TDOT contract CN262007 bid tabulation
The upgrade of interchange lighting on i-24 at exit 110 (s.r. 53, l.m. 13.00) and exit 114 (u.s. 41/s.r. 2, l.m. 17.25) in manchester. Let by Tennessee DOT on February 6, 2026, Coffee County. 4 bids received; low bid $696,025 by S & W Contracting Company, LLC.
- Owner
- Tennessee DOT
- Letting
- 06 FEB 2026
- Pay items
- 28
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | S & W Contracting Company, LLC | $696,025 | Low |
| 2 | Davis H. Elliot Construction Company, Inc. | $734,380 | +6.0% |
| 3 | Stansell Electric Company, Inc. | $820,844 | +18% |
| 4 | Shelby Electric Company, Inc. | $985,929 | +42% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. S & W Contracting Company, LLC | 2. Davis H. Elliot Construction Company, Inc. | 3. Stansell Electric Company, Inc. | 4. Shelby Electric Company, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | High-visibility construction fence (707-08.11) | LF | 1,560 | $3.30 | $1.75 | $1.80 | $3.60 |
| 2 | Traffic control (712-01) | LS | 1 | $16,860 | $30,008 | $28,790 | $93,600 |
| 3 | Flexible drums (channelizing) (712-04.01) | EACH | 20 | $40.00 | $32.00 | $33.00 | $42.00 |
| 4 | Signs (construction) (712-06) | SF | 1,088 | $9.00 | $6.95 | $7.00 | $9.00 |
| 5 | Arrow board (type C) (712-08.03) | EACH | 4 | $2,500.00 | $850.00 | $871.00 | $1,080.00 |
| 6 | Changeable message sign unit (713-16.01) | EACH | 4 | $9,800.00 | $5,700.00 | $5,840.00 | $7,200.00 |
| 7 | Jacked or bored conduit (714-03) | LF | 835 | $60.00 | $10.79 | $44.00 | $43.94 |
| 8 | Direct burial conduit (2" PVC, schedule 40) (714-03.01) | LF | 3,320 | $12.00 | $8.69 | $11.00 | $18.75 |
| 9 | Pull boxes (type C) (714-05.04) | EACH | 12 | $1,000.00 | $3,500.00 | $1,600.00 | $1,250.00 |
| 10 | Pull boxes (replace cover) (714-05.06) | EACH | 1 | $500.00 | $3,500.00 | $740.00 | $968.75 |
| 11 | Cable (1/C # 8 AWG) (714-06.04) | LF | 15,000 | $1.80 | $1.36 | $2.50 | $2.13 |
| 12 | Cable (1/C # 6 AWG) (714-06.05) | LF | 76,100 | $1.90 | $1.73 | $3.20 | $2.64 |
| 13 | Light standards (45' M.H., 15' arm) (714-08.01) | EACH | 17 | $6,800.00 | $6,000.00 | $5,540.00 | $8,144.23 |
| 14 | Light standards (add new handhole cover) (714-08.09) | EACH | 47 | $25.00 | $500.00 | $608.00 | $156.25 |
| 15 | Light standards (redrill for handhole cover) (714-08.10) | EACH | 6 | $25.00 | $750.00 | $1,100.00 | $312.50 |
| 16 | Foundation (only) for light standard (714-08.20) | EACH | 17 | $1,800.00 | $2,000.00 | $2,015.00 | $4,648.65 |
| 17 | Removal of light standard & foundation (714-08.32) | EACH | 17 | $500.00 | $1,000.00 | $761.00 | $2,375.00 |
| 18 | Removal of existing cobra head luminaire (714-08.33) | EACH | 102 | $250.00 | $500.00 | $266.00 | $181.25 |
| 19 | LED luminaires (118 watt) (714-09.47) | EACH | 64 | $740.00 | $1,000.00 | $742.00 | $658.38 |
| 20 | LED luminaires (82 watt) (714-09.48) | EACH | 38 | $705.00 | $1,000.00 | $692.00 | $633.44 |
| 21 | Control center (no. 1) (714-12.01) | LS | 1 | $11,420 | $22,690 | $11,650 | $13,125 |
| 22 | Control center (no. 2) (714-12.02) | LS | 1 | $11,420 | $22,690 | $11,950 | $13,125 |
| 23 | Electrical connection (control center no. 1) (714-25.01) | LS | 1 | $4,600.00 | $3,500.00 | $2,740.00 | $3,125.00 |
| 24 | Electrical connection (control center no. 2) (714-25.02) | LS | 1 | $4,600.00 | $3,500.00 | $2,740.00 | $3,125.00 |
| 25 | Mobilization (717-01) | LS | 1 | $40,000 | $36,719 | $64,300 | $89,630 |
| 26 | Temporary sediment tube 8IN (740-11.01) | LF | 3,050 | $3.30 | $2.50 | $2.60 | $6.38 |
| 27 | Seeding (with mulch) (801-01) | UNIT | 19 | $115.00 | $37.00 | $38.00 | $78.00 |
| 28 | Water (seeding & sodding) (801-03) | MG | 2 | $115.00 | $200.00 | $205.00 | $180.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of February 6, 2026. Compiled by Mirage Metrics.