00 | $10.75 | $17.00 | $9.85 |
| 0370 | Reflective sign post panels (6531500) | LF | 110 | $12.00 | $7.66 | $25.00 | $9.50 | $23.00 | $7.15 |
| 0380 | Design & installation of rdwy. lighting electrical system 001 (6581000) | EACH | 1 | $84,500 | $80,000 | $80,000 | $110,000 | $75,000 | $80,000 |
| 0390 | SGL.light STD.35'HT.AL.pole- incl top tenon MT. (6581145) | EACH | 9 | $15,225 | $9,500.00 | $16,000 | $9,300.00 | $8,200.00 | $14,500 |
| 0400 | 18" smooth wall pipe (7143618) | LF | 1,040 | $97.78 | $90.00 | $67.25 | $99.00 | $105.00 | $159.00 |
| 0410 | 24" smooth wall pipe (7143624) | LF | 337 | $100.00 | $104.00 | $92.00 | $121.00 | $138.50 | $187.00 |
| 0420 | 30" smooth wall pipe (7143630) | LF | 525 | $153.00 | $140.00 | $127.00 | $155.00 | $166.00 | $231.00 |
| 0430 | Cleaning existing pipe (7149999) | LF | 1,150 | $7.65 | $3.00 | $40.00 | $8.00 | $40.00 | $50.00 |
| 0440 | Catch basin -type 1 CB - type 1 (7191005) | EACH | 1 | $8,030.00 | $5,950.00 | $4,200.00 | $6,250.00 | $8,140.00 | $5,700.00 |
| 0450 | Catch basin -type 1 with standard 4' X 4' box (7191006) | EACH | 1 | $10,230 | $5,950.00 | $7,900.00 | $6,700.00 | $8,645.00 | $6,200.00 |
| 0460 | Catch basin - type 1 special (7191050) | EACH | 5 | $8,000.00 | $5,400.00 | $4,200.00 | $6,700.00 | $8,145.00 | $7,200.00 |
| 0470 | Catch basin -type 9 with standard 3' X 4' box (7191206) | EACH | 1 | $8,030.00 | $4,800.00 | $6,500.00 | $6,900.00 | $7,500.00 | $5,700.00 |
| 0480 | Catch basin -type 9 MH (7191250) | EACH | 1 | $7,480.00 | $4,800.00 | $4,200.00 | $6,900.00 | $7,500.00 | $5,700.00 |
| 0490 | Catch basin -type 16 (7191605) | EACH | 5 | $8,200.00 | $6,500.00 | $7,400.00 | $7,700.00 | $8,810.00 | $8,900.00 |
| 0500 | Catch basin -type 17 (7191625) | EACH | 7 | $9,100.00 | $12,400 | $9,500.00 | $9,350.00 | $10,585 | $11,000 |
| 0510 | Drop inlet (24" X 36") with standard 4' X 4' box (7192021) | EACH | 1 | $9,405.00 | $6,200.00 | $7,800.00 | $5,800.00 | $8,900.00 | $6,150.00 |
| 0520 | Manhole with standard 4' X 4' box (7192107) | EACH | 6 | $7,700.00 | $5,535.00 | $7,800.00 | $6,150.00 | $8,200.00 | $6,150.00 |
| 0530 | Extra depth of box (7196000) | LF | 10 | $580.00 | $700.00 | $600.00 | $1,160.00 | $430.00 | $450.00 |
| 0540 | Beveling of pipe end (7199100) | EACH | 5 | $200.00 | $400.00 | $700.00 | $200.00 | $990.00 | $450.00 |
| 0550 | Concrete curb (9" X 15") (7201000) | LF | 250 | $66.74 | $53.00 | $74.00 | $63.25 | $35.00 | $50.00 |
| 0560 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 1,420 | $61.28 | $47.00 | $39.00 | $51.75 | $32.00 | $40.00 |
| 0570 | Concrete median (7206000) | SY | 400 | $118.50 | $120.00 | $130.00 | $102.75 | $90.00 | $90.00 |
| 0580 | Planted median subsurface drainage (8020100) | SY | 330 | $73.00 | $95.00 | $79.00 | $132.50 | $120.00 | $125.00 |
| 0590 | Rip-rap (class A) (8041010) | TON | 210 | $104.50 | $100.00 | $76.00 | $106.50 | $125.00 | $115.20 |
| 0600 | Rip-rap (class B) (8041020) | TON | 90 | $134.50 | $125.00 | $76.00 | $114.50 | $125.00 | $115.20 |
| 0610 | Geotextile fabric for erosion control under riprap (class 2) (8042800) | SY | 840 | $1.88 | $2.25 | $4.00 | $3.25 | $8.00 | $6.16 |
