TxDOT contract A00121395 bid tabulation
Widen Road - Add Lanes, UPLAND AVE (UPLAND AVENUE, FROM 82ND STREET to 98TH STREET). Let by Texas DOT on April 8, 2026, Lubbock, Lubbock District. 5 bids received; low bid $14,858,178 by L A Fuller & Sons Construction, LTD., +2.7% against the engineer's estimate of $14,464,478.
- Owner
- Texas DOT
- Letting
- 08 APR 2026
- Pay items
- 147
- Data through
- 19 NOV 2026
2 of the 5 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | L A Fuller & Sons Construction, LTD. | $14,858,178 | Low | +3.0% |
| 5 | Duininck, Inc. | $18,999,996 | +28% | +31% |
Engineer's estimate: $14,464,478.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. L A Fuller & Sons Construction, LTD. | 2. Duininck, Inc. |
|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 79 | $15,000 | $1,484.20 | $12,500 |
| 2 | Removing concrete (pavement) (104-7001) | SY | 223 | $75.00 | $45.90 | $94.50 |
| 3 | Removing concrete (riprap) (104-7006) | SY | 40 | $250.00 | $41.05 | $90.50 |
| 4 | Removing concrete (driveways) (104-7011) | SY | 1,234 | $75.00 | $21.61 | $46.50 |
| 5 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 1,538 | $50.00 | $28.11 | $29.00 |
| 6 | Removing concrete (curb & gutter) (104-7017) | LF | 634 | $25.00 | $9.95 | $12.50 |
| 7 | Excavation (roadway) (110-7001) | CY | 28,185.70 | $15.00 | $24.10 | $48.50 |
| 8 | Excavation (channel) (110-7002) | CY | 1,112 | $15.00 | $16.60 | $43.00 |
| 9 | Embankment (final)(DC)(type C) (132-7006) | CY | 2,359.20 | $25.00 | $7.40 | $24.00 |
| 10 | Furn & place topsoil (4") (160-7002) | SY | 9,661 | $3.00 | $2.70 | $8.10 |
| 11 | Hydro mulch seed (permanent_rural_sand_hel) (164-7071) | SY | 9,661 | $1.00 | $1.75 | $1.05 |
| 12 | Fertilizer (166-7001) | ACRE | 2 | $600.00 | $145.50 | $405.00 |
| 13 | Vegetative watering (168-7001) | TGL | 275 | $30.00 | $44.30 | $39.00 |
| 14 | Irrigation system (miscellaneous) (170-7013) | LS | 1 | $2,500.00 | $17,250 | $22,500 |
| 15 | Mulch (192-7002) | SY | 50 | $15.00 | $92.00 | $58.00 |
| 16 | Loose aggregate GRND cover (type I) (192-7024) | CY | 84 | $250.00 | $192.90 | $580.00 |
| 17 | Rdside amenity (removing & reset) (194-7020) | EACH | 18 | $250.00 | $1,102.80 | $2,900.00 |
| 18 | Proof rolling (216-7001) | HR | 35 | $150.00 | $130.65 | $220.00 |
| 19 | FL BS (compacted in place)(type A GR 4) (12") (247-7115) | SY | 0 | $20.00 | $0.00 | $0.00 |
| 20 | Cement (275-7001) | TON | 0 | $250.00 | $0.00 | $0.00 |
| 21 | Cement TRT (existing material)(8") (275-7003) | SY | 0 | $4.00 | $0.00 | $0.00 |
| 22 | Prime coat (MC-30) (310-7004) | GAL | 0 | $5.75 | $0.00 | $0.00 |
| 23 | Fog seal (CSS-1H) (315-7004) | GAL | 0 | $4.00 | $0.00 | $0.00 |
| 24 | D-GR HMA type-C sac-A PG70-28 (341-7027) | TON | 0 | $250.00 | $0.00 | $0.00 |
| 25 | D-GR HMA type D sac-B PG70-28 (341-7054) | TON | 0 | $250.00 | $0.00 | $0.00 |
| 26 | D-GR HMA type-B sac-B PG70-28 (341-7083) | TON | 0 | $300.00 | $0.00 | $0.00 |
| 27 | Flexible pavement structure repair(3") (351-7002) | SY | 923 | $40.00 | $116.10 | $150.00 |
| 28 | Planing asphalt concrete pavement (0" to 9") (354-7037) | SY | 28,037 | $9.00 | $9.95 | $13.50 |
| 29 | Concrete pavement (CRCP) (9") (360-7003) | SY | 0 | $97.00 | $0.00 | $0.00 |
| 30 | Concrete pavement(transition slab) (9") (360-7032) | SY | 0 | $150.00 | $0.00 | $0.00 |
| 31 | Struct excavation (box) (400-7002) | CY | 198 | $25.00 | $39.55 | $58.00 |
| 32 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 232 | $320.00 | $373.75 | $240.00 |
| 33 | Drilled shaft (traffic signal pole) (24 in) (416-7042) | LF | 48 | $200.00 | $287.50 | $205.00 |
| 34 | Drilled shaft (traffic signal pole) (48 in) (416-7046) | LF | 88 | $500.00 | $632.50 | $640.00 |
| 35 | Riprap (concrete)(5 in) (432-7002) | CY | 514 | $550.00 | $597.65 | $695.00 |
| 36 | Riprap (concrete)(flume) (432-7012) | CY | 4 | $900.00 | $852.25 | $815.00 |
| 37 | Concrete box culvert (6 FT X 2 FT) (462-7010) | LF | 226 | $680.00 | $708.27 | $465.00 |
| 38 | Set (type I)(S= 6 FT)(HW= 3 FT)(6:1)(P) (467-7127) | EACH | 6 | $12,000 | $11,807 | $8,100.00 |
| 39 | Clean existing culverts (480-7001) | EACH | 4 | $1,000.00 | $2,417.25 | $5,800.00 |
| 40 | Removing structure (pipe) (496-7007) | LF | 120 | $50.00 | $45.15 | $40.50 |
| 41 | Mobilization (500-7001) | LS | 1 | $1,315,000 | $1,337,771 | $1,800,000 |
| 42 | Barricades, signs and traffic handling (502-7001) | MO | 21 | $20,000 | $27,675 | $50,000 |
| 43 | Portable changeable message sign (503-7001) | DAY | 1,760 | $40.00 | $112.50 | $115.00 |
| 44 | TMA (stationary) (505-7001) | DAY | 596 | $250.00 | $432.80 | $350.00 |
| 45 | TMA (mobile operation) (505-7003) | DAY | 108 | $500.00 | $108.30 | $1,300.00 |
| 46 | Rock filter dams (install) (type 2) (506-7002) | LF | 150 | $50.00 | $123.15 | $56.00 |
| 47 | Rock filter dams (remove) (506-7011) | LF | 150 | $50.00 | $49.70 | $17.50 |
| 48 | Construction exits (install) (type 1) (506-7020) | SY | 460 | $40.00 | $45.10 | $28.00 |
| 49 | Construction exits (remove) (506-7024) | SY | 460 | $20.00 | $26.90 | $14.00 |
| 50 | Sandbags for erosion control (8") (506-7037) | LF | 172 | $10.00 | $30.10 | $37.00 |
| 51 | Temporary sediment control fence (install) (506-7039) | LF | 200 | $8.00 | $6.90 | $8.70 |
| 52 | Temporary sediment control fence (remove) (506-7041) | LF | 200 | $8.00 | $2.30 | $4.65 |
| 53 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 2,450 | $10.00 | $5.75 | $9.85 |
| 54 | Biodegradable erosion control logs (remove) (506-7046) | LF | 2,450 | $5.00 | $1.15 | $1.75 |
| 55 | Constructing detours (508-7001) | SY | 8,170 | $90.00 | $94.45 | $110.00 |
| 56 | Concrete curb & gutter (type II) (529-7009) | LF | 9,483 | $28.00 | $38.15 | $52.50 |
| 57 | Concrete curb & gutter (slotted) (529-7021) | LF | 751 | $50.00 | $29.10 | $105.00 |
| 58 | Driveways (concrete) (530-7006) | SY | 2,304 | $105.00 | $105.85 | $115.00 |
| 59 | Concrete sidewalks (4") (531-7001) | SY | 10,813 | $75.00 | $62.25 | $68.50 |
| 60 | Curb ramps (type 2) (531-7006) | EACH | 4 | $2,000.00 | $3,983.10 | $3,500.00 |
| 61 | Curb ramps (type 7) (531-7010) | EACH | 17 | $2,000.00 | $4,420.20 | $3,500.00 |
| 62 | Concrete median (536-7002) | SY | 288 | $200.00 | $134.10 | $120.00 |
| 63 | Mailbox install-M (TWG-post) type 1 (560-7001) | EACH | 3 | $500.00 | $632.50 | $640.00 |
| 64 | In RD IL (type SA) 30S-8 (250W EQ) LED (610-7064) | EACH | 29 | $5,000.00 | $6,325.00 | $4,300.00 |
| 65 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 10,495 | $16.00 | $17.25 | $11.00 |
| 66 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 615 | $27.00 | $19.55 | $24.00 |
| 67 | Conduit (PVC) (schedule 80) (3") (618-7060) | LF | 355 | $15.00 | $28.75 | $13.00 |
| 68 | Conduit (PVC) (schedule 80) (4") (618-7064) | LF | 20 | $25.00 | $34.50 | $16.50 |
| 69 | Conduit (PVC) (schedule 80) (4") (bore) (618-7065) | LF | 570 | $40.00 | $40.25 | $36.00 |
| 70 | Electrical conductor (no.14) insulated (620-7002) | LF | 5,510 | $2.70 | $3.15 | $1.15 |
| 71 | Electrical conductor (no.12) insulated (620-7004) | LF | 320 | $2.00 | $2.90 | $1.20 |
| 72 | Electrical conductor (no.8) bare (620-7007) | LF | 5,505 | $2.90 | $2.90 | $1.75 |
| 73 | Electrical conductor (no.8) insulated (620-7008) | LF | 12,290 | $2.00 | $3.15 | $1.85 |
| 74 | Electrical conductor (no.6) bare (620-7009) | LF | 1,015 | $2.00 | $3.45 | $2.05 |
| 75 | Electrical conductor (no.6) insulated (620-7010) | LF | 50 | $2.00 | $3.45 | $2.30 |
| 76 | ITS GND box(pcast) type 1 (243636)W/aprn (623-7002) | EACH | 3 | $6,000.00 | $8,050.00 | $3,900.00 |
| 77 | Ground box type A (122311)W/apron (624-7002) | EACH | 4 | $950.00 | $1,725.00 | $1,100.00 |
| 78 | Ground box type C (162911)W/apron (624-7006) | EACH | 11 | $1,200.00 | $1,725.00 | $1,300.00 |
| 79 | Elc SRV type A 240/480 100(NS)AL(E)PS(U) (628-7068) | EACH | 1 | $9,000.00 | $10,350 | $9,300.00 |
| 80 | Elc SRV type D 120/240 070(NS)SS(E)SP(U) (628-7192) | EACH | 1 | $6,825.00 | $8,625.00 | $9,300.00 |
| 81 | Install small roadside sign support and assembly type 10BWG(1)SB(P) (644-7009) | EACH | 20 | $1,500.00 | $1,121.25 | $1,100.00 |
| 82 | Remove SM RD SN sup&AM (644-7073) | EACH | 72 | $175.00 | $115.00 | $115.00 |
| 83 | Work zone pavement marking non-removing (W)4"(solid) (662-7004) | LF | 15,441 | $0.13 | $0.70 | $0.70 |
| 84 | Work zone pavement marking non-removing (Y)4"(solid) (662-7035) | LF | 31,825 | $0.16 | $0.70 | $0.70 |
| 85 | Work zone pavement marking removing (reflectorized) type I-C (662-7049) | EACH | 487 | $4.78 | $6.90 | $6.95 |
| 86 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 780 | $3.15 | $6.90 | $6.95 |
| 87 | Work zone pavement marking removing (traffic BTN) type W (662-7057) | EACH | 737 | $4.50 | $6.30 | $6.40 |
| 88 | Work zone pavement marking removing (traffic BTN) type Y (662-7059) | EACH | 930 | $3.82 | $6.30 | $6.40 |
| 89 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 397 | $3.50 | $20.15 | $20.50 |
| 90 | Reflectorized pavement marking type I (W)8"(lane drop)(100MIL) (666-7021) | LF | 107 | $2.50 | $1.75 | $1.75 |
| 91 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 5,008 | $2.50 | $1.75 | $1.75 |
| 92 | Pavement sler 6" (666-7347) | LF | 14,565 | $1.25 | $0.70 | $0.70 |
| 93 | Pavement sler 8" (666-7348) | LF | 5,115 | $1.50 | $0.90 | $0.93 |
| 94 | Pavement sler 24" (666-7352) | LF | 3,213 | $2.00 | $7.10 | $7.15 |
| 95 | Pavement sler (arrow) (666-7353) | EACH | 24 | $50.00 | $126.50 | $130.00 |
| 96 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 3,069 | $2.25 | $1.45 | $1.45 |
| 97 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 248 | $2.25 | $1.45 | $1.45 |
| 98 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 1,976 | $2.25 | $1.45 | $1.45 |
| 99 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 9,272 | $2.25 | $1.45 | $1.45 |
| 100 | Prefabricated PM type B (W)(24")(solid) (668-7021) | LF | 3,213 | $40.00 | $40.25 | $40.50 |
| 101 | Prefabricated PM type B (W)(arrow) (668-7023) | EACH | 24 | $1,100.00 | $575.00 | $580.00 |
| 102 | Reflectorized pavement marker type I-C (672-7002) | EACH | 157 | $10.00 | $6.90 | $6.95 |
| 103 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 199 | $10.00 | $6.90 | $6.95 |
| 104 | Eliminating existing PM & markers (24") (677-7008) | LF | 312 | $3.00 | $5.75 | $5.80 |
| 105 | Pavement surface preparation for marking (6") (678-7002) | LF | 14,565 | $1.20 | $0.60 | $0.58 |
| 106 | Pavement surface preparation for marking (8") (678-7004) | LF | 5,115 | $1.50 | $0.70 | $0.70 |
| 107 | Pavement surface preparation for marking (24") (678-7008) | LF | 3,213 | $15.00 | $6.35 | $6.40 |
| 108 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 24 | $15.00 | $115.00 | $115.00 |
| 109 | Install highway traffic signal (system) (680-7003) | EACH | 1 | $22,142 | $34,500 | $29,000 |
| 110 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 12 | $300.00 | $575.00 | $350.00 |
| 111 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 8 | $300.00 | $575.00 | $350.00 |
| 112 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 12 | $300.00 | $575.00 | $350.00 |
| 113 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 12 | $300.00 | $575.00 | $350.00 |
| 114 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 12 | $300.00 | $575.00 | $350.00 |
| 115 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 4 | $300.00 | $575.00 | $350.00 |
| 116 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 8 | $900.00 | $862.50 | $930.00 |
| 117 | Backplate W/reflectorized border(3 sec)aluminum (682-7039) | EACH | 8 | $200.00 | $230.00 | $290.00 |
| 118 | Backplate W/reflectorized border(4 sec)aluminum (682-7040) | EACH | 4 | $250.00 | $287.50 | $350.00 |
| 119 | Backplate W/reflectorized border(5 sec)aluminum (682-7041) | EACH | 4 | $250.00 | $287.50 | $375.00 |
| 120 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 495 | $3.50 | $3.45 | $5.25 |
| 121 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 375 | $5.00 | $3.75 | $5.80 |
| 122 | Traffic signal CBL (type A)(14 AWG)(10 conductor) (684-7036) | LF | 1,410 | $7.00 | $5.75 | $6.40 |
| 123 | Traffic signal CBL (type A)(14 AWG)(20 conductor) (684-7046) | LF | 735 | $8.00 | $14.40 | $10.00 |
| 124 | Traffic signal CBL (type C)(12 AWG)(2 conductor) (684-7079) | LF | 1,450 | $5.00 | $3.45 | $2.30 |
| 125 | Ins traffic signal PL AM(S)1 arm(50')lum (686-7055) | EACH | 1 | $32,000 | $43,700 | $40,000 |
| 126 | Ins traffic signal PL AM(S)1 arm(55')lum (686-7059) | EACH | 2 | $35,000 | $44,275 | $42,000 |
| 127 | Ins traffic signal PL AM(S)1 arm(65')lum (686-7067) | EACH | 1 | $37,000 | $44,852 | $43,500 |
| 128 | Pedestrian pole assembly (687-7001) | EACH | 8 | $3,000.00 | $4,025.00 | $2,000.00 |
| 129 | Pedestrian push button pole (687-7002) | EACH | 8 | $2,300.00 | $4,025.00 | $1,700.00 |
| 130 | Relocate pedestrian pole assembly (687-7003) | EACH | 2 | $6,000.00 | $2,875.00 | $1,500.00 |
| 131 | Full - width mowing (730-7019) | CYC | 2 | $2,500.00 | $8,493.00 | $8,700.00 |
| 132 | Litter removal (734-7002) | CYC | 2 | $2,500.00 | $979.95 | $3,500.00 |
| 133 | Post and cable fence (removal) (772-7001) | LF | 493 | $35.00 | $9.80 | $17.50 |
| 134 | Post and cable fence (new installation) (772-7003) | LF | 493 | $60.00 | $39.20 | $115.00 |
| 135 | VIVDS cabling (6006-7007) | LF | 975 | $3.00 | $2.30 | $3.50 |
| 136 | VIVDS prosr sys (install only) (6006-7009) | EACH | 1 | $366.00 | $862.50 | $580.00 |
| 137 | VIVDS cam assy (install only) (6006-7010) | EACH | 4 | $2,000.00 | $402.50 | $580.00 |
| 138 | FL BS (compacted in place)(type A GR 4) (12") (247-7115) | SY | 18,069 | $17.81 | $27.95 | $40.00 |
| 139 | Cement (275-7001) | TON | 431 | $245.01 | $277.60 | $265.00 |
| 140 | Cement TRT (existing material)(8") (275-7003) | SY | 33,258 | $4.75 | $3.10 | $8.40 |
| 141 | Prime coat (MC-30) (310-7004) | GAL | 11,259 | $5.75 | $5.85 | $10.00 |
| 142 | Fog seal (CSS-1H) (315-7004) | GAL | 6,118 | $4.00 | $7.25 | $6.35 |
| 143 | D-GR HMA type-C sac-A PG70-28 (341-7027) | TON | 1,853 | $250.00 | $273.40 | $260.00 |
| 144 | D-GR HMA type D sac-B PG70-28 (341-7054) | TON | 1,957 | $250.00 | $248.55 | $350.00 |
| 145 | D-GR HMA type-B sac-B PG70-28 (341-7083) | TON | 3,706 | $300.00 | $266.65 | $235.00 |
| 146 | Concrete pavement (CRCP) (9") (360-7003) | SY | 33,982 | $97.00 | $114.25 | $130.00 |
| 147 | Concrete pavement(transition slab) (9") (360-7032) | SY | 277 | $150.00 | $127.80 | $350.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 8, 2026. Compiled by Mirage Metrics.