SCDOT contract 4263310 bid tabulation
Replace SC 418 Bridge over Arnold Creek with Culvert. Let by South Carolina DOT on October 14, 2025, Spartanburg, District 3. 6 bids received; low bid $1,778,580 by Eagle Construction Company.
- Owner
- South Carolina DOT
- Letting
- 14 OCT 2025
- Pay items
- 68
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Eagle Construction Company | $1,778,580 | Low |
| 2 | Civil Pros Inc | $1,780,492 | 0.0% |
| 3 | Universal Civil Construction, LLC | $1,863,336 | +5.0% |
| 4 | Reeves Construction Company | $2,159,941 | +21% |
| 5 | Mountain Creek Contractors, Inc. | $2,486,972 | +40% |
| 6 | Aos Specialty Contractors, Inc. | $2,682,713 | +51% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Eagle Construction Company | 2. Civil Pros Inc | 3. Universal Civil Construction, LLC | 4. Reeves Construction Company | 5. Mountain Creek Contractors, Inc. | 6. Aos Specialty Contractors, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $86,000 | $100,000 | $90,000 | $100,000 | $120,000 | $270,700 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $14,000 | $20,000 | $45,000 | $40,785 | $71,500 | $33,532 |
| 0030 | Construction stakes, lines & grades (1050800) | EACH | 1 | $25,000 | $10,000 | $25,000 | $25,000 | $30,000 | $51,192 |
| 0040 | Utility staking (1052001) | LS | 1 | $4,500.00 | $3,000.00 | $5,000.00 | $4,200.00 | $10,000 | $17,816 |
| 0050 | CPM progress schedule (1080300) | LS | 1 | $2,000.00 | $7,500.00 | $1,200.00 | $13,000 | $13,400 | $16,747 |
| 0060 | Clearing & grubbing within roadway (2012000) | LS | 1 | $26,200 | $25,000 | $25,000 | $31,000 | $45,000 | $49,352 |
| 0070 | Removal & disposal of existing asphalt pavement (2025000) | SY | 749 | $8.00 | $11.00 | $11.00 | $15.00 | $15.83 | $13.00 |
| 0080 | Removal of exist. guardrail (2027801) | LF | 199 | $3.00 | $80.00 | $3.25 | $3.50 | $4.00 | $16.00 |
| 0090 | Removal & disposal of existing bridge (2028100) | LS | 1 | $70,000 | $28,000 | $65,000 | $75,000 | $34,000 | $136,000 |
| 0100 | Unclassified excavation (2031000) | CY | 402 | $20.00 | $40.00 | $56.00 | $57.00 | $39.00 | $77.00 |
| 0110 | Borrow excavation (2033000) | CY | 6,151 | $50.00 | $32.00 | $30.00 | $59.00 | $35.00 | $43.00 |
| 0120 | Muck excavation (2034000) | CY | 357 | $20.00 | $50.00 | $32.00 | $60.00 | $91.84 | $113.00 |
| 0130 | Geotextile, separation (2036020) | SY | 556 | $3.50 | $6.00 | $5.00 | $7.50 | $35.59 | $8.00 |
| 0140 | Structure excavation for culverts (2041000) | CY | 1,231 | $18.00 | $40.00 | $20.00 | $46.50 | $100.00 | $108.00 |
| 0150 | No. 57 stone for backfill (2052000) | TON | 430 | $62.25 | $45.00 | $84.00 | $91.00 | $229.67 | $123.00 |
| 0160 | Fine grading (2081001) | SY | 444 | $2.00 | $26.00 | $10.00 | $9.75 | $20.00 | $46.00 |
| 0170 | Dewatering system no. 001 (2991000) | LS | 1 | $114,000 | $55,000 | $65,000 | $23,500 | $37,098 | $39,183 |
| 0180 | Liquid asphalt binder PG64-22 (4011004) | TON | 52 | $700.00 | $775.00 | $653.50 | $700.00 | $999.62 | $1,069.00 |
| 0190 | Full depth asph. pav. patching 6" unif. (4012060) | SY | 100 | $375.00 | $87.60 | $60.00 | $300.00 | $100.00 | $363.00 |