| 0620 | Geotextile for erosion control under riprap(class 2)type A (8048200) | SY | 100 | $7.87 | $2.25 | $5.00 | $3.25 | $26.00 | $9.96 |
| 0630 | Right of way marker(rebar and cap) (8091010) | EACH | 23 | $165.00 | $165.00 | $175.00 | $240.00 | $170.00 | $110.00 |
| 0640 | Right of way plat (8091050) | LS | 1 | $3,850.00 | $3,850.00 | $3,000.00 | $5,000.00 | $4,000.00 | $6,000.00 |
| 0650 | Permanent cover (8100100) | ACRE | 1.92 | $1,635.00 | $1,925.00 | $1,800.00 | $1,800.00 | $3,960.00 | $1,500.00 |
| 0660 | Temporary cover (8100200) | ACRE | 4 | $1,033.00 | $1,540.00 | $1,600.00 | $1,000.00 | $2,800.00 | $1,325.00 |
| 0670 | Seeding - eragrostis curvula - weeping lovegrass (8102520) | MSY | 0.55 | $1,100.00 | $1,030.93 | $2,200.00 | $1,215.00 | $5,000.00 | $1,600.00 |
| 0680 | Fertilizer (nitrogen) (8104005) | LB | 193 | $1.78 | $2.58 | $5.00 | $2.00 | $1.85 | $4.25 |
| 0690 | Fertilizer (phosphoric acid) (8104010) | LB | 193 | $1.78 | $2.58 | $5.00 | $2.00 | $1.85 | $4.25 |
| 0700 | Fertilizer (potash) (8104015) | LB | 193 | $1.78 | $2.58 | $5.00 | $2.00 | $1.85 | $4.25 |
| 0710 | Agricultural granular lime (8105005) | LB | 3,846 | $1.05 | $0.26 | $0.60 | $1.15 | $0.50 | $0.40 |
| 0720 | Selective watering (8109050) | GAL | 54,300 | $0.16 | $0.01 | $0.10 | $0.03 | $0.10 | $0.09 |
| 0730 | Mowing (8109901) | ACRE | 7.69 | $480.00 | $670.00 | $580.00 | $350.00 | $675.00 | $485.00 |
| 0740 | Turf reinforcement matting (TRM) type 1 (8151101) | MSY | 1 | $3,835.00 | $4,600.00 | $4,550.00 | $4,015.00 | $3,900.00 | $3,800.00 |
| 0750 | Hydraulic erosion control product (hecp) - type 3 (8151203) | ACRE | 5.92 | $3,988.00 | $4,000.00 | $3,500.00 | $4,175.00 | $3,600.00 | $2,900.00 |
| 0760 | Inlet structure filter - type F (weighted) (8152004) | LF | 870 | $11.70 | $17.00 | $15.00 | $12.25 | $14.50 | $15.00 |
| 0770 | Inlet structure filter- type F (non-weighted) (8152006) | LF | 870 | $10.66 | $12.00 | $14.00 | $11.15 | $12.25 | $13.75 |
| 0780 | Sediment tubes for ditch checks (8152007) | LF | 620 | $12.45 | $13.30 | $14.00 | $13.00 | $12.00 | $13.25 |
| 0790 | Silt fence (8153000) | LF | 4,940 | $2.80 | $2.85 | $4.75 | $2.95 | $5.50 | $3.00 |
| 0800 | Replace/repair silt fence (8153090) | LF | 1,500 | $4.25 | $2.10 | $7.00 | $4.50 | $4.50 | $5.25 |
| 0810 | Cleaning silt basins (8154010) | CY | 290 | $7.00 | $10.35 | $12.00 | $1.00 | $30.00 | $30.00 |
| 0820 | Removal of silt retained by silt fence (8154050) | LF | 1,235 | $1.58 | $9.28 | $5.00 | $4.00 | $5.00 | $10.00 |
| 0830 | Inlet filter cleaning (8154155) | EACH | 102 | $20.00 | $10.00 | $75.00 | $99.00 | $145.00 | $200.00 |
| 0840 | Inlet structure filter - type B (8156210) | EACH | 24 | $166.00 | $92.78 | $380.00 | $165.00 | $250.00 | $650.00 |
| 0850 | Inlet structure filter - type A (8156219) | LF | 1,520 | $3.45 | $9.79 | $20.00 | $6.00 | $10.00 | $10.00 |
| 0860 | Aggregate no.5 or 57 for erosion control (8156410) | TON | 40 | $120.00 | $75.00 | $61.00 | $75.00 | $60.00 | $90.00 |
| 0870 | Stabilized construction entrance (8156490) | SY | 550 | $25.81 | $16.00 | $25.50 | $19.50 | $7.00 | $30.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of September 9, 2025. Compiled by Mirage Metrics.