20 contracts let by South Carolina DOT on September 10, 2024, $166,412,309 in low bids, a median of 2 bidders per contract.
- Owner
- South Carolina DOT
- Contracts
- 20
- Low bids, total
- $166,412,309
- Data through
- 13 OCT 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Source |
|---|---|---|---|---|---|---|---|---|
| 5669620 | 2025 Primary Pavement Improvement Program | District 6 | 2 | Apac-Atlantic Inc. | $16,941,456 | $16,990,631 | 0.0% | SCDOT |
| 1569780 | 2025 Primary Pavement Improvement Program -NHS | District 6 | 3 | Banks Construction Company | $13,479,315 | $15,788,239 | +17% | SCDOT |
| 4269150 | 2025 Primary Pavement Improvement Program | District 3 | 4 | Reeves Construction Company | $13,330,106 | $13,492,667 | +1.0% | SCDOT |
| 5269760 | 2025 Primary Pavement Improvement Program | District 2 | 2 | King Asphalt, Inc. | $12,464,652 | $15,303,763 | +23% | SCDOT |
| 2368800 | 2025 Primary Pavement Improvement Program | District 3 | 4 | King Asphalt, Inc. | $12,369,243 | $12,754,349 | +3.0% | SCDOT |
| 5170050 | I-20/I-26/I-126 - Corridor Improvements - Phase 3B Clearing and Grubbing DBB Project | District 1 | 2 | NJR Group, Inc | $11,720,137 | $20,970,169 | +79% | SCDOT |
| 5269770 | 2025 FA Secondary Pavement Improvement Program | District 2 | 1 | Satterfield Construction Company, Inc. | $10,194,203 | SCDOT | ||
| 5662380 | Safety Improvements - RSA S-75 (Ashley Phosphate Rd) | District 6 | 2 | Banks Construction Company | $10,092,950 | $14,845,858 | +47% | SCDOT |
| 1168710 | 2025 Primary Pavement Improvement Program | District 4 | 3 | King Asphalt, Inc. | $8,592,419 | $9,715,676 | +13% | SCDOT |
| 3269950 | 2025 FA Secondary Pavement Improvement Program | District 1 | 3 | Palmetto Corp. of Conway | $8,374,359 | $9,467,064 | +13% | SCDOT |
| 3469270 | 2025 NHS Primary Pavement Improvement Program | District 5 | 3 | King Asphalt, Inc. | $7,817,607 | $7,861,987 | +1.0% | SCDOT |
| 1469820 | 2025 Primary Pavement Improvement Program | District 7 | 2 | C.R. Jackson, Inc. | $7,780,734 | $8,120,125 | +4.0% | SCDOT |
| 2269280 | 2025 FA SECONDARY PAVEMENT IMPROVEMENT PROGRAM | District 5 | 3 | Coastal Asphalt, LLC | $7,754,226 | $8,768,133 | +13% | SCDOT |
| 2169300 | 2025 PRIMARY PAVEMENT IMPROVEMENT PROGRAM | District 5 | 3 | C.R. Jackson, Inc. | $7,619,132 | $7,805,480 | +2.0% | SCDOT |
| 0270130 | 2025 Primary Pavement Improvement Program | District 7 | 2 | Satterfield Construction Company, Inc. | $7,271,991 | $8,578,705 | +18% | SCDOT |
| 3170040 | 2025 Primary Pavement Improvement Program | District 1 | 2 | C.R. Jackson, Inc. | $6,562,820 | $6,611,501 | +1.0% | SCDOT |
| 2269530 | Georgetown CTC - state | District 5 | 3 | Coastal Asphalt, LLC | $1,268,871 | $1,404,234 | +11% | SCDOT |
| 8870240 | I-95 Resigning | District 1, District 5 | 2 | W.M. Roebuck, Incorporated | $1,215,399 | $1,311,952 | +8.0% | SCDOT |
| 5457171 | Type II Signal Rebuilds D4 | District 4 | 1 | W.M. Roebuck, Incorporated | $1,034,840 | SCDOT | ||
| 0168561 | Abbeville CTC - state | District 2 | 2 | Satterfield Construction Company, Inc. | $527,848 | $714,845 | +35% | SCDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than SCDOT received, the others did not match their published totals and are left out.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.