TDOT contract CNZ180 bid tabulation

The repair of the bridge on lawnville road over i-40 (l.m. 1.70). Let by Tennessee DOT on June 27, 2025, Roane County. 3 bids received; low bid $345,996 by Southern Constructors, Inc..

Owner
Tennessee DOT
Letting
27 JUN 2025
Pay items
17
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Southern Constructors, Inc.$345,996Low
2Jamison Construction, LLC$432,118+25%
3Mid-State Construction Company, Inc.$575,134+66%
TDOT contract CNZ180: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Southern Constructors, Inc.2. Jamison Construction, LLC3. Mid-State Construction Company, Inc.
1Scoring shoulders (continuous) (16IN width) (411-12.01)LM0.42$1,800.00$3,000.00$155,000
2Reinforcing steel (repairs) (604-10.19)LS1$25,000$6,000.00$25,000
3Concrete repairs (604-10.42)CF26$1,000.00$1,525.00$3,250.00
4Traffic control (712-01)LS1$25,000$80,000$65,304
5Portable barrier rail (MASH TL-3) (712-02.10)LF180$120.00$95.00$125.00
6Portable barrier rail, reduced deflection (MASH TL-3) (712-02.12)LF110$200.00$150.00$200.00
7Temporary work zone crash cushion (MASH TL-3) (712-02.60)EACH1$5,000.00$12,000$3,500.00
8Flexible drums (channelizing) (712-04.01)EACH281$50.00$48.00$40.00
9Barrier rail delineator (712-04.50)EACH6$45.00$20.00$14.00
10Signs (construction) (712-06)SF308$15.00$12.00$8.15
11Arrow board (type C) (712-08.03)EACH1$2,000.00$1,800.00$625.00
12Queue protection truck (712-08.12)DAY10$2,000.00$1,600.00$1,400.00
13Portable queue warning system (712-08.14)DAY5$15,000$10,400$8,700.00
14Removable pavement marking (8" barrier line) (712-09.02)LF5,400$5.00$5.10$4.25
15Removable black-out tape (8IN) (712-09.31)LF3,940$5.00$5.60$4.65
16Changeable message sign unit (713-16.01)EACH3$8,000.00$6,800.00$8,000.00
17Mobilization (717-01)LS1$34,000$102,500$150,000
TDOT contract CNZ180: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of June 27, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy