TDOT contract CN261075 bid tabulation

009,crp-32(108),15s032-f3-005,crp-33(169),62s033-f3-009,crp- 34(144),45s034-f3-004,crp-34(145),90s034-f3-007 the traffic signal modernization improvements at various intersections along various u.s. and state routes. Let by Tennessee DOT on October 2, 2026, Counties Cocke, Hawkins, Jefferson, Monroe, Scott, And Washington. 3 bids received; low bid $715,638 by Stansell Electric Company, Inc..

Owner
Tennessee DOT
Letting
02 OCT 2026
Pay items
42
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Stansell Electric Company, Inc.$715,638Low
2Davis H. Elliot Construction Company, Inc.$792,165+11%
3Progression Electric, LLC$903,399+26%
TDOT contract CN261075: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Stansell Electric Company, Inc.2. Davis H. Elliot Construction Company, Inc.3. Progression Electric, LLC
1Traffic control (712-01)LS1$41,550$20,000$26,650
2Street name sign (suspended 0.100IN thick) (713-14.22)SF48$181.00$60.00$23.50
3Suspended flat sheet aluminum sign (0.080" thick) (713-15.07)EACH8$608.00$650.00$422.00
4Signs (R10-11, 24" X 30", ground mounted) (713-16.20)EACH1$501.00$500.00$864.00
5Signs (R10-11, 24" X 30", strain pole mounted) (713-16.21)EACH1$446.00$500.00$519.00
6Remove and reinstall sign (street name) (713-16.70)EACH6$409.00$350.00$259.00
7Remove and reinstall sign (intersection number sign) (713-16.71)EACH2$297.00$250.00$244.00
8Plastic pavement marking (stop line) (716-02.05)LF75$15.00$25.00$21.15
9Plastic pavement marking (turn lane arrow) (716-02.06)EACH1$180.00$400.00$289.00
10Plastic pavement marking (straight-turn arrow) (716-04.01)EACH1$230.00$600.00$354.00
11Removal of pavement marking (stop line) (716-08.05)LF75$8.00$10.00$12.00
12Removal of pavement marking (turn lane arrow) (716-08.06)EACH1$100.00$100.00$191.00
13Removal of pavement marking (straight-turn arrow) (716-08.07)EACH1$125.00$1,500.00$285.00
14Mobilization (717-01)LS1$70,300$39,608$60,000
15Signal head assembly (130 A3) (730-02.02)EACH2$1,370.00$2,350.00$1,294.00
16Signal head assembly (130 A3 with backplate) (730-02.03)EACH9$1,320.00$2,300.00$1,507.00
17Signal head assembly (130) (730-02.07)EACH10$1,120.00$2,150.00$1,878.00
18Signal head assembly (130 with backplate) (730-02.09)EACH58$1,215.00$2,250.00$1,489.00
19Signal head assembly (140 A1) (730-02.13)EACH2$1,355.00$2,350.00$2,075.00
20Signal head assembly (150 A2H) (730-02.16)EACH4$1,565.00$2,450.00$2,331.00
21Signal head assembly (150 A2H with backplate) (730-02.17)EACH13$1,865.00$2,750.00$2,621.00
22Signal head assembly (260) (730-02.24)EACH6$1,705.00$2,500.00$3,212.00
23Signal head assembly (260 A3) (730-02.30)EACH1$1,740.00$2,550.00$3,192.00
24Signal head assembly (260 A6) (730-02.31)EACH1$1,780.00$2,650.00$3,192.00
25Modify existing electrical service connection (730-05.04)EACH1$980.00$3,000.00$3,455.00
26Signal cable - 5 conductor (730-08.02)LF2,125$3.00$4.00$2.85
27Signal cable - 7 conductor (730-08.03)LF7,310$3.60$5.00$3.00
28Span wire assembly (730-09.20)LF3,830$3.80$5.00$3.40
29Span wire assembly (location 1) (730-09.21)LF190$6.00$5.00$3.40
30Span wire assembly (location 2) (730-09.22)LF575$5.00$5.00$3.40
31Tether wire assembly - 1/4" diameter (730-10.01)LF4,595$3.00$5.00$2.85
32Vehicle detector (radar - stop line) (730-13.12)EACH8$8,115.00$8,500.00$12,118
33Vehicle detector (radar - advance) (730-13.13)EACH10$8,710.00$7,500.00$11,000
34Vehicle detector (360-degree camera) (730-13.14)EACH1$29,150$24,802$38,759
35Vehicle detector (radar/video) (730-13.16)EACH2$7,605.00$8,500.00$35,797
36Vehicle detector (radar-single unit multi-approach) (730-13.18)EACH4$13,300$18,000$19,220
37Cabinet maintenance (filter) (730-15.16)EACH11$115.00$1,000.00$85.00
38Modify cabinet (controller programming) (730-15.25)EACH1$196.00$2,250.00$306.00
39Modify cabinet (radar installation) (730-15.26)EACH6$5,975.00$2,250.00$306.00
40Modify cabinet (video installation) (730-15.27)EACH1$2,955.00$2,250.00$306.00
41Controller (atc) (730-16.04)EACH11$6,115.00$6,000.00$11,018
42Cabinet monitor unit (730-16.51)EACH11$1,590.00$2,000.00$2,891.00
TDOT contract CN261075: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of October 2, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy