Intersection Improvement US 178 @ S-73/S-27. Let by South Carolina DOT on March 10, 2026, Anderson, Pickens, District 2, District 3. 6 bids received; low bid $2,295,097 by McMurria Grading LLC.
- Owner
- South Carolina DOT
- Letting
- 10 MAR 2026
- Pay items
- 95
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | McMurria Grading LLC | $2,295,097 | Low |
| 2 | Thrift Development Corporation | $2,492,059 | +9.0% |
| 3 | S and S Construction, Inc. of Anderson | $2,506,516 | +9.0% |
| 4 | Reeves Construction Company | $2,713,170 | +18% |
| 5 | Eagle Construction Company | $3,443,869 | +50% |
| 6 | King Asphalt, Inc. | $3,534,266 | +54% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. McMurria Grading LLC | 2. Thrift Development Corporation | 3. S and S Construction, Inc. of Anderson | 4. Reeves Construction Company | 5. Eagle Construction Company | 6. King Asphalt, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $25,000 | $35,625 | $24,500 | $115,000 | $120,000 | $109,750 |
| 0020 | Mobilization - subcontractor (1031100) | LS | 1 | $47,500 | $57,200 | $58,000 | $30,000 | $125,000 | $37,600 |
| 0030 | Bonds and insurance (1032010) | LS | 1 | $39,500 | $26,600 | $39,800 | $30,000 | $32,500 | $14,250 |
| 0040 | Construction stakes, lines & grades (1050800) | EACH | 1 | $15,500 | $20,000 | $19,250 | $25,000 | $66,000 | $50,250 |
| 0050 | Utility staking (1052001) | LS | 1 | $1,500.00 | $7,500.00 | $2,200.00 | $3,000.00 | $11,500 | $13,750 |
| 0060 | Small public water relocation no. ____ no. 1 (1052100) | EACH | 1 | $140,000 | $175,858 | $160,000 | $176,000 | $152,920 | $225,000 |
| 0070 | CPM progress schedule (1080300) | LS | 1 | $5,000.00 | $10,293 | $4,000.00 | $4,825.00 | $6,500.00 | $5,250.00 |
| 0080 | Clearing & grubbing within right of way (2011000) | LS | 1 | $25,000 | $49,500 | $88,500 | $55,000 | $91,000 | $355,000 |
| 0090 | Removal & disposal of existing asphalt pavement (2025000) | SY | 410 | $41.00 | $23.40 | $18.50 | $20.00 | $20.00 | $9.40 |
| 0100 | Unclassified excavation (2031000) | CY | 1,788 | $9.00 | $10.95 | $20.00 | $38.00 | $55.00 | $27.70 |
| 0110 | Borrow excavation (2033000) | CY | 7,769 | $19.00 | $30.35 | $25.88 | $33.50 | $49.00 | $37.60 |
| 0120 | Fine grading (2081001) | SY | 3,595 | $5.00 | $3.50 | $10.00 | $6.50 | $4.00 | $4.65 |
| 0130 | Flowable fill (2103000) | CY | 14 | $300.00 | $350.00 | $320.00 | $580.00 | $780.00 | $775.00 |
| 0140 | Maintenance stone (3059900) | TON | 100 | $42.00 | $50.15 | $40.00 | $130.00 | $52.00 | $85.00 |
| 0150 | Liquid asphalt binder PG64-22 (4011004) | TON | 181.84 | $784.00 | $615.00 | $700.00 | $640.00 | $650.00 | $615.00 |
| 0160 | Full depth asph. pav. patching 8" unif (4012080) | SY | 500 | $145.60 | $148.50 | $145.60 | $90.00 | $155.00 | $135.00 |
| 0170 | Milling existing asphalt pavement 2.0" (4013120) | SY | 1,750 | $11.20 | $7.70 | $11.20 | $7.75 | $9.00 | $7.00 |
| 0180 | Milling existing asphalt pavement (variable) (4013990) | SY | 350 | $16.80 | $33.00 | $16.80 | $34.00 | $40.00 | $30.00 |
| 0190 | Asphalt base course - type A (4020310) | TON | 1,443.10 | $134.40 | $123.75 | $134.40 | $88.00 | $125.00 | $112.50 |
| 0200 | Asphalt intermediate course type B (4030320) | TON | 497.60 | $137.76 | $176.00 | $137.76 | $135.00 | $175.00 | $160.00 |
| 0210 | Asphalt surface course type B (4040320) | TON | 1,460.20 | $138.88 | $126.50 | $138.88 | $101.00 | $130.00 | $115.00 |
| 0220 | Asphalt surface course type E (4040360) | TON | 165 | $156.80 | $154.00 | $156.80 | $275.00 | $160.00 | $140.00 |
| 0230 | Stained concrete pavement (8" uniform) (5019010) | SY | 440 | $187.40 | $189.75 | $225.00 | $200.00 | $240.00 | $180.00 |
| 0240 | Traffic control (6011000) | LS | 1 | $30,000 | $153,984 | $68,500 | $81,850 | $409,000 | $525,000 |
| 0250 | Barricade - type III (6041200) | LF | 84 | $33.06 | $29.65 | $30.00 | $28.00 | $40.00 | $26.50 |
| 0260 | Permanent construction signs (ground mounted) (6051120) | SF | 484 | $12.53 | $10.99 | $12.00 | $7.50 | $12.00 | $7.00 |
| 0270 | Permanent construction signs (barricade mounted) (6051125) | SF | 152 | $12.53 | $8.79 | $12.00 | $10.00 | $15.00 | $9.45 |
| 0280 | Type B - flashing light (608100B) | EACH | 8 | $50.00 | $92.40 | $110.00 | $185.00 | $225.00 | $175.00 |
| 0290 | Pavement markings (temporary paint) 24"X36" white triangle yield bar (609138A) | LF | 200 | $3.50 | $1.65 | $20.00 | $2.30 | $2.50 | $2.10 |
| 0300 | Temporary yellow pavement markers BI-dir.- 4"X4" (6092155) | EACH | 150 | $7.00 | $7.70 | $7.50 | $8.00 | $9.00 | $7.80 |
| 0310 | 4" white broken lines -(gaps excluded)-fast dry paint (6240005) | LF | 1,110 | $0.65 | $0.17 | $0.25 | $0.17 | $0.20 | $0.16 |
| 0320 | 4" white solid lines (PVT. edge lines)-fast dry paint (6240010) | LF | 26,500 | $0.65 | $0.17 | $0.25 | $0.17 | $0.20 | $0.16 |
| 0330 | 8"white solid lines (crosswalk& channelization)fast dry paint (6240015) | LF | 950 | $0.85 | $0.55 | $0.60 | $0.30 | $0.50 | $0.26 |
| 0340 | 24" white solid lines (stop/diagonal lines)-fast dry paint (6240025) | LF | 90 | $4.00 | $1.65 | $1.75 | $1.70 | $2.00 | $1.60 |
| 0350 | 4"yellow solid line(PVT.edge&no passing zone)-fast dry paint (6240110) | LF | 40,300 | $0.75 | $0.17 | $0.25 | $0.17 | $0.20 | $0.15 |
| 0360 | 6"yellow solid line(PVT.edge&no passing zone)-fast dry paint (6240111) | LF | 300 | $0.65 | $0.28 | $0.35 | $0.17 | $0.20 | $0.15 |
| 0370 | 6"yel solid lines on 6"conc.curb(top&side)-fast dry PNT (6240113) | LF | 1,300 | $0.65 | $0.28 | $0.35 | $1.15 | $1.25 | $1.05 |
| 0380 | 8" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271008) | LF | 160 | $2.00 | $2.20 | $2.25 | $5.75 | $6.00 | $5.25 |
| 0390 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 2,200 | $0.75 | $0.83 | $1.00 | $0.85 | $1.00 | $0.80 |
| 0400 | 8" white solid lines thermoplastic - 125 mil. (6271015) | LF | 200 | $3.50 | $2.20 | $2.25 | $2.85 | $3.00 | $2.65 |
| 0410 | 24IN X 36IN white triang. yield bar (gaps exc)thermo-125MIL (6271024) | LF | 100 | $30.00 | $11.00 | $11.00 | $16.00 | $20.00 | $15.80 |
| 0420 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 4,300 | $0.65 | $0.83 | $1.00 | $0.85 | $1.00 | $0.80 |
| 0430 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 100 | $7.90 | $7.70 | $7.75 | $8.00 | $9.00 | $7.90 |
| 0440 | Removal of pavement markings (6319505) | LF | 6,763 | $2.00 | $1.10 | $1.20 | $1.00 | $1.10 | $0.90 |
| 0450 | Flat sheet, type III, fixed SZ. & MSG. sign (6510105) | SF | 248.58 | $16.00 | $24.75 | $33.00 | $60.00 | $45.00 | $27.50 |
| 0460 | U-section post for sign supports - 3P (6531210) | LF | 517 | $15.00 | $14.25 | $15.70 | $37.00 | $23.00 | $15.80 |
| 0470 | Reflective sign post panels (6531500) | LF | 100 | $13.00 | $12.09 | $8.00 | $28.00 | $28.00 | $13.70 |
| 0480 | Design & installation of rdwy. lighting electrical system no. 1 (6581000) | EACH | 1 | $108,000 | $99,550 | $84,000 | $115,000 | $90,000 | $105,000 |
| 0490 | SGL.light STD.35'HT.AL.pole- incl top tenon MT. (6581145) | EACH | 8 | $13,700 | $13,475 | $15,680 | $11,500 | $17,000 | $10,750 |
| 0500 | 18" smooth wall pipe (7143618) | LF | 920 | $110.00 | $128.55 | $125.00 | $145.00 | $75.00 | $135.00 |
| 0510 | 24" smooth wall pipe (7143624) | LF | 32 | $125.00 | $192.45 | $155.00 | $275.00 | $110.00 | $180.00 |
| 0520 | 30" smooth wall pipe (7143630) | LF | 56 | $135.00 | $245.02 | $185.00 | $195.00 | $151.00 | $160.00 |
| 0530 | Cleaning existing pipe (7149999) | LF | 120 | $1.00 | $25.00 | $12.50 | $55.00 | $80.00 | $76.75 |
| 0540 | Catch basin-type 1 special(modified for conc.median barrier) (7191060) | EACH | 6 | $4,256.00 | $3,365.95 | $4,850.00 | $5,100.00 | $5,000.00 | $8,000.00 |
| 0550 | Catch basin -type 16 (7191605) | EACH | 12 | $7,000.00 | $5,473.20 | $6,995.00 | $8,150.00 | $7,500.00 | $8,275.00 |
| 0560 | Manhole with standard 4' X 4' box (7192107) | EACH | 1 | $5,040.00 | $3,865.95 | $5,500.00 | $7,000.00 | $5,500.00 | $9,050.00 |
| 0570 | Manhole with standard 5' X 5' box (7192108) | EACH | 2 | $6,720.00 | $5,134.85 | $6,950.00 | $7,400.00 | $7,300.00 | $9,050.00 |
| 0580 | Extra depth of box (7196000) | LF | 13 | $560.00 | $520.00 | $550.00 | $315.00 | $650.00 | $650.00 |
| 0590 | Beveling of pipe end (7199100) | EACH | 14 | $275.00 | $250.00 | $250.00 | $1,100.00 | $800.00 | $560.00 |
| 0600 | Concrete curb (transition) (7201100) | LF | 80 | $112.00 | $31.90 | $110.00 | $35.00 | $125.00 | $52.50 |
| 0610 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 1,650 | $39.20 | $31.90 | $40.00 | $42.00 | $40.00 | $35.00 |
| 0620 | Concrete median (7206000) | SY | 390 | $131.46 | $115.50 | $135.00 | $130.00 | $135.00 | $120.00 |
| 0630 | Planted median subsurface drainage (8020100) | SY | 140 | $92.50 | $85.40 | $120.00 | $180.00 | $130.00 | $145.00 |
| 0640 | Rip-rap (class A) (8041010) | TON | 250 | $90.00 | $72.15 | $89.00 | $235.00 | $86.00 | $175.00 |
| 0650 | Rip-rap (class B) (8041020) | TON | 570 | $90.00 | $72.15 | $89.00 | $143.00 | $84.00 | $190.00 |
| 0660 | Geotextile for erosion control under riprap(class 2)type C (8048210) | SY | 1,100 | $4.20 | $3.50 | $4.00 | $15.00 | $4.00 | $14.50 |
| 0670 | Reset fence (8071000) | LF | 564 | $3.50 | $34.80 | $0.05 | $17.00 | $55.00 | $5.25 |
| 0680 | Moving item no. 01 (8081000) | LS | 1 | $2,500.00 | $20,785 | $5,000.00 | $2,400.00 | $32,000 | $3,160.00 |
| 0690 | Right of way marker(rebar and cap) (8091010) | EACH | 37 | $165.00 | $109.25 | $160.00 | $140.00 | $250.00 | $330.00 |
| 0700 | Right of way plat (8091050) | LS | 1 | $3,500.00 | $4,283.75 | $3,000.00 | $5,300.00 | $6,500.00 | $9,475.00 |