| 0200 | Asphalt base course - type B (4020320) | TON | 480 | $175.00 | $150.00 | $140.00 | $128.00 | $200.00 | $314.00 |
| 0210 | Asphalt intermediate course type C (4030330) | TON | 348 | $175.00 | $160.00 | $150.00 | $180.00 | $225.00 | $482.00 |
| 0220 | Asphalt surface course type C (4040340) | TON | 200 | $160.00 | $200.00 | $145.00 | $195.00 | $250.00 | $580.00 |
| 0230 | Traffic control (6011000) | LS | 1 | $32,500 | $30,000 | $30,000 | $38,000 | $7,600.00 | $23,500 |
| 0240 | Barricade - type III (6041200) | LF | 156 | $50.00 | $30.00 | $27.65 | $29.00 | $25.00 | $29.00 |
| 0250 | Permanent construction signs (ground mounted) (6051120) | SF | 128 | $10.00 | $11.40 | $10.60 | $11.00 | $6.85 | $9.50 |
| 0260 | Permanent construction signs (barricade mounted) (6051125) | SF | 256 | $12.00 | $8.40 | $7.80 | $8.00 | $6.85 | $9.50 |
| 0270 | Construction zone electric changeable message sign (trailer (6062000) | EACH | 2 | $4,800.00 | $10,800 | $10,000 | $17,000 | $9,000.00 | $4,100.00 |
| 0280 | Type B - flashing light (608100B) | EACH | 16 | $160.00 | $94.20 | $85.00 | $90.00 | $170.00 | $113.00 |
| 0290 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 1,300 | $2.00 | $1.80 | $1.60 | $1.75 | $3.00 | $2.00 |
| 0300 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 1,300 | $2.00 | $1.80 | $1.60 | $1.75 | $3.00 | $2.00 |
| 0310 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 10 | $12.50 | $12.00 | $16.00 | $11.00 | $15.00 | $12.00 |
| 0320 | Milled-in rumble strip (6321000) | MI | 0.50 | $12,000 | $1,200.00 | $19,500 | $1,100.00 | $5,000.00 | $4,454.00 |
| 0330 | Conc. for structures - class 4000(culvert) (7011402) | CY | 340.30 | $975.00 | $1,364.25 | $1,520.00 | $1,500.00 | $1,709.30 | $1,292.00 |
| 0340 | Reinf. steel for structures (roadway) (7031100) | LB | 76,827 | $2.30 | $2.68 | $2.85 | $2.75 | $4.22 | $2.30 |
| 0350 | 24" smooth wall pipe (7143624) | LF | 136 | $98.00 | $160.00 | $123.00 | $228.00 | $204.00 | $229.00 |
| 0360 | 24" X 36" junction box (7192215) | EACH | 1 | $7,500.00 | $6,500.00 | $5,000.00 | $7,800.00 | $7,045.00 | $10,231 |
| 0370 | 12" temporary pipe slope drain (8034120) | LF | 320 | $40.00 | $20.00 | $33.00 | $25.00 | $31.80 | $60.00 |
| 0380 | Rip-rap (class A) (8041010) | TON | 9 | $90.00 | $110.00 | $105.00 | $535.00 | $171.00 | $355.00 |
| 0390 | Rip-rap (class B) (8041020) | TON | 53 | $76.00 | $110.00 | $105.00 | $140.00 | $176.00 | $182.00 |
| 0400 | Rip-rap (class C) (8041030) | TON | 965 | $91.00 | $130.00 | $125.00 | $102.00 | $186.00 | $113.00 |
| 0410 | Geotextile fabric for erosion control under riprap (class 2) (8042800) | SY | 6 | $10.00 | $150.00 | $3.50 | $140.00 | $15.00 | $18.00 |
| 0420 | Geotextile for erosion control under riprap(class 2)type C (8048210) | SY | 675 | $4.00 | $3.00 | $3.50 | $5.50 | $21.00 | $14.00 |
| 0430 | MT2 leading end treatment TL2 (8051155) | EACH | 2 | $2,600.00 | $2,616.00 | $2,415.00 | $4,600.00 | $3,400.00 | $2,590.00 |
| 0440 | MB trailing end treatment (8051710) | EACH | 2 | $1,750.00 | $1,779.00 | $1,650.00 | $119.00 | $1,600.00 | $1,764.00 |
| 0450 | MGS3 GR standard shoulder (8052100) | LF | 625 | $26.50 | $26.40 | $24.50 | $33.00 | $28.00 | $26.00 |
| 0460 | Non-mow strip under guardrail (8055250) | SY | 75 | $160.00 | $60.00 | $170.00 | $200.00 | $250.00 | $151.00 |
| 0470 | Temporary barrier fence (orange) (8068301) | LF | 400 | $7.00 | $4.50 | $4.50 | $3.50 | $6.00 | $4.00 |
| 0480 | Right of way marker(rebar and cap) (8091010) | EACH | 19 | $150.00 | $150.00 | $145.00 | $175.00 | $200.00 | $178.00 |
| 0490 | Right of way plat (8091050) | LS | 1 | $1,500.00 | $2,000.00 | $4,000.00 | $2,975.00 | $12,500 | $8,900.00 |
| 0500 | Permanent cover (8100100) | ACRE | 0.86 | $2,500.00 | $1,620.00 | $2,500.00 | $4,500.00 | $2,087.72 | $2,987.00 |
| 0510 | Temporary cover (8100200) | ACRE | 0.43 | $4,700.00 | $1,380.00 | $1,800.00 | $3,800.00 | $4,072.43 | $4,176.00 |
| 0520 | Fertilizer (nitrogen) (8104005) | LB | 86 | $11.50 | $1.80 | $2.40 | $2.35 | $10.00 | $3.50 |
| 0530 | Fertilizer (phosphoric acid) (8104010) | LB | 86 | $11.50 | $1.80 | $2.40 | $2.35 | $10.00 | $3.50 |
| 0540 | Fertilizer (potash) (8104015) | LB | 86 | $11.50 | $1.80 | $2.40 | $2.35 | $10.00 | $3.50 |
| 0550 | Agricultural granular lime (8105005) | LB | 1,710 | $0.75 | $0.48 | $1.20 | $1.19 | $0.45 | $3.50 |
| 0560 | Selective watering (8109050) | GAL | 54,300 | $0.10 | $0.01 | $0.02 | $0.01 | $0.09 | $0.20 |
| 0570 | Mowing (8109901) | ACRE | 2.57 | $600.00 | $300.00 | $350.00 | $594.00 | $523.98 | $1,428.00 |
| 0580 | Turf reinforcement matting (TRM) type 2 (8151102) | MSY | 0.23 | $7,150.00 | $5,400.00 | $4,850.00 | $4,500.00 | $6,146.55 | $8,360.00 |
| 0590 | Temporary erosion control blanket (ecb) (8151110) | MSY | 2.31 | $2,300.00 | $1,620.00 | $2,100.00 | $2,200.00 | $1,986.98 | $2,261.00 |
| 0600 | Hydraulic erosion control product (hecp) - type 2 (8151202) | ACRE | 0.64 | $3,300.00 | $4,200.00 | $4,000.00 | $4,150.00 | $2,845.55 | $5,929.00 |
| 0610 | Hydraulic erosion control product (hecp) - type 3 (8151203) | ACRE | 0.21 | $5,200.00 | $4,200.00 | $4,500.00 | $5,800.00 | $4,415.89 | $1,835.61 |
| 0620 | Sediment tubes for ditch checks (8152007) | LF | 250 | $16.00 | $12.00 | $10.00 | $12.50 | $14.00 | $38.00 |
| 0630 | Silt fence (8153000) | LF | 1,084 | $4.50 | $3.60 | $5.75 | $3.75 | $3.75 | $5.00 |
| 0640 | Cleaning silt basins (8154010) | CY | 6 | $100.00 | $300.00 | $125.00 | $1,000.00 | $60.00 | $97.00 |
| 0650 | Removal of silt retained by silt fence (8154050) | LF | 15 | $10.00 | $50.00 | $6.80 | $205.00 | $10.00 | $13.00 |
| 0660 | Inlet structure filter - type B (8156210) | EACH | 5 | $500.00 | $225.00 | $165.00 | $595.00 | $1,000.00 | $804.00 |
| 0670 | Aggregate no.5 or 57 for erosion control (8156410) | TON | 64 | $63.00 | $60.00 | $75.00 | $275.00 | $96.00 | $81.00 |
| 0680 | Stabilized construction entrance (8156490) | SY | 550 | $24.00 | $11.00 | $18.75 | $25.00 | $10.80 | $23.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of October 14, 2025. Compiled by Mirage Metrics.