SCDOT contract 4059900 bid tabulation
Safety Improvement - SC 764 (Richland Co). Let by South Carolina DOT on May 12, 2026, Richland, District 1. 7 bids received; low bid $294,336 by Site-Prep, Inc. of NC.
- Owner
- South Carolina DOT
- Letting
- 12 MAY 2026
- Pay items
- 31
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Site-Prep, Inc. of NC | $294,336 | Low |
| 2 | Aos Specialty Contractors, Inc. | $368,627 | +25% |
| 3 | Cherokee, Inc. | $411,002 | +40% |
| 4 | Palmetto Corp. of Conway | $417,470 | +42% |
| 5 | Eagle Construction Company | $445,051 | +51% |
| 6 | Palmetto Sitework Services, LLC | $453,903 | +54% |
| 7 | L-J, Inc. | $499,136 | +70% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Site-Prep, Inc. of NC | 2. Aos Specialty Contractors, Inc. | 3. Cherokee, Inc. | 4. Palmetto Corp. of Conway | 5. Eagle Construction Company | 6. Palmetto Sitework Services, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $27,500 | $40,523 | $20,550 | $20,000 | $22,000 | $55,000 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $5,000.00 | $7,091.00 | $8,220.00 | $8,000.00 | $8,800.00 | $15,000 |
| 0030 | Construction stakes, lines & grades (1050800) | EACH | 1 | $7,570.00 | $9,142.00 | $20,000 | $7,500.00 | $18,000 | $27,500 |
| 0050 | Unclassified excavation (2031000) | CY | 315 | $28.25 | $46.00 | $100.00 | $90.00 | $50.00 | $55.00 |
| 0060 | Borrow excavation (2033000) | CY | 399 | $55.71 | $41.00 | $40.00 | $88.00 | $60.00 | $65.00 |
| 0080 | Maintenance stone (3059900) | TON | 20 | $50.00 | $83.00 | $60.00 | $170.00 | $60.00 | $125.00 |
| 0120 | Traffic control (6011000) | LS | 1 | $32,250 | $72,888 | $138,100 | $94,600 | $85,000 | $89,520 |
| 0130 | Permanent construction signs (ground mounted) (6051120) | SF | 176 | $6.60 | $8.50 | $10.00 | $5.60 | $15.00 | $8.00 |
| 0140 | 8" white solid lines thermoplastic - 125 mil. (6271015) | LF | 131 | $3.30 | $4.50 | $5.00 | $4.00 | $6.00 | $4.50 |
| 0150 | 24" white solid lines (stop/diag lines)-thermo.-125 mil (6271025) | LF | 18 | $22.00 | $13.00 | $15.00 | $12.00 | $20.00 | $13.50 |
| 0160 | 14"X 23" horizontal elliptical(HE) RC pipe cul.- class HE-III (7141141) | LF | 32 | $383.00 | $487.00 | $400.00 | $357.00 | $195.00 | $487.00 |
| 0170 | 18" smooth wall pipe (7143618) | LF | 292 | $145.25 | $161.00 | $100.00 | $147.00 | $86.00 | $171.00 |
| 0180 | Drop inlet (24" X 24") (7192010) | EACH | 4 | $3,810.00 | $4,270.00 | $5,000.00 | $4,685.00 | $4,700.00 | $5,500.00 |
| 0190 | Drop inlet (24" X 24") with standard 4' X 4' box (7192011) | EACH | 4 | $5,213.00 | $5,029.00 | $5,000.00 | $5,615.00 | $9,700.00 | $5,500.00 |
| 0200 | Beveling of pipe end (7199100) | EACH | 5 | $200.00 | $515.00 | $500.00 | $840.00 | $1,000.00 | $550.00 |
| 0210 | Concrete sidewalk(4" uniform) (7204100) | SY | 478 | $79.08 | $74.00 | $65.00 | $94.35 | $107.50 | $75.00 |
| 0220 | Concrete driveway(6" uniform) (7205000) | SY | 14 | $110.15 | $366.00 | $72.00 | $210.00 | $140.00 | $110.00 |
| 0230 | Pedestrian ramp construction (7209000) | SY | 150 | $126.50 | $124.00 | $100.00 | $158.75 | $350.00 | $200.00 |
| 0240 | Surface applied detectable warning (7209100) | SF | 75 | $61.10 | $51.00 | $45.00 | $40.00 | $170.00 | $50.00 |
| 0250 | Rip-rap (class B) (8041020) | TON | 66 | $122.00 | $109.00 | $115.00 | $240.00 | $94.00 | $160.00 |
| 0260 | Geotextile for erosion control under riprap(class 2)type B (8048205) | SY | 81 | $6.54 | $4.00 | $10.00 | $14.00 | $10.00 | $5.00 |
| 0270 | Right of way marker(rebar and cap) (8091010) | EACH | 4 | $385.00 | $382.00 | $220.00 | $600.00 | $500.00 | $390.00 |
| 0280 | Right of way plat (8091050) | LS | 1 | $2,750.00 | $2,728.00 | $3,500.00 | $1,500.00 | $3,500.00 | $2,800.00 |
| 0290 | Permanent grassing for non-permitted resurfacing projects (8100102) | ACRE | 0.25 | $7,088.54 | $3,818.00 | $10,600 | $4,000.00 | $12,500 | $9,350.00 |
| 0300 | Hydraulic erosion control product (hecp) - type 1 (8151201) | ACRE | 0.50 | $1,500.00 | $1,746.00 | $4,500.00 | $3,200.00 | $5,100.00 | $3,850.00 |
| 0310 | Sediment tubes for ditch checks (8152007) | LF | 60 | $14.50 | $14.00 | $15.00 | $14.00 | $25.00 | $13.75 |
| 0320 | Silt fence (8153000) | LF | 1,397 | $3.55 | $4.00 | $5.50 | $3.60 | $4.50 | $3.00 |
| 0330 | Cleaning silt basins (8154010) | CY | 12 | $57.50 | $136.00 | $5.00 | $35.00 | $200.00 | $55.00 |
| 0340 | Cleaning inlet structure filters (8156200) | EACH | 8 | $200.00 | $393.00 | $60.00 | $60.00 | $350.00 | $55.00 |
| 0350 | Inlet structure filter - type B (8156210) | EACH | 8 | $220.00 | $246.00 | $350.00 | $300.00 | $625.00 | $192.50 |
| 0360 | Stabilized construction entrance (8156490) | SY | 550 | $14.50 | $22.00 | $15.00 | $21.00 | $32.50 | $15.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of May 12, 2026. Compiled by Mirage Metrics.