| 0710 | Permanent cover (8100100) | ACRE | 5 | $3,200.00 | $1,100.00 | $1,100.00 | $1,300.00 | $1,850.00 | $1,800.00 |
| 0720 | Temporary cover (8100200) | ACRE | 10 | $1,250.00 | $935.00 | $850.00 | $1,300.00 | $1,200.00 | $1,575.00 |
| 0730 | Seeding - eragrostis curvula - weeping lovegrass (8102520) | MSY | 0.50 | $1,000.00 | $1,650.00 | $1,700.00 | $1,350.00 | $5,000.00 | $6,850.00 |
| 0740 | Fertilizer (nitrogen) (8104005) | LB | 500 | $0.90 | $0.83 | $1.00 | $3.70 | $2.50 | $2.65 |
| 0750 | Fertilizer (phosphoric acid) (8104010) | LB | 500 | $0.90 | $0.83 | $1.00 | $3.70 | $2.50 | $2.65 |
| 0760 | Fertilizer (potash) (8104015) | LB | 500 | $0.90 | $0.83 | $1.00 | $3.70 | $2.50 | $2.65 |
| 0770 | Agricultural granular lime (8105005) | LB | 10,000 | $0.66 | $0.22 | $0.40 | $0.45 | $1.25 | $0.35 |
| 0780 | Selective watering (8109050) | GAL | 54,300 | $0.01 | $0.05 | $0.02 | $0.09 | $0.06 | $0.05 |
| 0790 | Mowing (8109901) | ACRE | 30 | $55.00 | $500.00 | $10.00 | $400.00 | $525.00 | $475.00 |
| 0800 | Turf reinforcement matting (TRM) type 1 (8151101) | MSY | 2.10 | $2,100.00 | $3,850.00 | $3,800.00 | $4,000.00 | $5,100.00 | $5,525.00 |
| 0810 | Turf reinforcement matting (TRM) type 2 (8151102) | MSY | 0.30 | $2,200.00 | $3,850.00 | $3,800.00 | $9,750.00 | $5,100.00 | $18,500 |
| 0820 | Temporary erosion control blanket (ecb) (8151110) | MSY | 5.20 | $1,600.00 | $1,485.00 | $1,850.00 | $1,700.00 | $2,800.00 | $1,250.00 |
| 0830 | Hydraulic erosion control product (hecp) - type 1 (8151201) | ACRE | 6.75 | $1,500.00 | $1,815.00 | $1,850.00 | $1,500.00 | $1,900.00 | $1,575.00 |
| 0840 | Hydraulic erosion control product (hecp) - type 3 (8151203) | ACRE | 8.25 | $4,100.00 | $3,850.00 | $3,800.00 | $3,200.00 | $4,200.00 | $3,475.00 |
| 0850 | Inlet structure filter - type F (weighted) (8152004) | LF | 540 | $10.00 | $12.65 | $12.00 | $17.00 | $16.00 | $17.10 |
| 0860 | Inlet structure filter- type F (non-weighted) (8152006) | LF | 540 | $7.50 | $6.85 | $12.00 | $13.75 | $15.00 | $4.80 |
| 0870 | Sediment tubes for ditch checks (8152007) | LF | 1,100 | $8.00 | $7.35 | $11.85 | $14.50 | $15.00 | $10.25 |
| 0880 | Silt fence (8153000) | LF | 2,030 | $3.00 | $3.50 | $3.00 | $3.45 | $4.50 | $2.45 |
| 0890 | Replace/repair silt fence (8153090) | LF | 203 | $4.00 | $4.00 | $6.00 | $4.50 | $9.00 | $1.70 |
| 0900 | Cleaning silt basins (8154010) | CY | 10 | $10.00 | $50.00 | $10.00 | $576.00 | $400.00 | $185.00 |
| 0910 | Removal of silt retained by silt fence (8154050) | LF | 508 | $0.10 | $6.50 | $1.00 | $28.00 | $7.00 | $2.10 |
| 0920 | Inlet filter cleaning (8154155) | EACH | 57 | $15.00 | $125.00 | $10.00 | $172.00 | $200.00 | $295.00 |
| 0930 | Inlet structure filter - type A (8156219) | LF | 840 | $4.50 | $4.00 | $12.00 | $6.75 | $25.00 | $6.35 |
| 0940 | Aggregate no.5 or 57 for erosion control (8156410) | TON | 160 | $55.00 | $64.65 | $59.00 | $62.00 | $70.00 | $95.00 |
| 0950 | Stabilized construction entrance (8156490) | SY | 550 | $19.00 | $20.40 | $18.38 | $35.00 | $31.50 | $18.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of March 10, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.