TxDOT contract A00120208 bid tabulation

Rehabilitate Existing Roadway, US 84 (FM 2458 to CR 386). Let by Texas DOT on March 4, 2025, Garza, Lubbock District. 5 bids received; low bid $13,312,185 by A. L. Helmcamp, Inc., -13% against the engineer's estimate of $15,389,416.

Owner
Texas DOT
Letting
04 MAR 2025
Pay items
65
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1A. L. Helmcamp, Inc.$13,312,185Low-13%
2Duininck, Inc.$16,158,744+21%+5.0%
3RK Hall, LLC$16,251,642+22%+6.0%
4James Hamilton Construction Co.$17,314,509+30%+13%
5Kiewit Infrastructure South Co.$18,368,117+38%+19%
TxDOT contract A00120208: bids by rank

Engineer's estimate: $15,389,416.

Bid tabulation

LinePay itemUnitQuantityEstimate1. A. L. Helmcamp, Inc.2. Duininck, Inc.3. RK Hall, LLC4. James Hamilton Construction Co.5. Kiewit Infrastructure South Co.
1Removing concrete (mowstrip) (104-7005)LF2,300$30.00$15.00$14.50$14.58$15.00$22.89
2Excavation (roadway) (110-7001)CY5,725$30.00$21.00$20.00$20.35$20.00$18.21
3Backfill (type B) (134-7002)STA1,120$250.00$95.00$95.50$195.20$400.00$83.64
4Blading (150-7001)STA1,120$200.00$70.00$40.50$132.52$300.00$337.04
5Emuls asphalt (erosion control)(CSS-1H) (314-7011)GAL25,903$3.50$5.00$4.00$4.67$4.30$2.65
6Fog seal (CSS-1H) (315-7004)GAL7,100$6.00$5.00$4.00$4.77$5.00$3.81
7SP mixes SP-C sac-B PG70-28 (344-7025)TON22,014$180.00$150.00$191.50$174.50$203.00$202.06
8Tack coat (344-7077)GAL19,890$4.50$4.50$3.50$7.45$5.50$5.93
9Tom-C PG76-28 sac-A (347-7003)TON22,956$160.00$178.00$210.00$187.22$217.00$226.68
10Tack coat (347-7011)GAL55,891$4.50$4.50$3.50$4.44$5.50$5.93
11Flexible pavement structure repair(3") (351-7002)SY18,866$40.00$37.00$35.00$44.85$32.00$46.63
12Flexible pavement structure repair(8") (351-7007)SY19,865$100.00$93.00$90.00$97.18$94.00$106.53
13Planing asphalt concrete pavement(0" to 2") (354-7032)SY52,224$4.00$1.70$3.00$7.17$2.90$1.99
14Planing asphalt concrete pavement(0" to 4") (354-7034)SY80,546$4.00$3.50$5.00$8.48$4.30$2.64
15Cem stabil BKFL (400-7010)CY47$270.00$380.00$357.50$340.00$459.96
16Concrete structure repair (vertical & overhead) (429-7007)SF28$220.00$540.00$385.00$450.00$657.09
17Riprap (mow strip)(5 in) (432-7014)CY107$900.00$725.00$645.00$660.00$660.00$788.51
18RC pipe (CL III)(24 in) (464-7005)LF204$120.00$195.00$165.00$155.00$243.68
19Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH1$4,400.00$3,800.00$2,200.00$3,500.00$4,599.65
20Mobilization (500-7001)LS1$1,399,000$814,000$1,600,000$1,499,778$1,421,000$1,525,758
21Barricades, signs and traffic handling (502-7001)MO16$20,000$9,000.00$24,500$11,472$35,000$45,000
22Portable changeable message sign (503-7001)DAY780$150.00$50.00$81.00$78.32$50.00$64.03
23TMA (stationary) (505-7001)DAY416$300.00$150.00$270.00$281.27$300.00$563.49
24TMA (mobile operation) (505-7003)DAY51$1,000.00$150.00$970.00$415.22$900.00$1,111.03
25Rock filter dams (remove) (506-7011)LF50$40.00$54.00$73.60$40.00$72.28
26Construction exits (install) (type 1) (506-7020)SY666$50.00$15.00$64.50$52.82$35.00$78.85
27Construction exits (remove) (506-7024)SY333$25.00$4.00$27.00$34.34$8.00$32.85
28Sandbags for erosion control (506-7035)EACH1,352$20.00$10.00$31.50$26.97$22.50$38.11
29Temporary sediment control fence (install) (506-7039)LF480$5.00$8.50$8.65$23.38$9.00$10.51
30Temporary sediment control fence (remove) (506-7041)LF240$2.00$2.00$5.40$22.23$4.50$6.57
31Biodegradable erosion control logs (install) (18") (506-7045)LF8,685$5.00$9.00$9.70$7.83$7.50$11.83
32Biodegradable erosion control logs (remove) (506-7046)LF4,343$3.00$1.00$2.15$1.83$4.00$2.63
33Rock filter dams (install) (type 1) 6:1 (506-7047)LF100$125.00$135.00$124.08$75.00$164.27
34Mill rumble strips (asphalt) (shoulder) (533-7001)LF176,600$0.30$0.23$0.09$0.22$0.20$0.14
35Metal W-beam guard fence (steel post) (540-7002)LF4,525$30.00$31.00$32.00$34.65$34.00$41.40
36Downstream anchor terminal section (540-7015)EACH12$1,800.00$1,800.00$1,925.00$2,000.00$2,299.82
37Metal thrie-beam guard fence (steel post) (540-7020)EACH4$1,600.00$2,500.00$2,500.00$3,547.50$3,500.00$4,238.25
38Remove metal beam guard fence (542-7001)LF4,382$6.00$3.20$3.25$3.30$3.30$3.94
39Remove terminal anchor section (542-7002)EACH14$500.00$320.00$325.00$330.00$330.00$394.26
40Cable barrier system (relocate)(TL-4) (543-7020)LF2,300$30.00$17.00$27.00$27.50$28.00$32.85
41Guardrail end treatment (install) (544-7001)EACH14$5,000.00$3,400.00$3,500.00$3,822.50$3,750.00$4,566.79
42Guardrail end treatment (remove) (544-7003)EACH14$800.00$320.00$325.00$330.00$330.00$394.26
43Relocate SM RD SN sup&AM type 10BWG (644-7065)EACH40$700.00$850.00$1,000.00$1,045.00$1,050.00$1,248.48
44Install delineator assembly (D-SW)SZ 1(WFLX)GF2 (658-7001)EACH39$60.00$68.00$54.00$55.00$55.00$65.71
45Install delineator assembly (D-SY)SZ 1(yflx)GF2 (658-7021)EACH26$60.00$68.00$54.00$55.00$55.00$65.71
46Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059)EACH1$110.00$220.00$225.50$230.00$269.41
47Work zone pavement marking non-removing (W)6"(broken) (662-7005)LF16,620$0.30$0.26$0.30$0.31$0.33$0.39
48Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF66,452$0.30$0.26$0.30$0.31$0.31$0.37
49Work zone pavement marking non-removing (W)8"(solid) (662-7012)LF3,600$0.80$0.50$0.30$0.31$0.44$0.53
50Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF66,452$0.30$0.26$0.30$0.31$0.31$0.37
51Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH15,596$2.00$1.20$1.60$2.48$1.40$2.63
52Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018)LF1,300$1.00$1.26$1.20$1.21$1.37$1.64
53Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF3,855$1.00$1.05$1.10$1.10$1.20$1.45
54Type I high perf PM (W)6"(broken)(100MIL) (666-7290)LF25,950$0.50$0.75$0.67$0.68$0.90$1.05
55Type I high perf PM (W)6"(solid)(100MIL) (666-7293)LF97,000$0.50$0.75$0.67$0.68$0.73$0.88
56Type I high perf PM (Y)6"(solid)(100MIL) (666-7305)LF103,800$0.50$0.75$0.67$0.68$0.73$0.88
57Prefabricated PM type C (W)(24")(solid) (668-7089)LF900$20.00$15.00$21.50$22.00$19.00$23.00
58Prefabricated PM type C (W)(arrow) (668-7091)EACH40$500.00$320.00$325.00$330.00$275.00$328.55
59Prefabricated PM type C (W)(36")(yld tri) (668-7111)EACH200$100.00$26.00$26.00$26.40$66.00$78.85
60Reflectorized pavement marker type II-C-R (672-7006)EACH1,922$3.00$4.50$4.90$5.01$5.50$6.57
61Full - width mowing (730-7019)CYC2$20,000$7,500.00$6,500.00$8,847.05$4,200.00$8,330.29
62Litter removal (734-7002)CYC2$5,000.00$5,000.00$5,200.00$12,837$2,100.00$5,264.68
63Reinforced fab for asphalt PVMNT overlays (3002-7001)SY19,865$7.00$7.00$7.55$7.80$7.20$13.66
64Asphalt for reinforced fab (PG70-28) (3002-7003)GAL2,980$6.00$6.50$3.15$22.60$6.50$14.13
65Temporary speed monitor sys (6016-7001)EACH2$15,000$12,000$8,100.00$11,480$16,500$8,673.62
TxDOT contract A00120208: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of March 4, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy