TxDOT contract A00131922 bid tabulation
Rehabilitate Existing Roadway, FM 1421 (SH 100 to US 281). Let by Texas DOT on December 2, 2025, Cameron, Pharr District. 6 bids received; low bid $14,628,509 by Ioc Company LLC, -20% against the engineer's estimate of $18,316,364.
- Owner
- Texas DOT
- Letting
- 02 DEC 2025
- Pay items
- 118
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ioc Company LLC | $14,628,509 | Low | -20% |
| 2 | Posillico Civil, Inc. | $15,395,000 | +5.0% | -16% |
| 3 | Reim Construction, Inc. | $16,138,874 | +10% | -12% |
| 4 | Foremost Paving, Inc. | $16,354,780 | +12% | -11% |
| 5 | Go Underground, Limited Liability Company | $16,493,451 | +13% | -10% |
| 6 | CK Newberry, LLC | $17,174,566 | +17% | -6.0% |
Engineer's estimate: $18,316,364.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Ioc Company LLC | 2. Posillico Civil, Inc. | 3. Reim Construction, Inc. | 4. Foremost Paving, Inc. | 5. Go Underground, Limited Liability Company | 6. CK Newberry, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 344 | $7,000.00 | $1,500.00 | $2,850.00 | $1,750.00 | $2,500.00 | $1,779.07 | $200.00 |
| 2 | Removing concrete (pavement) (104-7001) | SY | 337 | $10.20 | $21.41 | $12.00 | $18.75 | $7.10 | $12.00 | $20.00 |
| 3 | Removing concrete (riprap) (104-7006) | SY | 270 | $18.00 | $20.45 | $15.00 | $16.25 | $37.90 | $12.00 | $30.00 |
| 4 | Removing concrete (driveways) (104-7011) | SY | 888 | $30.00 | $19.36 | $5.00 | $14.25 | $44.20 | $12.00 | $30.00 |
| 5 | Excavation (roadway) (110-7001) | CY | 56,233 | $11.00 | $7.00 | $4.50 | $7.60 | $13.50 | $6.00 | $10.00 |
| 6 | Embankment (final)(DC)(type C) (132-7006) | CY | 3,905 | $15.00 | $5.92 | $3.00 | $6.25 | $9.40 | $8.00 | $13.00 |
| 7 | Backfill (type A) (134-7001) | STA | 344 | $300.00 | $245.00 | $200.00 | $240.00 | $205.90 | $1,200.00 | $200.00 |
| 8 | Furn & place topsoil (vehicle) (160-7007) | CY | 50 | $32.50 | $36.14 | $115.00 | $48.50 | $33.80 | $120.00 | $50.00 |
| 9 | Hydro mulch seed (permanent_rural_clay) (164-7018) | SY | 133,942 | $0.55 | $0.38 | $0.47 | $0.40 | $0.80 | $0.74 | $0.75 |
| 10 | Hydro mulch seed (temporary_warm) (164-7021) | SY | 133,942 | $0.50 | $0.30 | $0.47 | $0.35 | $0.70 | $0.65 | $0.65 |
| 11 | Vegetative watering (168-7001) | TGL | 2,254 | $11.00 | $30.00 | $20.00 | $32.00 | $26.00 | $170.00 | $16.00 |
| 12 | Sprinkling (dust control) (204-7001) | TGL | 1,377 | $9.00 | $1.00 | $1.00 | $32.00 | $1.00 | $12.00 | $20.00 |
| 13 | FL BS (roadway del)(type E GR 4)(final pos) (247-7277) | CY | 29,143 | $29.00 | $55.00 | $42.00 | $56.00 | $43.40 | $43.86 | $64.00 |
| 14 | Geogrid base reinforcement (type 2) (250-7002) | SY | 170,202 | $1.35 | $1.75 | $1.00 | $1.25 | $1.40 | $1.54 | $1.00 |
| 15 | Rework BS metal (type B)(6")(DC)(org pos) (251-7034) | CY | 25,236 | $3.00 | $4.00 | $9.50 | $6.60 | $6.60 | $4.00 | $15.00 |
| 16 | Lime (com or QK)(slurry) (260-7005) | TON | 5,054 | $220.00 | $215.50 | $300.00 | $364.00 | $237.20 | $375.94 | $350.00 |
| 17 | Lime TRT (existing material)(12") (260-7009) | SY | 170,202 | $3.00 | $3.25 | $2.50 | $2.00 | $3.40 | $2.00 | $3.25 |
| 18 | Cement (275-7001) | TON | 1,835 | $205.00 | $190.00 | $200.00 | $222.00 | $174.20 | $200.00 | $200.00 |
| 19 | Cement TRT (existing material & new base)(12") (275-7009) | SY | 163,130 | $2.75 | $2.50 | $2.00 | $2.25 | $2.60 | $2.00 | $2.00 |
| 20 | Salvage,haul & stockpile reclaimed asphalt PV (2") (305-7018) | SY | 151,413 | $6.13 | $1.00 | $1.00 | $1.45 | $1.90 | $2.00 | $1.00 |
| 21 | Prime coat (MC-30) (310-7004) | GAL | 32,626 | $5.20 | $4.00 | $4.00 | $4.60 | $4.30 | $10.00 | $4.00 |
| 22 | Asphalt (tier II) (316-7266) | GAL | 48,938 | $5.00 | $3.75 | $5.00 | $2.95 | $6.20 | $10.00 | $3.00 |
| 23 | Aggregate (type-B GR-4P sac-B) (316-7267) | CY | 1,358 | $100.00 | $100.00 | $120.00 | $249.00 | $66.10 | $165.00 | $120.00 |
| 24 | SP mixes SP-D sac-A PG76-22 (344-7064) | TON | 26,688 | $120.00 | $124.10 | $120.00 | $145.00 | $116.25 | $129.56 | $140.00 |
| 25 | Plane & text asphalt concrete pavement(1.5") (354-7018) | SY | 2,163 | $1.50 | $3.00 | $1.00 | $4.50 | $13.70 | $8.00 | $7.00 |
| 26 | Struct excavation (400-7001) | CY | 102 | $33.00 | $50.00 | $65.00 | $10.75 | $35.00 | $24.00 | $50.00 |
| 27 | Struct excavation (special) (400-7005) | CY | 35 | $100.00 | $150.00 | $200.00 | $109.00 | $90.00 | $100.00 | $250.00 |
| 28 | Cut & restore asphalt paving (400-7008) | SY | 98 | $150.00 | $170.00 | $225.00 | $74.00 | $200.00 | $85.00 | $100.00 |
| 29 | Cem stabil BKFL (400-7010) | CY | 55 | $120.00 | $75.00 | $100.00 | $155.00 | $180.00 | $85.00 | $275.00 |
| 30 | Trench excavation protection (402-7001) | LF | 249 | $3.50 | $5.00 | $60.00 | $3.80 | $1.00 | $1.00 | $20.00 |
| 31 | Riprap (concrete)(4 in) (432-7001) | CY | 872 | $600.00 | $500.00 | $385.00 | $540.00 | $860.00 | $480.00 | $800.00 |
| 32 | Riprap (concrete)(CL B)(5 in) (432-7008) | CY | 35 | $600.00 | $655.00 | $400.00 | $573.00 | $1,670.00 | $476.00 | $775.00 |
| 33 | Riprap (mow strip)(4 in) (432-7013) | CY | 290 | $600.00 | $550.00 | $425.00 | $640.00 | $805.00 | $481.00 | $725.00 |
| 34 | RC pipe (CL III)(18 in) (464-7003) | LF | 8,682 | $95.00 | $100.00 | $95.00 | $72.50 | $108.70 | $89.09 | $85.00 |
| 35 | RC pipe (CL III)(24 in) (464-7005) | LF | 48 | $100.00 | $160.00 | $165.00 | $100.00 | $365.00 | $100.67 | $160.00 |
| 36 | RC pipe (CL IV)(24 in) (464-7021) | LF | 114 | $200.00 | $170.00 | $170.00 | $121.00 | $385.00 | $120.80 | $125.00 |
| 37 | Inlet(complete)(PSL)(SFG)(3FTX5FT-3FTX5FT) (465-7148) | EACH | 1 | $12,288 | $5,500.00 | $8,000.00 | $5,570.00 | $9,200.00 | $5,150.00 | $14,000 |
| 38 | Inlet(complete)(pazd)(FG)(4FTX4FT-3FTX3FT) (465-7159) | EACH | 1 | $5,000.00 | $5,000.00 | $9,000.00 | $10,900 | $8,700.00 | $4,700.00 | $14,000 |
| 39 | Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306) | EACH | 2 | $1,500.00 | $1,350.00 | $1,500.00 | $672.00 | $1,200.00 | $1,325.00 | $2,000.00 |
| 40 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 399 | $1,200.00 | $1,000.00 | $3,250.00 | $818.00 | $1,350.00 | $1,425.00 | $1,800.00 |
| 41 | Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325) | EACH | 2 | $2,200.00 | $1,500.00 | $1,800.00 | $964.00 | $1,470.00 | $1,175.00 | $2,000.00 |
| 42 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 1 | $1,700.00 | $2,000.00 | $2,200.00 | $977.00 | $1,470.00 | $2,300.00 | $3,200.00 |
| 43 | Clean existing culverts (480-7001) | EACH | 12 | $5,000.00 | $2,000.00 | $450.00 | $4,500.00 | $27,000 | $4,000.00 | $3,200.00 |
