TxDOT contract A00060109 bid tabulation
Install Raised Median, FM 1938 (FM 1709 to STARNES RD). Let by Texas DOT on November 6, 2025, Tarrant, Fort Worth District. 9 bids received; low bid $9,907,252 by Ragle Construction, Inc., -13% against the engineer's estimate of $11,406,087.
- Owner
- Texas DOT
- Letting
- 06 NOV 2025
- Pay items
- 69
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ragle Construction, Inc. | $9,907,252 | Low | -13% |
| 2 | Austin Bridge & Road Services, LP | $10,302,389 | +4.0% | -10% |
| 3 | Jagoe-Public Company | $10,609,372 | +7.0% | -7.0% |
| 4 | Reynolds Asphalt & Construction Company | $11,065,988 | +12% | -3.0% |
| 5 | Northeastern Pavers, LLC | $11,568,497 | +17% | +1.0% |
| 6 | O. Trevino Construction, LLC | $12,634,600 | +28% | +11% |
| 7 | Texas Materials Group, Inc. | $12,986,232 | +31% | +14% |
| 8 | Grey Sky Construction LLC | $13,816,731 | +39% | +21% |
| 9 | Peachtree Construction, LTD. | $14,534,870 | +47% | +27% |
Engineer's estimate: $11,406,087.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Ragle Construction, Inc. | 2. Austin Bridge & Road Services, LP | 3. Jagoe-Public Company | 4. Reynolds Asphalt & Construction Company | 5. Northeastern Pavers, LLC | 6. O. Trevino Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (mowstrip) (104-7005) | LF | 263 | $8.80 | $8.81 | $12.00 | $10.45 | $10.00 | $13.50 | |
| 2 | Removing concrete (medians) (104-7008) | SY | 319 | $40.00 | $20.40 | $32.40 | $15.00 | $37.20 | $36.00 | $16.00 |
| 3 | Removing concrete (curb & gutter) (104-7017) | LF | 693 | $20.00 | $10.70 | $11.74 | $6.00 | $13.50 | $12.00 | $12.00 |
| 4 | Remove (2"-6") TRT/untrt base & asphalt pavement (105-7002) | SY | 34,258 | $10.43 | $6.80 | $7.21 | $15.00 | $17.05 | $8.00 | $11.50 |
| 5 | Furn & place topsoil (6") (160-7004) | SY | 1,052 | $25.00 | $29.00 | $11.05 | $13.00 | $20.45 | $30.00 | $20.00 |
| 6 | Block sodding (162-7002) | SY | 1,052 | $8.50 | $15.50 | $6.85 | $8.00 | $14.25 | $25.00 | $7.50 |
| 7 | Fertilizer (166-7001) | ACRE | 0.22 | $2,000.00 | $500.00 | $3,000.00 | $5,000.00 | $2,700.00 | $5,000.00 | $3,200.00 |
| 8 | Vegetative watering (168-7001) | TGL | 22 | $30.00 | $355.00 | $175.00 | $220.00 | $530.00 | $225.00 | $195.00 |
| 9 | Asphalt (AC-20-5TR) (316-7007) | GAL | 65,518 | $5.00 | $5.00 | $4.00 | $5.70 | $3.15 | $7.60 | |
| 10 | Aggregate (type-B, GR-4)(sac-B) (316-7173) | CY | 1,567 | $175.00 | $175.00 | $150.00 | $366.00 | $50.00 | $377.00 | |
| 11 | D-GR HMA type D PG64-22 (level-UP) (341-7046) | TON | 500 | $125.00 | $154.00 | $169.05 | $200.00 | $296.90 | $175.00 | $222.00 |
| 12 | SP mixes SP-C PG70-28 (344-7023) | TON | 1,734 | $185.00 | $165.30 | $230.00 | $115.00 | $315.50 | $325.00 | $255.00 |
| 13 | SP mixes SP-C sac-A PG70-28 (344-7024) | TON | 20,423 | $146.80 | $150.42 | $115.00 | $156.50 | $195.00 | $160.00 | |
| 14 | Tack coat (346-7028) | GAL | 1,014 | $5.00 | $50.00 | $4.00 | $6.00 | $10.40 | $4.00 | $11.00 |
| 15 | Flexible pavement structure repair(13") (351-7012) | SY | 695 | $120.00 | $180.00 | $300.00 | $161.75 | $140.00 | $185.00 | |
| 16 | Planing asphalt concrete pavement (2" to 4 1/2") (354-7081) | SY | 172,416 | $2.00 | $2.20 | $3.50 | $4.20 | $3.75 | $4.20 | |
| 17 | Riprap (mow strip)(4 in) (432-7013) | CY | 72 | $657.00 | $567.22 | $1,400.00 | $671.00 | $800.00 | $1,300.00 | |
| 18 | Resizing and sealing joints (438-7009) | LF | 210 | $46.00 | $46.00 | $1,000.00 | $71.00 | $160.00 | $40.00 | |
| 19 | Mobilization (500-7001) | LS | 1 | $1,028,508 | $990,000 | $1,133,263 | $1,175,000 | $515,000 | $1,500,000 | $1,200,000 |
| 20 | Barricades, signs and traffic handling (502-7001) | MO | 23 | $10,000 | $58,000 | $45,000 | $15,000 | $15,200 | $10,000 | $27,100 |
| 21 | Portable changeable message sign (503-7002) | EACH | 6 | $12,000 | $16,600 | $15,000 | $20,000 | $21,750 | $15,000 | $15,000 |
| 22 | TMA (stationary) (505-7001) | DAY | 550 | $200.00 | $346.00 | $316.25 | $350.00 | $217.00 | $0.01 | $200.00 |
| 23 | TMA (mobile operation) (505-7003) | DAY | 45 | $310.00 | $675.00 | $10.00 | $350.00 | $1,010.00 | $0.01 | $780.00 |
| 24 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 2,495 | $7.50 | $4.75 | $3.95 | $4.75 | $4.75 | $6.00 | $4.50 |
| 25 | Biodegradable erosion control logs (remove) (506-7046) | LF | 2,495 | $3.00 | $1.10 | $1.65 | $2.00 | $3.00 | $1.50 | $1.75 |
| 26 | Colored textured concrete (4") (527-7001) | SY | 6,031 | $150.00 | $81.00 | $158.70 | $185.00 | $170.65 | $180.00 | $130.00 |
| 27 | Concrete curb & gutter (type II) (529-7009) | LF | 14,702 | $60.00 | $22.00 | $21.88 | $35.00 | $29.50 | $35.00 | $45.00 |
| 28 | Concrete curb (dowel) (529-7014) | LF | 275 | $55.00 | $47.00 | $23.36 | $80.00 | $27.65 | $19.00 | $26.00 |
| 29 | Driveways (ACP) (type 2) (530-7012) | SY | 354 | $86.00 | $60.23 | $25.00 | $125.00 | $75.00 | $133.00 | |
| 30 | Concrete median (536-7002) | SY | 4,925 | $200.00 | $250.00 | $244.67 | $350.00 | $308.00 | $285.00 | $475.00 |
| 31 | Metal W-beam guard fence (timber post) (540-7001) | LF | 2,050 | $20.25 | $20.25 | $25.00 | $29.50 | $35.00 | $22.00 | |
| 32 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,275.00 | $1,525.00 | $3,000.00 | $2,190.00 | $2,700.00 | $2,550.00 | |
| 33 | Short radius (28") (540-7013) | LF | 75 | $36.00 | $36.00 | $50.00 | $29.60 | $75.00 | $38.00 | |
| 34 | Downstream anchor terminal section (540-7015) | EACH | 12 | $1,300.00 | $1,300.00 | $1,500.00 | $1,420.00 | $2,100.00 | $1,375.00 | |
| 35 | Remove metal beam guard fence (542-7001) | LF | 1,725 | $3.00 | $3.00 | $3.00 | $3.00 | $4.00 | $3.00 | |
| 36 | Remove terminal anchor section (542-7002) | EACH | 5 | $300.00 | $300.00 | $300.00 | $180.00 | $400.00 | $320.00 | |
| 37 | Remove downstream anchor terminal (542-7003) | EACH | 2 | $300.00 | $300.00 | $300.00 | $180.00 | $400.00 | $320.00 | |
| 38 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 2 | $300.00 | $300.00 | $300.00 | $240.00 | $400.00 | $320.00 | |
| 39 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $2,875.00 | $2,875.00 | $5,000.00 | $3,500.00 | $4,200.00 | $3,100.00 | |
| 40 | Guardrail end treatment (remove) (544-7003) | EACH | 7 | $300.00 | $300.00 | $300.00 | $300.00 | $400.00 | $320.00 | |
| 41 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 6 | $1,000.00 | $850.00 | $750.00 | $900.00 | $1,500.00 | $1,000.00 | $1,000.00 |
| 42 | Remove delin & object marker assms (658-7078) | EACH | 347 | $25.00 | $40.00 | $23.00 | $40.00 | $31.35 | $300.00 | $21.00 |
| 43 | Work zone pavement marking removing (W)(arrow) (662-7082) | EACH | 94 | $29.00 | $29.00 | $170.00 | $37.00 | $300.00 | $35.00 | |
| 44 | Work zone pavement marking removing (W)(word) (662-7092) | EACH | 94 | $29.00 | $29.00 | $200.00 | $37.00 | $150.00 | $35.00 | |
| 45 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 6,048 | $2.00 | $0.50 | $4.00 | $2.00 | $2.00 | $1.40 | |
| 46 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 190 | $5.00 | $0.75 | $0.75 | $2.25 | $0.95 | $1.75 | $0.90 |
| 47 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 34,281 | $2.00 | $0.75 | $0.75 | $1.25 | $0.95 | $0.87 | $0.90 |
| 48 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 1,689 | $5.50 | $5.50 | $9.00 | $7.00 | $6.55 | $6.75 | |
| 49 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 209 | $230.00 | $119.00 | $119.00 | $170.00 | $150.50 | $125.00 | $150.00 |
| 50 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 209 | $250.00 | $128.00 | $128.00 | $200.00 | $162.00 | $150.00 | $160.00 |
| 51 | Type I high perf PM (W)6"(broken)(100MIL) (666-7290) | LF | 20,162 | $0.50 | $0.50 | $0.80 | $0.65 | $0.60 | $0.60 | |
| 52 | Type I high perf PM (W)6"(solid)(100MIL) (666-7293) | LF | 37,741 | $0.50 | $0.50 | $0.80 | $0.65 | $0.60 | $0.60 | |
| 53 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 58,580 | $1.00 | $0.48 | $0.48 | $0.80 | $0.65 | $0.60 | $0.60 |
| 54 | Pavement sler 6" (666-7347) | LF | 96,321 | $0.50 | $0.09 | $0.09 | $0.15 | $0.15 | $0.17 | $0.11 |
| 55 | Pavement sler 8" (666-7348) | LF | 34,281 | $1.70 | $0.12 | $0.12 | $0.20 | $0.15 | $0.25 | $0.20 |
| 56 | Pavement sler 24" (666-7352) | LF | 1,689 | $0.40 | $0.40 | $1.00 | $0.50 | $1.35 | $0.70 | |
| 57 | Pavement sler (arrow) (666-7353) | EACH | 209 | $50.00 | $10.00 | $10.00 | $25.00 | $12.65 | $25.00 | $12.00 |
| 58 | Pavement sler (word) (666-7354) | EACH | 209 | $60.00 | $10.00 | $10.00 | $30.00 | $12.65 | $30.00 | $12.00 |
| 59 | Reflectorized pavement marker type I-C (672-7002) | EACH | 2,732 | $6.00 | $3.38 | $3.38 | $6.00 | $4.30 | $4.25 | $5.00 |
| 60 | Eliminating existing PM & markers (4") (677-7001) | LF | 19,277 | $1.25 | $0.45 | $0.45 | $0.20 | $0.60 | $0.33 | $0.60 |
| 61 | Eliminating existing PM & markers (6") (677-7002) | LF | 4,389 | $1.25 | $0.49 | $0.49 | $0.20 | $0.65 | $0.33 | $0.60 |
| 62 | Eliminating existing PM & markers (24") (677-7008) | LF | 302 | $7.00 | $1.90 | $1.90 | $2.00 | $2.40 | $2.60 | $2.50 |
| 63 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 68 | $90.00 | $38.00 | $38.00 | $35.00 | $48.10 | $37.00 | $50.00 |
| 64 | Eliminating existing PM & markers (word) (677-7015) | EACH | 42 | $90.00 | $38.00 | $38.00 | $35.00 | $48.10 | $43.00 | $50.00 |
| 65 | Pavement surface preparation for marking (6") (678-7002) | LF | 58,580 | $1.00 | $0.10 | $0.10 | $0.01 | $0.15 | $0.02 | $0.15 |
| 66 | Pavement surface preparation for marking (8") (678-7004) | LF | 19,627 | $1.70 | $0.15 | $0.15 | $0.05 | $0.20 | $0.06 | $0.20 |
| 67 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 115 | $60.00 | $8.00 | $8.00 | $10.00 | $10.15 | $11.25 | $10.50 |
| 68 | Pavement surface preparation for marking (word) (678-7016) | EACH | 115 | $80.00 | $8.00 | $8.00 | $10.00 | $10.15 | $13.00 | $10.50 |
| 69 | Bridge joint repair (armor) (785-7004) | LF | 210 | $110.00 | $96.00 | $120.00 | $125.00 | $70.00 | $62.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 6, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.