TxDOT contract A00128998 bid tabulation

Construct Ramps, IH 20 (AT WESTBOUND EXIT to RANCH HOUSE ROAD). Let by Texas DOT on July 2, 2025, Parker, Fort Worth District. 5 bids received; low bid $5,099,675 by Prater Dirt Work LLC, -13% against the engineer's estimate of $5,855,861.

Owner
Texas DOT
Letting
02 JUL 2025
Pay items
99
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Prater Dirt Work LLC$5,099,675Low-13%
2Ed Bell Construction Company$5,195,981+2.0%-11%
3Jay Mills Contracting, Incorporated$6,005,863+18%+3.0%
4Road Maker Contractors, LLC$6,206,566+22%+6.0%
5Jagoe-Public Company$6,737,037+32%+15%
TxDOT contract A00128998: bids by rank

Engineer's estimate: $5,855,861.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Prater Dirt Work LLC2. Ed Bell Construction Company3. Jay Mills Contracting, Incorporated4. Road Maker Contractors, LLC5. Jagoe-Public Company
1Preparing row (100-7002)STA32$15,000$1,000.00$4,000.00$1,500.00$6,300.00$3,500.00
2Removing concrete (pavement) (104-7001)SY3,091$22.00$22.50$21.00$35.00$16.28$45.00
3Removing concrete (riprap) (104-7006)SY30$70.00$30.00$42.00$25.00$40.71$29.00
4Removing concrete (curb) (104-7016)LF175$3.00$10.00$15.75$25.00$22.05$10.00
5Remove (10"-14") TRT/untrt base & asphalt pavement (105-7010)SY9,101$12.00$8.00$10.50$12.00$14.27$15.00
6Excavation (roadway) (110-7001)CY3,019$70.00$13.00$15.00$36.00$17.29$75.00
7Embankment (final)(OC)(type A) (132-7001)CY4,044$80.00$23.00$70.00$102.00$56.95$100.00
8Embankment (final)(OC)(type D) (132-7011)CY2,135$60.00$27.00$15.00$17.00$19.50$60.00
9Compost manuf topsoil (4") (161-7002)SY13,428$7.00$1.38$6.00$1.50$3.84$3.00
10Broadcast seed (permanent_rural_clay) (164-7002)SY13,428$3.00$0.26$1.00$0.30$0.95$0.50
11Broadcast seed (temporary_warm) (164-7005)SY6,715$0.30$0.17$0.50$0.20$0.88$0.05
12Broadcast seed (temporary_cool) (164-7006)SY6,715$0.30$0.17$0.50$0.20$0.90$0.05
13Vegetative watering (168-7001)TGL471$165.00$70.00$70.00$75.00$110.00$80.00
14Soil ret BLKT(SL_mod_clay_long_roll) (169-7010)SY6,715$1.50$3.03$2.00$3.50$3.75$1.75
15Lime (commercial lime slurry) (260-7004)TON635$400.00$325.00$32.10$400.00$401.25$300.00
16Lime TRT (existing material & new base)(8") (260-7011)SY8,451$4.20$6.00$3.15$12.00$22.82$14.00
17Salvage,haul & stockpile reclaimed asphalt PV (2") (305-7018)SY7,964$4.00$8.00$6.30$3.00$3.75$6.00
18Prime coat(MC-30 or AE-P) (310-7013)GAL1,680$20.00$10.50$7.15$8.50$12.74$1.00
19D-GR HMA type-B PG64-22 (341-7001)TON4,218$120.00$160.00$124.60$128.00$177.58$95.00
20SP mixes SP-C sac-A PG70-28 (344-7024)TON1,305$180.00$215.00$168.20$217.00$234.39$135.00
21Tack coat (344-7077)GAL2,275$5.00$8.00$1.00$0.01$7.80$1.00
22Concrete pavement (CRCP) (8") (360-7002)SY7,831$110.00$102.00$120.00$107.00$124.77$170.00
23Trench excavation protection (402-7001)LF749$14.00$100.00$5.25$1.50$21.00$18.00
24Drilled shaft (sign mounts) (48 in) (416-7032)LF28$800.00$689.00$715.00$725.00$1,440.00$1,100.00
25Drilled shaft (sign mounts) (54 in) (416-7033)LF16$1,000.00$928.00$962.50$1,000.00$1,440.00$1,100.00
26Retaining wall (MSE) (423-7001)SF6,700$80.00$120.00$105.00$156.00$115.50$150.00
27Riprap (mow strip)(4 in) (432-7013)CY103$800.00$715.00$840.00$750.00$787.50$1,000.00
28Rail (type SSTR) (450-7024)LF1,415$55.00$90.00$100.00$95.00$108.12$120.00
29RC pipe (CL III)(24 in) (464-7005)LF515$138.00$80.00$100.00$105.00$152.25$150.00
30RC pipe (CL V)(24 in) (464-7034)LF234$155.00$117.00$120.00$120.00$222.60$150.00
31Inlet (complete)(FGR)(FTW) (465-7232)EACH5$13,500$11,660$15,750$12,500$13,750$16,000
32Inlet (complete)(AD)(3FT X 3FT)(FTW) (465-7234)EACH2$13,250$9,540.00$10,500$10,000$13,125$9,000.00
33Manh (complete)(type SD)(3FT X 3FT)(FTW) (465-7259)EACH1$7,000.00$6,360.00$10,500$8,000.00$12,240$7,000.00
34Removing structure (inlet) (496-7002)EACH1$2,000.00$1,590.00$2,100.00$2,400.00$1,751.00$1,900.00
35Removing structure (pipe) (496-7007)LF80$45.00$26.50$21.00$32.00$20.60$24.00
36Mobilization (500-7001)LS1$519,260$450,000$500,000$600,000$422,208$747,000
37Barricades, signs and traffic handling (502-7001)MO8$18,000$4,000.00$42,000$30,000$19,380$40,000
38Portable changeable message sign (503-7001)DAY340$120.00$300.00$105.00$125.00$131.25$80.00
39TMA (stationary) (505-7001)DAY340$280.00$300.00$157.50$300.00$204.75$50.00
40Rock filter dams (install) (type 2) (506-7002)LF80$40.00$59.00$75.00$65.00$68.85$42.00
41Rock filter dams (remove) (506-7011)LF80$20.00$23.75$25.00$25.00$17.55$15.00
42Construction exits (install) (type 1) (506-7020)SY160$40.00$41.58$35.00$45.00$47.25$15.00
43Construction exits (remove) (506-7024)SY160$20.00$15.17$11.00$16.00$14.85$5.00
44Temporary sediment control fence (install) (506-7039)LF3,450$3.50$5.75$4.00$6.25$4.86$4.25
45Temporary sediment control fence (remove) (506-7041)LF3,450$1.20$1.50$1.25$1.75$1.62$1.50
46Biodegradable erosion control logs (install) (18") (506-7045)LF240$20.00$14.75$7.50$16.00$9.11$8.00
47Biodegradable erosion control logs (remove) (506-7046)LF240$3.50$1.66$1.50$2.00$1.69$1.50
48Portable concrete traffic barrier (des source)(F-shape)(type 1) (512-7017)LF2,340$30.00$35.00$10.00$20.00$23.10$10.00
49Portable concrete traffic barrier (move)(F-shape)(type 1) (512-7029)LF1,230$6.00$12.50$7.50$18.00$18.90$15.00
50Portable concrete traffic barrier (stockpile)(F-shape)(type 1) (512-7041)LF2,340$20.00$20.00$10.00$16.00$16.80$10.00
51Concrete curb & gutter (type II) (529-7009)LF169$60.00$66.00$75.00$70.00$57.75$70.00
52Mill rumble strips (asphalt) (shoulder) (533-7001)LF768$0.15$10.00$6.00$14.00$12.85$10.00
53Metal W-beam guard fence (timber post) (540-7001)LF325$24.00$27.56$29.00$29.00$33.75$27.00
54Metal beam guard fence trans (thrie-beam) (540-7005)EACH2$2,000.00$2,332.00$3,500.00$2,500.00$2,497.50$4,100.00
55Downstream anchor terminal section (540-7015)EACH2$800.00$1,908.00$2,100.00$2,000.00$1,714.50$1,400.00
56Remove metal beam guard fence (542-7001)LF500$5.00$3.18$4.00$3.50$3.38$3.25
57Remove terminal anchor section (542-7002)EACH2$400.00$318.00$350.00$335.00$337.50$240.00
58Remove downstream anchor terminal (542-7003)EACH2$800.00$318.00$350.00$335.00$337.50$240.00
59Guardrail end treatment (install) (544-7001)EACH4$3,500.00$3,551.00$4,000.00$3,750.00$4,185.00$3,600.00
60Crash cushion attenuator (move & reset) (545-7002)EACH1$1,500.00$2,500.00$2,500.00$4,400.00$2,875.00$1,300.00
61Crash cushion attenuator (remove) (545-7004)EACH1$1,500.00$1,000.00$2,000.00$3,500.00$1,035.00$1,300.00
62Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH1$10,000$11,500$12,600$13,000$10,580$16,000
63Pipe underdrains (type 8) (6") (556-7008)LF1,285$50.00$45.00$42.00$40.00$34.65$26.00
64Aluminum signs (type O) (636-7003)SF640$35.00$36.04$40.00$38.00$77.70$46.00
65Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH2$800.00$610.00$635.00$650.00$1,068.00$1,100.00
66Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH6$850.00$864.00$900.00$925.00$1,320.00$1,300.00
67Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH3$1,100.00$1,050.00$1,100.00$1,150.00$936.00$1,500.00
68Install small roadside sign support and assembly TYS80(2)SA(P-exal) (644-7049)EACH1$1,200.00$2,327.00$2,500.00$2,500.00$3,120.00$4,100.00
69Install small roadside sign support and assembly (rail mount) (644-7063)EACH3$4,800.00$4,505.00$5,000.00$4,800.00$6,120.00$9,000.00
70Remove SM RD SN sup&AM (644-7073)EACH12$180.00$120.00$200.00$167.00$252.00$310.00
71Install overhead sign support(30 FT cant) (650-7032)EACH1$48,000$34,980$40,000$37,000$69,600$43,000
72Install overhead sign support(35 FT cant) (650-7038)EACH2$48,000$40,280$45,000$43,000$81,600$55,000
73Remove overhd sign sup (650-7193)EACH2$7,000.00$12,200$12,600$13,000$22,800$10,000
74Install delineator assembly (D-SW)SZ 1(WFLX)GND (658-7003)EACH3$55.00$58.00$100.00$65.00$52.50$120.00
75Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012)EACH3$16.00$16.00$75.00$20.00$28.35$36.00
76Install delineator assembly (D-SW)SZ 1(BRF)GF1 (658-7015)EACH1$20.00$16.00$75.00$20.00$31.50$24.00
77Install object marker assembly (OM-2Z)(WFLX)GND (658-7058)EACH6$70.00$64.00$100.00$70.00$147.00$170.00
78Work zone pavement marking removing (W)6"(broken) (662-7065)LF1,630$1.25$1.54$1.55$1.50$1.58$1.50
79Work zone pavement marking removing (W)6"(solid) (662-7068)LF3,258$1.25$1.11$1.10$1.50$1.47$1.25
80Work zone pavement marking removing (W)8"(solid) (662-7072)LF860$1.25$2.12$2.10$4.50$2.73$4.50
81Work zone pavement marking removing (Y)6"(solid) (662-7100)LF6,150$1.25$1.11$1.10$1.50$1.26$1.25
82Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF2,312$2.00$1.06$1.05$1.50$1.68$1.25
83Reflectorized pavement marking type I (W)12"(lane drop)(100MIL) (666-7027)LF348$4.00$2.92$2.90$2.50$3.68$2.50
84Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030)LF928$4.50$2.92$2.90$5.00$6.30$5.00
85Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042)EACH2$195.00$185.50$185.00$280.00$215.25$300.00
86Reflectorized pavement marking type I (W)(number)(100MIL) (666-7063)EACH3$165.00$190.80$190.00$400.00$236.25$430.00
87Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066)EACH2$225.00$212.00$210.00$400.00$236.25$420.00
88RE PV marking type I(black)6"(shadow)(100MIL) (666-7138)LF2,010$2.50$1.33$1.35$2.50$1.05$2.75
89All-wther PM type I (W)6"(solid)(100MIL) (666-7309)LF8,069$1.40$1.22$1.25$1.00$1.05$1.00
90All-wther PM type I (W)6"(broken)(100MIL) (666-7310)LF2,740$1.60$1.59$1.65$1.00$1.05$1.00
91All-wther PM type I (Y)6"(solid)(100MIL) (666-7315)LF7,606$1.40$1.22$1.25$1.00$1.05$1.00
92Pavement sler 6" (666-7347)LF13,550$0.30$0.27$0.30$0.25$0.63$0.20
93Pavement sler 8" (666-7348)LF788$0.40$0.37$0.40$0.35$4.73$0.40
94Pavement sler 12" (666-7350)LF300$0.60$1.06$1.05$1.25$5.78$1.00
95Reflectorized pavement marker type II-C-R (672-7006)EACH330$6.50$6.10$6.10$8.00$5.25$8.00
96Eliminating existing PM & markers (4") (677-7001)LF7,523$0.50$0.64$0.65$1.00$1.05$1.00
97Eliminating existing PM & markers (6") (677-7002)LF9,640$1.00$0.64$0.65$1.00$1.58$1.00
98Eliminating existing PM & markers (8") (677-7004)LF1,138$1.20$1.06$1.05$1.75$2.63$1.75
99Anti-graffiti coatng (permnent-type III) (740-7006)SF6,700$1.70$2.40$1.50$1.50$5.63$2.25
TxDOT contract A00128998: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of July 2, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy