SCDOT contract 4149710 bid tabulation
US 378 Bridge Replacement over Little Saluda River. Let by South Carolina DOT on August 12, 2025, Saluda, District 2. 5 bids received; low bid $7,174,457 by Dane Construction, LLC.
- Owner
- South Carolina DOT
- Letting
- 12 AUG 2025
- Pay items
- 102
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Dane Construction, LLC | $7,174,457 | Low |
| 2 | Dellinger, Inc. | $7,297,986 | +2.0% |
| 3 | Aos Specialty Contractors, Inc. | $7,898,208 | +10% |
| 4 | Eagle Construction Company | $8,247,667 | +15% |
| 5 | United Infrastructure Group, Inc. | $9,964,048 | +39% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Dane Construction, LLC | 2. Dellinger, Inc. | 3. Aos Specialty Contractors, Inc. | 4. Eagle Construction Company | 5. United Infrastructure Group, Inc. |
|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $359,000 | $364,700 | $583,437 | $400,000 | $498,202 |
| 0020 | Bridge construction access (1031200) | LS | 1 | $100,000 | $200,000 | $150,497 | $128,800 | $199,281 |
| 0030 | Bonds and insurance (1032010) | LS | 1 | $142,900 | $60,000 | $98,900 | $160,500 | $298,921 |
| 0040 | Construction stakes, lines & grades (1050800) | EACH | 1 | $30,000 | $35,000 | $107,467 | $82,500 | $200,000 |
| 0060 | Small public water relocation no. ____ 01 (1052100) | EACH | 1 | $128,625 | $128,625 | $146,854 | $128,625 | $128,625 |
| 0070 | CPM progress schedule (1080300) | LS | 1 | $25,000 | $20,000 | $37,888 | $5,000.00 | $15,000 |
| 0080 | Clearing & grubbing within right of way (2011000) | LS | 1 | $50,000 | $130,000 | $89,405 | $99,200 | $2,944,890 |
| 0090 | Removal & disposal item no. 001 (2022000) | LS | 1 | $1,500.00 | $2,500.00 | $6,803.00 | $1,000.00 | $450.00 |
| 0100 | Removal & disposal of existing asphalt pavement (2025000) | SY | 3,132 | $10.00 | $10.05 | $11.50 | $11.50 | $28.90 |
| 0110 | Removal of exist. guardrail (2027801) | LF | 1,813 | $4.00 | $1.00 | $4.50 | $2.00 | $1.00 |
| 0120 | Removal & disposal of existing bridge (2028100) | LS | 1 | $300,000 | $150,000 | $428,729 | $500,000 | $300,000 |
| 0130 | Unclassified excavation (2031000) | CY | 1,864 | $26.00 | $25.00 | $53.00 | $44.47 | $25.00 |
| 0140 | Borrow excavation (2033000) | CY | 23,551 | $28.00 | $38.00 | $40.00 | $41.30 | $30.00 |
| 0150 | Geogrid reinforcement (uniaxial) (2037000) | SY | 278 | $7.50 | $25.47 | $25.00 | $10.00 | $7.75 |
| 0160 | Temporary shoring system (2047000) | LF | 125 | $800.00 | $639.51 | $935.00 | $900.00 | $500.00 |
| 0170 | Fine grading (2081001) | SY | 6,612 | $4.50 | $4.00 | $6.75 | $3.00 | $5.00 |
| 0180 | Flowable fill (2103000) | CY | 4 | $750.00 | $393.76 | $1,769.00 | $600.00 | $30.00 |
| 0190 | Maintenance stone (3059900) | TON | 100 | $72.00 | $43.00 | $108.00 | $53.00 | $100.00 |
| 0200 | Liquid asphalt binder PG64-22 (4011004) | TON | 279 | $708.00 | $708.00 | $800.00 | $730.00 | $708.00 |
| 0210 | Full depth asph. pav. patching 6" unif. (4012060) | SY | 500 | $75.00 | $75.25 | $85.00 | $88.00 | $75.00 |
| 0220 | Milling existing asphalt pavement (variable) (4013990) | SY | 135 | $30.00 | $31.00 | $109.00 | $40.00 | $30.00 |
| 0230 | Asphalt base course - type B (4020320) | TON | 3,566 | $115.00 | $115.20 | $133.00 | $119.00 | $115.00 |
| 0240 | Asphalt intermediate course type C (4030330) | TON | 1,001 | $122.00 | $122.25 | $138.00 | $128.00 | $122.00 |
| 0250 | Asphalt surface course type C (4040340) | TON | 912 | $120.00 | $120.25 | $135.00 | $127.00 | $120.00 |
| 0260 | Asphalt surface course type E (4040360) | TON | 7 | $350.00 | $400.00 | $395.00 | $600.00 | $350.00 |
| 0270 | Traffic control (6011000) | LS | 1 | $60,000 | $180,000 | $215,030 | $96,000 | $125,000 |
| 0280 | Permanent construction signs (ground mounted) (6051120) | SF | 232 | $6.75 | $6.75 | $9.60 | $10.00 | $7.40 |
| 0290 | Portable terminal impact attenuator-test level 3-60 MPH (6052122) | EACH | 4 | $9,500.00 | $12,150 | $10,450 | $8,500.00 | $12,150 |
| 0300 | Anchor kit - port. attenuator(test level 3) 60MPH (605212B) | EACH | 5 | $850.00 | $3,250.00 | $1,355.00 | $2,000.00 | $3,250.00 |
| 0310 | Temporary concrete barrier - unanchored (6053110) | LF | 1,700 | $44.00 | $58.88 | $60.00 | $25.50 | $49.30 |
| 0320 | Pavement markings(temporary-paint)-4" white solid lines (609115A) | LF | 27,000 | $0.20 | $0.20 | $0.23 | $0.25 | $0.20 |
| 0330 | Pavement markings(temporary-paint)-4" yellow solid lines (609115B) | LF | 27,000 | $0.20 | $0.20 | $0.23 | $0.25 | $0.20 |
| 0340 | Pref.flex.wet retro.PVMT.mark(T- 2)temp.removable 4"WH.solid pref. (609115G) | LF | 1,000 | $2.50 | $2.50 | $2.82 | $3.00 | $2.50 |
| 0350 | Pref.flex.wet retro.PVMT.mark(T- 2)temp.REMOVABLE4"yel.solid pref. (609115H) | LF | 1,000 | $2.50 | $2.50 | $2.82 | $3.00 | $2.50 |
| 0360 | Temporary yellow pavement markers mono-dir.- 4"X4" (6092150) | EACH | 350 | $7.50 | $7.50 | $8.47 | $9.00 | $7.50 |
| 0370 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 4,800 | $0.75 | $0.75 | $0.85 | $0.90 | $0.75 |
| 0380 | 24" white solid lines (stop/diag lines)-thermo.-125 mil (6271025) | LF | 50 | $15.00 | $15.00 | $16.94 | $18.00 | $15.00 |
| 0390 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 4,800 | $0.75 | $0.75 | $0.85 | $0.90 | $0.75 |
| 0400 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 40 | $7.50 | $7.50 | $8.47 | $9.00 | $7.50 |
| 0410 | Milled-in rumble strip (6321000) | MI | 1.50 | $2,500.00 | $3,900.00 | $4,518.00 | $8,000.00 | $1,000.00 |
| 0420 | Pref.flex.retro.PVMT.mark(T- 1)perm.(60MIL)4"WH.solid (6351150) | LF | 600 | $5.00 | $5.00 | $5.65 | $6.00 | $5.00 |
| 0430 | Pref.flex.retro.PVMT.mark(T- 1)perm.(60MIL)4"yel.sol. (6351450) | LF | 600 | $5.00 | $5.00 | $5.65 | $6.00 | $5.00 |
| 0440 | Flat sheet, type III, fixed SZ. & MSG. sign (6510105) | SF | 30 | $13.00 | $28.00 | $33.89 | $40.00 | $27.00 |
| 0450 | Flat sheet, type III, size determined by MSG (6510106) | SF | 10.50 | $13.00 | $28.00 | $35.50 | $60.00 | $27.00 |
| 0460 | U-section post for sign supports - 2P (6531205) | LF | 40 | $7.00 | $9.45 | $16.94 | $20.00 | $9.50 |
| 0470 | U-section post for sign supports - 3P (6531210) | LF | 48 | $7.25 | $10.15 | $11.77 | $15.00 | $14.75 |
| 0480 | Furnish & install 2.0" schedule 80 PVC conduit (6750278) | LF | 1,252 | $31.89 | $50.00 | $17.00 | $20.00 | $9.00 |
| 0490 | Conc. for structures - class 4000 (7011400) | CY | 699.80 | $2,050.00 | $1,915.66 | $1,324.00 | $1,900.00 | $1,800.00 |
| 0500 | Conc. for structures - class 4000DS (7011510) | CY | 14 | $1,000.00 | $500.00 | $3,692.00 | $1,000.00 | $2,000.00 |
| 0510 | Grooved surface finish (7023200) | SY | 1,268 | $3.55 | $18.55 | $7.00 | $4.00 | $10.98 |
| 0520 | Reinf. steel for structures (bridge) (7031200) | LB | 170,499 | $3.00 | $1.05 | $2.03 | $2.10 | $1.32 |
| 0530 | Hoop reinforcing steel for structures (bridge) (7031220) | LB | 5,651 | $4.50 | $2.28 | $5.74 | $5.00 | $3.71 |
| 0540 | Prestressed concrete bulb tee beam(54"mod.) (7044554) | LF | 1,614 | $445.00 | $600.00 | $583.00 | $700.00 | $355.29 |
| 0550 | 42" MASH concrete barrier parapet/railing wall (7051050) | LF | 624 | $112.00 | $200.00 | $135.00 | $125.00 | $100.57 |
| 0560 | Steel H bearing piling (HP14 X 89) (7112230) | LF | 290 | $84.50 | $70.23 | $245.00 | $95.00 | $142.46 |
| 0570 | Drilled shaft set-UP (7120006) | EACH | 6 | $4,500.00 | $30,000 | $14,145 | $4,700.00 | $30,000 |
| 0580 | Crosshole sonic logging setup (7120010) | EACH | 6 | $850.00 | $3,102.62 | $3,163.00 | $1,000.00 | $2,722.82 |
| 0590 | Drilled shaft with rock excavation - 42" diameter (7120152) | LF | 48 | $4,600.00 | $4,949.72 | $4,688.00 | $5,100.00 | $959.86 |
| 0600 | Drilled shaft with wet & dry excavation - 48" diameter (7120161) | LF | 133 | $2,300.00 | $896.95 | $678.00 | $2,500.00 | $965.04 |
| 0610 | Construction casing - 48" diameter (7120165) | LF | 133 | $505.00 | $410.26 | $398.00 | $600.00 | $408.37 |
| 0620 | 18" smooth wall pipe (7143618) | LF | 140 | $115.00 | $110.00 | $187.00 | $73.50 | $75.00 |
| 0630 | 24" smooth wall pipe (7143624) | LF | 144 | $132.00 | $125.00 | $225.00 | $112.00 | $100.00 |
| 0640 | Drilled pile set-UP (7160008) | EACH | 12 | $3,200.00 | $4,000.00 | $1,414.00 | $5,000.00 | $6,549.06 |
| 0650 | Soil excavation for drilled pile foundations - 30" diameter (7160023) | LF | 200 | $610.00 | $219.05 | $172.00 | $670.00 | $467.50 |
| 0660 | Rock excavation for drilled pile foundations - 30" diameter (7160063) | LF | 77 | $1,200.00 | $981.34 | $1,019.00 | $1,300.00 | $467.50 |
| 0670 | Beveling of pipe end (7199100) | EACH | 10 | $875.00 | $350.00 | $1,400.00 | $700.00 | $250.00 |
| 0680 | 4' slope flume (6" curb style with cutoffs) (7199200) | LF | 60 | $260.00 | $260.00 | $192.00 | $355.00 | $260.00 |
| 0690 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 142 | $56.00 | $56.00 | $50.00 | $76.00 | $56.00 |
| 0700 | Elastomeric bearing (7243100) | EACH | 36 | $600.00 | $256.48 | $326.00 | $725.00 | $935.62 |
| 0710 | Waterproofing (7282000) | SY | 31 | $80.00 | $60.94 | $104.00 | $84.00 | $240.70 |
| 0720 | Aggregate underdrain(agg#789)with 4"perf.pipe for struc (8011210) | TON | 144 | $75.00 | $96.14 | $141.00 | $84.00 | $158.54 |
| 0730 | 12" temporary pipe slope drain (8034120) | LF | 100 | $21.00 | $75.00 | $60.00 | $49.00 | $40.00 |
| 0740 | Rip-rap (class A) (8041010) | TON | 83 | $73.00 | $96.50 | $190.00 | $83.00 | $100.00 |
| 0750 | Rip-rap (class B) (8041020) | TON | 724 | $73.00 | $96.00 | $100.00 | $83.00 | $100.00 |
| 0760 | Geotextile for erosion control under riprap(class 2)type C (8048210) | SY | 1,337 | $10.00 | $3.00 | $5.00 | $3.50 | $5.00 |
| 0770 | MT3 leading end treatment TL3 (8051151) | EACH | 3 | $3,300.00 | $3,400.00 | $4,123.00 | $4,200.00 | $3,400.00 |
| 0780 | MGS3 GR standard shoulder (8052100) | LF | 462.50 | $23.00 | $24.50 | $31.50 | $32.20 | $24.50 |
| 0790 | Premash thriebeam bridge conn TBBC3 (8053250) | EACH | 2 | $1,200.00 | $2,600.00 | $564.00 | $575.00 | $2,600.00 |
| 0800 | MTBBC3 MASH thrie-beam barrier connector TL3 (8053253) | EACH | 3 | $3,100.00 | $2,700.00 | $4,123.00 | $4,200.00 | $2,700.00 |
| 0810 | Flume inlet at guardrail (handwork) (8053257) | EACH | 2 | $5,000.00 | $5,000.00 | $6,760.00 | $6,500.00 | $5,000.00 |
| 0820 | Non-mow strip under guardrail (8055250) | SY | 75 | $130.00 | $130.00 | $200.00 | $170.00 | $150.00 |
| 0830 | Right of way marker(rebar and cap) (8091010) | EACH | 37 | $150.00 | $150.00 | $169.00 | $175.00 | $125.00 |
| 0840 | Right of way plat (8091050) | LS | 1 | $5,000.00 | $5,000.00 | $5,640.00 | $2,300.00 | $7,500.00 |
| 0850 | Permanent cover (8100100) | ACRE | 3.94 | $1,597.56 | $1,600.00 | $2,123.00 | $1,600.00 | $1,382.60 |
| 0860 | Temporary cover (8100200) | ACRE | 1.97 | $1,394.31 | $1,400.00 | $1,894.00 | $1,500.00 | $1,270.77 |
| 0870 | Fertilizer (nitrogen) (8104005) | LB | 394 | $2.00 | $2.00 | $3.44 | $6.00 | $5.08 |
| 0880 | Fertilizer (phosphoric acid) (8104010) | LB | 394 | $2.00 | $2.00 | $3.44 | $6.00 | $5.08 |
| 0890 | Fertilizer (potash) (8104015) | LB | 394 | $2.00 | $2.00 | $3.44 | $6.00 | $5.08 |
| 0900 | Agricultural granular lime (8105005) | LB | 7,872 | $0.60 | $0.60 | $0.40 | $0.75 | $0.46 |
| 0910 | Selective watering (8109050) | GAL | 54,300 | $0.03 | $0.03 | $0.17 | $0.10 | $0.09 |
| 0920 | Mowing (8109901) | ACRE | 11.81 | $74.95 | $75.00 | $975.00 | $530.00 | $457.48 |
| 0930 | Turf reinforcement matting (TRM) type 1 (8151101) | MSY | 0.21 | $7,464.45 | $7,500.00 | $7,982.00 | $4,950.00 | $4,269.79 |
| 0940 | Temporary erosion control blanket (ecb) (8151110) | MSY | 1.59 | $2,892.72 | $2,900.00 | $2,141.00 | $2,000.00 | $1,728.25 |
| 0950 | Hydraulic erosion control product (hecp) - type 1 (8151201) | ACRE | 1.26 | $2,900.00 | $2,900.00 | $2,156.00 | $1,550.00 | $1,321.60 |
| 0960 | Silt fence (8153000) | LF | 5,100 | $3.15 | $3.15 | $3.11 | $3.75 | $3.05 |
| 0970 | Replace/repair silt fence (8153090) | LF | 510 | $3.15 | $3.15 | $2.26 | $6.25 | $5.34 |
| 0980 | Cleaning silt basins (8154010) | CY | 589 | $21.00 | $25.00 | $90.00 | $15.00 | $10.00 |
| 0990 | Removal of silt retained by silt fence (8154050) | LF | 1,275 | $15.00 | $4.00 | $13.00 | $4.00 | $10.00 |
| 1000 | Cleaning inlet structure filters (8156200) | EACH | 1 | $150.00 | $500.00 | $568.00 | $200.00 | $150.00 |
| 1010 | Inlet structure filter - type B (8156210) | EACH | 1 | $450.00 | $675.00 | $765.00 | $600.00 | $508.31 |
| 1020 | Aggregate no.5 or 57 for erosion control (8156410) | TON | 35 | $72.00 | $110.00 | $78.00 | $68.50 | $55.00 |
| 1030 | Stabilized construction entrance (8156490) | SY | 550 | $15.00 | $25.00 | $22.00 | $34.00 | $25.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of August 12, 2025. Compiled by Mirage Metrics.