| 44 | Removing structure (inlet) (496-7002) | EACH | 2 | $1,000.00 | $750.00 | $700.00 | $721.00 | $620.00 | $1,200.00 | $2,100.00 |
| 45 | Removing structure (set) (496-7004) | EACH | 351 | $400.00 | $250.00 | $150.00 | $422.00 | $420.00 | $199.72 | $600.00 |
| 46 | Removing structure (pipe) (496-7007) | LF | 7,481 | $20.00 | $10.00 | $8.00 | $18.50 | $20.00 | $4.00 | $12.00 |
| 47 | Mobilization (500-7001) | LS | 1 | $1,987,860 | $1,338,500 | $1,397,355 | $1,450,000 | $1,200,000 | $906,000 | $1,675,000 |
| 48 | Barricades, signs and traffic handling (502-7001) | MO | 27 | $12,839 | $2,350.00 | $7,000.00 | $4,320.00 | $7,800.00 | $12,211 | $5,000.00 |
| 49 | Portable changeable message sign (503-7002) | EACH | 5 | $13,000 | $15,000 | $12,000 | $5,470.00 | $7,936.70 | $22,000 | $20,000 |
| 50 | TMA (stationary) (505-7001) | DAY | 776 | $210.00 | $1.00 | $55.00 | $51.50 | $45.10 | $25.00 | $250.00 |
| 51 | TMA (mobile operation) (505-7003) | DAY | 31 | $211.00 | $10.00 | $400.00 | $399.00 | $0.01 | $25.00 | $300.00 |
| 52 | Rock filter dams (install) (type 2) (506-7002) | LF | 560 | $100.00 | $39.00 | $35.00 | $46.75 | $95.00 | $34.00 | $95.00 |
| 53 | Rock filter dams (remove) (506-7011) | LF | 560 | $30.00 | $17.00 | $5.00 | $17.50 | $40.00 | $1.00 | $40.00 |
| 54 | Construction exits (install) (type 2) (506-7021) | SY | 936 | $20.00 | $25.00 | $25.00 | $10.75 | $23.50 | $28.00 | $25.00 |
| 55 | Construction exits (remove) (506-7024) | SY | 936 | $5.50 | $10.00 | $5.00 | $9.00 | $13.10 | $1.00 | $10.00 |
| 56 | FRNT end loader work (ersn & sedm cont) (506-7031) | HR | 40 | $200.00 | $100.00 | $25.00 | $87.00 | $90.60 | $150.00 | $100.00 |
| 57 | Temporary sediment control fence (install) (506-7039) | LF | 6,084 | $4.30 | $3.10 | $3.00 | $3.75 | $4.50 | $6.50 | $4.50 |
| 58 | Temporary sediment control fence (remove) (506-7041) | LF | 6,084 | $1.30 | $1.10 | $1.00 | $1.30 | $2.00 | $1.00 | $2.00 |
| 59 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 3,040 | $5.00 | $4.00 | $3.00 | $3.50 | $6.80 | $8.75 | $6.75 |
| 60 | Biodegradable erosion control logs (remove) (506-7046) | LF | 3,040 | $1.37 | $0.10 | $1.00 | $1.00 | $2.00 | $1.00 | $2.00 |
| 61 | Driveways (concrete) (530-7006) | SY | 1,106 | $120.00 | $125.00 | $90.00 | $69.50 | $76.20 | $78.70 | $75.00 |
| 62 | Driveways (ACP) (530-7010) | SY | 8,155 | $55.00 | $60.00 | $38.00 | $41.50 | $54.10 | $65.00 | $45.00 |
| 63 | Turnouts (concrete) (530-7017) | SY | 446 | $90.66 | $150.00 | $65.00 | $89.50 | $81.40 | $120.00 | $125.00 |
| 64 | Metal W-beam guard fence (timber post) (540-7001) | LF | 4,000 | $29.00 | $25.85 | $28.00 | $29.75 | $27.60 | $28.60 | $30.00 |
| 65 | Remove metal beam guard fence (542-7001) | LF | 4,200 | $3.00 | $4.25 | $3.00 | $7.50 | $2.90 | $6.00 | $3.00 |
| 66 | Remove terminal anchor section (542-7002) | EACH | 13 | $260.00 | $275.00 | $250.00 | $621.00 | $220.00 | $400.00 | $300.00 |
| 67 | Remove downstream anchor terminal (542-7003) | EACH | 13 | $200.00 | $275.00 | $250.00 | $725.00 | $230.00 | $400.00 | $300.00 |
| 68 | Guardrail end treatment (install) (544-7001) | EACH | 26 | $3,500.00 | $3,463.00 | $3,200.00 | $4,390.00 | $3,275.00 | $4,510.00 | $3,500.00 |
| 69 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 116 | $260.00 | $375.00 | $250.00 | $581.00 | $315.00 | $400.00 | $375.00 |
| 70 | Electrical conductor (no.8) bare (620-7007) | LF | 15 | $2.20 | $1.87 | $1.00 | $1.95 | $1.70 | $1.70 | $1.50 |
| 71 | Tray cable (4 conductor) (12 AWG) (621-7006) | LF | 615 | $3.00 | $2.65 | $2.00 | $2.75 | $2.40 | $2.40 | $3.50 |
| 72 | Aluminum signs (type A) (636-7001) | SF | 23 | $30.00 | $36.38 | $40.00 | $37.50 | $33.00 | $33.00 | $50.00 |
| 73 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 47 | $800.00 | $675.00 | $1,000.00 | $769.00 | $725.00 | $850.00 | $675.00 |
| 74 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 13 | $950.00 | $950.00 | $1,200.00 | $1,080.00 | $945.00 | $1,025.00 | $950.00 |
| 75 | Remove SM RD SN sup&AM (644-7073) | EACH | 60 | $100.00 | $85.00 | $50.00 | $97.00 | $288.50 | $200.00 | $85.00 |
| 76 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 94 | $35.00 | $35.00 | $170.00 | $40.00 | $30.00 | $25.00 | $25.00 |
| 77 | Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059) | EACH | 26 | $96.62 | $95.00 | $170.00 | $108.00 | $54.00 | $80.00 | $175.00 |
| 78 | Remove delin & object marker assms (658-7078) | EACH | 26 | $21.00 | $25.00 | $8.00 | $27.75 | $121.50 | $35.00 | $15.00 |
| 79 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 67,909 | $0.32 | $0.63 | $0.50 | $0.60 | $0.70 | $0.67 | $0.60 |
| 80 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 80 | $10.68 | $12.98 | $11.00 | $18.25 | $12.80 | $12.80 | $13.00 |
| 81 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 67,545 | $0.33 | $0.63 | $0.50 | $0.60 | $0.70 | $0.62 | $0.65 |
| 82 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 1,196 | $1.15 | $1.12 | $1.00 | $0.88 | $1.10 | $1.10 | $1.10 |
| 83 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 400 | $1.15 | $1.12 | $1.00 | $0.88 | $1.10 | $1.10 | $1.10 |
| 84 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 1,722 | $1.25 | $1.50 | $1.20 | $1.15 | $1.30 | $0.57 | $2.00 |
| 85 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 1,000 | $1.10 | $1.42 | $1.00 | $1.20 | $1.40 | $1.40 | $1.40 |
| 86 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 620 | $8.00 | $11.56 | $10.00 | $18.25 | $11.40 | $11.40 | $11.50 |
| 87 | Reflectorized pavement marking type I (Y)12"(solid)(100MIL) (666-7117) | LF | 1,058 | $4.00 | $4.26 | $4.00 | $2.30 | $4.20 | $4.10 | $4.20 |
| 88 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 67,445 | $0.80 | $0.76 | $0.50 | $1.10 | $0.80 | $0.75 | $0.75 |
| 89 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 6,650 | $0.50 | $0.73 | $0.50 | $1.20 | $0.80 | $0.72 | $0.75 |
| 90 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 26,119 | $0.65 | $0.71 | $0.50 | $1.05 | $0.70 | $0.70 | $0.70 |
| 91 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 14 | $230.00 | $243.38 | $225.00 | $171.00 | $240.00 | $240.00 | $240.00 |
| 92 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 7 | $280.00 | $243.38 | $225.00 | $285.00 | $240.00 | $240.00 | $240.00 |
| 93 | Prefabricated PM type C (W)(RR crossing) (668-7108) | EACH | 1 | $600.00 | $689.58 | $650.00 | $684.00 | $680.00 | $680.00 | $680.00 |
| 94 | Reflectorized pavement marker type I-C (672-7002) | EACH | 51 | $4.50 | $4.87 | $4.00 | $8.50 | $4.80 | $4.80 | $4.80 |
| 95 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 1,030 | $4.00 | $3.85 | $3.00 | $8.50 | $3.80 | $3.80 | $3.80 |
| 96 | Traffic button type Y (672-7008) | EACH | 1,536 | $2.04 | $2.84 | $2.00 | $4.00 | $2.80 | $2.80 | $2.80 |
| 97 | Traffic button type B (672-7009) | EACH | 10,800 | $2.10 | $2.23 | $2.00 | $2.30 | $2.20 | $2.20 | $2.20 |
| 98 | Eliminating existing PM & markers (4") (677-7001) | LF | 34,377 | $0.35 | $0.46 | $0.40 | $0.35 | $0.50 | $0.45 | $0.45 |
| 99 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 2 | $55.00 | $101.41 | $75.00 | $85.50 | $100.00 | $100.00 | $100.00 |
| 100 | Eliminating existing PM & markers (word) (677-7015) | EACH | 1 | $62.00 | $101.41 | $75.00 | $85.50 | $100.00 | $100.00 | $100.00 |
| 101 | Install highway traffic signal (flash beacon) (680-7001) | EACH | 1 | $9,000.00 | $716.48 | $5,500.00 | $741.00 | $650.00 | $650.00 | $9,500.00 |
| 102 | Install highway traffic signal (isolated) (680-7002) | EACH | 1 | $20,000 | $3,306.83 | $8,800.00 | $3,420.00 | $3,000.00 | $3,000.00 | $25,000 |
| 103 | Removing traffic signals (680-7004) | EACH | 2 | $6,700.00 | $2,039.22 | $2,800.00 | $2,110.00 | $1,850.00 | $1,850.00 | $6,000.00 |
| 104 | Temporary traffic signals (681-7001) | EACH | 2 | $60,000 | $3,086.38 | $6,800.00 | $3,190.00 | $2,800.00 | $2,800.00 | $6,000.00 |
| 105 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 8 | $300.00 | $330.68 | $363.00 | $342.00 | $300.00 | $300.00 | $250.00 |
| 106 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 4 | $300.00 | $330.68 | $363.00 | $342.00 | $300.00 | $300.00 | $250.00 |
| 107 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 12 | $300.00 | $330.68 | $363.00 | $342.00 | $300.00 | $300.00 | $250.00 |
| 108 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 8 | $300.00 | $330.68 | $363.00 | $342.00 | $300.00 | $300.00 | $250.00 |
| 109 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 10 | $300.00 | $330.68 | $363.00 | $342.00 | $300.00 | $300.00 | $250.00 |
| 110 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 4 | $300.00 | $330.68 | $363.00 | $342.00 | $300.00 | $300.00 | $250.00 |
| 111 | Backplate W/reflectorized border(4 sec) (682-7037) | EACH | 4 | $211.00 | $137.79 | $180.00 | $142.00 | $125.00 | $125.00 | $235.00 |
| 112 | Backplate W/reflectorized border(3 sec)aluminum (682-7039) | EACH | 8 | $210.00 | $203.92 | $130.00 | $211.00 | $185.00 | $185.00 | $210.00 |
| 113 | Traffic signal CBL (type A)(12 AWG)(5 conductor) (684-7010) | LF | 925 | $3.00 | $1.98 | $1.50 | $2.00 | $1.80 | $1.80 | $3.00 |
| 114 | Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012) | LF | 735 | $4.00 | $2.43 | $2.50 | $2.50 | $2.20 | $2.20 | $3.50 |
| 115 | Removal of conduit (690-7001) | LF | 2,115 | $13.33 | $2.20 | $3.00 | $2.30 | $2.00 | $2.00 | $4.85 |
| 116 | Removal of ground boxes (690-7006) | EACH | 21 | $1,500.00 | $216.05 | $250.00 | $223.00 | $196.00 | $196.00 | $150.00 |
| 117 | Bonding course (3007-7001) | GAL | 10,925 | $4.00 | $3.00 | $6.00 | $4.90 | $2.60 | $10.00 | $4.25 |
| 118 | RVDS (presence and advance detection) (6008-7003) | EACH | 4 | $9,000.00 | $9,810.27 | $7,800.00 | $10,100 | $8,900.00 | $10,900 | $4,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of December 2, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.