SCDOT contract 4472470 bid tabulation
S-68 Dutchman Creek Road over Dutchman Creek Br Replacement. Let by South Carolina DOT on October 14, 2025, Union, District 4. 6 bids received; low bid $2,580,843 by Ipc Paving LLC.
- Owner
- South Carolina DOT
- Letting
- 14 OCT 2025
- Pay items
- 90
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ipc Paving LLC | $2,580,843 | Low |
| 2 | Dellinger, Inc. | $2,764,423 | +7.0% |
| 3 | Civil Pros Inc | $2,817,034 | +9.0% |
| 4 | Reeves Construction Company | $2,956,349 | +15% |
| 5 | Dane Construction, LLC | $3,079,350 | +19% |
| 6 | Aos Specialty Contractors, Inc. | $3,924,592 | +52% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ipc Paving LLC | 2. Dellinger, Inc. | 3. Civil Pros Inc | 4. Reeves Construction Company | 5. Dane Construction, LLC | 6. Aos Specialty Contractors, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $127,500 | $135,000 | $175,000 | $140,000 | $153,965 | $334,509 |
| 0020 | Bridge construction access (1031200) | LS | 1 | $78,445 | $100,000 | $17,500 | $125,000 | $75,000 | $195,910 |
| 0030 | Bonds and insurance (1032010) | LS | 1 | $51,000 | $40,000 | $60,000 | $85,000 | $96,230 | $102,030 |
| 0040 | Construction stakes, lines & grades (1050800) | EACH | 1 | $25,200 | $40,000 | $35,000 | $50,000 | $25,000 | $48,947 |
| 0050 | Utility staking (1052001) | LS | 1 | $10,000 | $3,000.00 | $3,000.00 | $5,000.00 | $7,500.00 | $18,355 |
| 0060 | CPM progress schedule (1080300) | LS | 1 | $12,000 | $12,000 | $5,000.00 | $2,751.00 | $25,000 | $29,368 |
| 0070 | Clearing & grubbing within right of way (2011000) | LS | 1 | $35,000 | $68,820 | $47,500 | $150,000 | $82,000 | $37,120 |
| 0080 | Removal & disposal of existing bridge (2028100) | LS | 1 | $80,000 | $150,000 | $150,000 | $150,000 | $124,060 | $246,876 |
| 0090 | Unclassified excavation (2031000) | CY | 987 | $41.00 | $27.00 | $60.00 | $27.00 | $27.00 | $113.00 |
| 0100 | Borrow excavation (2033000) | CY | 2,172 | $70.00 | $35.00 | $25.75 | $36.00 | $36.00 | $55.00 |
| 0110 | Geogrid reinforcement (uniaxial) (2037000) | SY | 456 | $18.00 | $18.00 | $7.95 | $12.00 | $12.00 | $11.00 |
| 0120 | Fine grading (2081001) | SY | 2,000 | $38.00 | $20.00 | $18.00 | $8.00 | $8.00 | $24.00 |
| 0130 | Maintenance stone (3059900) | TON | 300 | $115.00 | $65.00 | $45.00 | $34.00 | $34.00 | $90.00 |
| 0140 | Liquid asphalt binder PG64-22 (4011004) | TON | 50 | $685.00 | $685.00 | $775.00 | $700.00 | $798.19 | $1,101.00 |
| 0150 | Full depth asph. pav. patching 6" unif. (4012060) | SY | 200 | $175.00 | $175.00 | $100.00 | $160.50 | $104.75 | $241.00 |
| 0160 | Milling existing asphalt pavement 2.0" (4013120) | SY | 470 | $28.30 | $28.30 | $20.00 | $31.00 | $24.64 | $51.00 |
| 0170 | Asphalt base course - type B (4020320) | TON | 321 | $160.00 | $160.00 | $150.00 | $217.00 | $126.49 | $500.00 |
| 0180 | Asphalt intermediate course type C (4030330) | TON | 260 | $190.00 | $190.00 | $142.00 | $200.00 | $121.89 | $509.00 |
| 0190 | Asphalt surface course type C (4040340) | TON | 200 | $190.00 | $190.00 | $140.00 | $218.00 | $148.09 | $559.00 |
| 0200 | Asphalt surface course type E (4040360) | TON | 50 | $375.00 | $375.00 | $250.00 | $300.00 | $246.62 | $606.00 |
| 0210 | Traffic control (6011000) | LS | 1 | $12,700 | $5,000.00 | $43,000 | $50,000 | $15,000 | $27,532 |
| 0220 | Barricade - type III (6041200) | LF | 102 | $25.00 | $25.00 | $24.75 | $25.00 | $18.50 | $30.00 |
| 0230 | Permanent construction signs (ground mounted) (6051120) | SF | 128 | $10.00 | $6.85 | $10.00 | $6.85 | $5.95 | $9.00 |
| 0240 | Permanent construction signs (barricade mounted) (6051125) | SF | 70 | $7.00 | $8.95 | $7.00 | $8.95 | $6.50 | $9.00 |
| 0250 | Type B - flashing light (608100B) | EACH | 16 | $78.50 | $120.00 | $78.50 | $150.00 | $90.00 | $116.00 |
| 0260 | 4" white broken lines -(gaps excluded)-fast dry paint (6240005) | LF | 1,270 | $0.15 | $0.15 | $0.15 | $0.15 | $0.15 | $0.18 |
| 0270 | 4"yellow solid line(PVT.edge&no passing zone)-fast dry paint (6240110) | LF | 1,270 | $0.15 | $0.15 | $0.15 | $0.15 | $0.15 | $0.18 |
| 0280 | 4" white solid lines (PVT. edge lines) epoxy paint fast cure (6262010) | LF | 320 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $6.00 |
| 0290 | 4"yellow solid lines- PVT.edge&no passing zone - epoxy paint fast cure (6262110) | LF | 320 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $6.00 |
| 0300 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 1,270 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 | $2.50 |
| 0310 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 1,270 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 | $2.50 |
| 0320 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 10 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 | $12.00 |
| 0330 | Flat sheet, type III, fixed SZ. & MSG. sign (6510105) | SF | 20 | $25.00 | $26.00 | $24.99 | $26.00 | $20.00 | $17.00 |
| 0340 | U-section post for sign supports - 2P (6531205) | LF | 60 | $14.50 | $7.75 | $14.50 | $7.75 | $15.00 | $9.00 |
| 0350 | Furnish & install 2.0" schedule 80 PVC conduit (6750278) | LF | 804 | $22.00 | $35.77 | $2.05 | $30.00 | $20.00 | $16.00 |
| 0360 | Conc. for structures - class 4000 (7011400) | CY | 122.20 | $1,450.00 | $2,300.00 | $1,200.00 | $1,600.00 | $2,500.00 | $2,546.00 |
| 0370 | Reinf. steel for structures (bridge) (7031200) | LB | 44,526 | $1.70 | $1.08 | $2.00 | $1.75 | $2.00 | $3.00 |
| 0380 | Hoop reinforcing steel for structures (bridge) (7031220) | LB | 2,996 | $5.50 | $2.17 | $2.00 | $3.25 | $5.00 | $8.50 |
| 0390 | 3'-0" X 1'-9" cored slabs (7046010) | LF | 997.50 | $334.00 | $300.00 | $340.00 | $380.00 | $490.00 | $290.00 |
| 0400 | 3'-0" X 2'-0" cored slabs (7046020) | LF | 589.80 | $351.00 | $400.00 | $380.00 | $415.00 | $600.00 | $356.00 |
| 0410 | 42" MASH concrete barrier parapet/railing wall (7051050) | LF | 399 | $121.00 | $117.57 | $300.00 | $114.00 | $155.00 | $196.00 |
| 0420 | Pile driving set-UP (7110010) | EACH | 12 | $3,600.00 | $6,000.00 | $3,500.00 | $1,500.00 | $3,500.00 | $4,929.00 |
| 0430 | Reinf. pile tips (HP14 X 73) (7111560) | EACH | 12 | $173.00 | $169.06 | $135.00 | $300.00 | $475.00 | $420.00 |
| 0440 | Steel H bearing piling (HP14 X 73) (7112220) | LF | 216 | $150.00 | $58.63 | $70.30 | $115.00 | $70.55 | $97.00 |
| 0450 | Drilled shaft set-UP (7120006) | EACH | 4 | $24,000 | $35,000 | $87,500 | $30,000 | $3,500.00 | $9,177.00 |
| 0460 | Crosshole sonic logging setup (7120010) | EACH | 4 | $500.00 | $2,500.00 | $1,500.00 | $4,000.00 | $875.00 | $9,544.00 |
| 0470 | Drilled shaft with rock excavation - 36" diameter (7120142) | LF | 58 | $1,140.00 | $2,216.23 | $2,000.00 | $2,000.00 | $3,200.00 | $2,447.00 |
| 0480 | Drilled shaft with wet & dry excavation - 42" diameter (7120151) | LF | 66 | $1,120.00 | $2,191.29 | $2,000.00 | $2,000.00 | $3,200.00 | $2,447.00 |
| 0490 | Construction casing - 42" diameter (7120155) | LF | 71 | $227.00 | $510.26 | $450.00 | $450.00 | $475.00 | $553.00 |
| 0500 | 18" smooth wall pipe (7143618) | LF | 28 | $236.00 | $150.00 | $270.00 | $92.00 | $92.00 | $487.00 |
| 0510 | Catch basin -type 16 (7191605) | EACH | 1 | $8,000.00 | $5,500.00 | $5,249.60 | $8,700.00 | $8,700.00 | $18,431 |
| 0520 | 4' slope flume (6" curb style with cutoffs) (7199200) | LF | 42 | $350.00 | $250.00 | $425.00 | $350.00 | $250.00 | $253.00 |
| 0530 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 141 | $125.00 | $48.00 | $200.00 | $75.00 | $48.00 | $99.00 |
| 0540 | Elastomeric bearing (7243100) | EACH | 60 | $330.00 | $150.00 | $160.00 | $300.00 | $325.00 | $344.00 |
| 0550 | Waterproofing (7282000) | SY | 5.40 | $883.00 | $57.71 | $60.18 | $400.00 | $200.00 | $387.00 |
| 0560 | Waterproofing (bridge deck) (7293000) | SY | 493.60 | $54.00 | $57.71 | $10.52 | $84.50 | $60.00 | $83.00 |
| 0570 | Aggregate underdrain(agg#789)with 4"perf.pipe for struc (8011210) | TON | 36 | $155.00 | $212.33 | $60.00 | $140.00 | $120.00 | $262.00 |
| 0580 | 6" pipe underdrain (8021106) | LF | 500 | $35.00 | $75.00 | $15.00 | $35.00 | $15.00 | $57.00 |
| 0590 | Rip-rap (class A) (8041010) | TON | 108 | $150.00 | $85.00 | $110.00 | $85.00 | $85.00 | $171.00 |
| 0600 | Rip-rap (class B) (8041020) | TON | 69 | $140.00 | $90.00 | $110.00 | $110.00 | $110.00 | $147.00 |
| 0610 | Rip-rap (class C) (8041030) | TON | 484 | $155.00 | $95.00 | $120.00 | $125.00 | $125.00 | $105.00 |
| 0620 | Geotextile for erosion control under riprap(class 2)type C (8048210) | SY | 440 | $15.00 | $10.00 | $6.00 | $6.00 | $6.00 | $9.00 |
| 0630 | MT3 leading end treatment TL3 (8051151) | EACH | 4 | $2,500.00 | $2,500.00 | $3,500.00 | $3,100.00 | $2,500.00 | $3,059.00 |
| 0640 | MGS3 GR standard shoulder (8052100) | LF | 150 | $25.00 | $25.00 | $20.00 | $24.00 | $25.00 | $30.00 |
| 0650 | MTBBC2 MASH thrie-beam barrier connector TL2 (8053255) | EACH | 4 | $1,787.00 | $1,787.50 | $1,800.00 | $1,650.00 | $1,787.50 | $2,203.00 |
| 0660 | Flume inlet at guardrail (handwork) (8053257) | EACH | 3 | $3,000.00 | $5,000.00 | $4,500.00 | $10,000 | $5,000.00 | $7,293.00 |
| 0670 | Temporary barrier fence (orange) (8068301) | LF | 100 | $10.00 | $3.78 | $10.00 | $3.00 | $3.00 | $6.00 |
| 0680 | Right of way marker(rebar and cap) (8091010) | EACH | 14 | $125.00 | $280.00 | $100.00 | $300.00 | $325.00 | $245.00 |
| 0690 | Right of way plat (8091050) | LS | 1 | $4,500.00 | $6,000.00 | $2,500.00 | $3,200.00 | $3,200.00 | $9,177.00 |
| 0700 | Permanent cover (8100100) | ACRE | 0.93 | $1,572.90 | $1,590.00 | $2,100.00 | $4,000.00 | $4,000.00 | $2,447.00 |
| 0710 | Temporary cover (8100200) | ACRE | 0.47 | $920.00 | $940.00 | $4,150.00 | $3,300.00 | $3,300.00 | $3,059.00 |
| 0720 | Compost (8101105) | CY | 251 | $6.00 | $6.00 | $35.00 | $40.00 | $40.00 | $98.00 |
| 0730 | Fertilizer (nitrogen) (8104005) | LB | 93 | $1.95 | $1.94 | $9.00 | $4.00 | $4.00 | $2.50 |
| 0740 | Fertilizer (phosphoric acid) (8104010) | LB | 93 | $1.95 | $1.94 | $9.00 | $4.00 | $4.00 | $2.50 |
| 0750 | Fertilizer (potash) (8104015) | LB | 93 | $1.95 | $1.94 | $9.00 | $4.00 | $4.00 | $2.50 |
| 0760 | Agricultural granular lime (8105005) | LB | 3,630 | $0.95 | $0.94 | $0.45 | $0.20 | $0.20 | $0.75 |
| 0770 | Selective watering (8109050) | GAL | 54,300 | $0.07 | $0.07 | $0.09 | $0.05 | $0.05 | $0.37 |
| 0780 | Mowing (8109901) | ACRE | 2.80 | $436.00 | $437.00 | $750.00 | $400.00 | $400.00 | $104.00 |
| 0790 | Temporary erosion control blanket (ecb) (8151110) | MSY | 3 | $2,455.00 | $2,399.00 | $2,000.00 | $2,000.00 | $2,000.00 | $3,548.00 |
| 0800 | Hydraulic erosion control product (hecp) - type 3 (8151203) | ACRE | 2 | $3,597.00 | $3,633.00 | $3,100.00 | $5,700.00 | $5,700.00 | $5,507.00 |
| 0810 | Inlet structure filter - type F (weighted) (8152004) | LF | 1 | $565.00 | $70.00 | $1,500.00 | $30.00 | $30.00 | $61.00 |
| 0820 | Silt fence (8153000) | LF | 2,000 | $3.45 | $4.44 | $3.25 | $4.00 | $4.00 | $3.85 |
| 0830 | Replace/repair silt fence (8153090) | LF | 200 | $3.90 | $3.87 | $6.50 | $4.00 | $4.00 | $3.85 |
| 0840 | Floating turbidity barrier- light duty(6'depth) (8153106) | LF | 100 | $35.55 | $45.00 | $8.25 | $65.00 | $50.00 | $59.00 |
| 0850 | Removal of silt retained by silt fence (8154050) | LF | 500 | $21.00 | $7.50 | $5.00 | $4.00 | $4.00 | $7.50 |
| 0860 | Inlet filter cleaning (8154155) | EACH | 1 | $198.00 | $800.00 | $2,000.00 | $100.00 | $100.00 | $613.00 |
| 0870 | Temporary diversion dike with ditch (8155110) | LF | 100 | $100.00 | $40.00 | $100.00 | $120.00 | $120.00 | $72.00 |
| 0880 | Filter material for inlet structure filter - type D2 (8156217) | EACH | 1 | $672.00 | $1,800.00 | $1,200.00 | $135.00 | $135.00 | $1,103.00 |
| 0890 | Aggregate no.5 or 57 for erosion control (8156410) | TON | 155 | $172.00 | $70.00 | $55.00 | $49.00 | $49.00 | $83.00 |
| 0900 | Stabilized construction entrance (8156490) | SY | 550 | $40.00 | $14.00 | $10.00 | $15.00 | $15.00 | $24.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of October 14, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.