TxDOT contract A00135291 bid tabulation

Resurface Roadway, SH 142 (Church Street to BORCHERT LOOP). Let by Texas DOT on August 7, 2025, Caldwell, Austin District. 3 bids received; low bid $1,719,623 by Hunter Industries, LTD., -20% against the engineer's estimate of $2,154,843.

Owner
Texas DOT
Letting
07 AUG 2025
Pay items
95
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Hunter Industries, LTD.$1,719,623Low-20%
2Dean Word Company, LTD.$1,853,305+8.0%-14%
3Texas Materials Group, Inc.$1,939,312+13%-10%
TxDOT contract A00135291: bids by rank

Engineer's estimate: $2,154,843.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Hunter Industries, LTD.2. Dean Word Company, LTD.3. Texas Materials Group, Inc.
1Preparing row (100-7002)STA16$1,148.85$1,500.00$2,650.00
2Removing concrete (driveways) (104-7011)SY100$27.60$66.50$30.00
3Removing concrete (curb & gutter) (104-7017)LF210$13.80$15.75$10.00
4Remove (2"-6") TRT/untrt base & asphalt pavement (105-7002)SY332$13.80$15.00$14.50
5Excavation (roadway) (110-7001)CY971$25.40$25.50$50.00
6Embankment (final)(OC)(type B) (132-7003)CY75$27.60$104.75$100.00
7Backfill (type A) (134-7001)STA33$125.00$159.25$53.00$200.00
8Broadcast seed (permanent_urban_clay) (164-7004)SY911$0.50$0.50$0.50
9Vegetative watering (168-7001)TGL5$31.05$257.25$100.00
10Soil ret BLKT(SL_mod_clay_long) (169-7002)SY911$3.25$3.75$3.25
11D-GR HMA type-B PG64-22 (341-7001)TON668$91.45$120.75$110.00
12D-GR HMA type D PG64-22 (level-UP) (341-7046)TON1,451$145.00$88.40$115.75$125.00
13D-GR HMA type D PG 76-22 (exempt) (341-7065)TON160$99.60$194.25$140.00
14Tom-C PG76-22 sac-B (347-7002)TON2,364$160.00$124.90$128.75$161.00
15Flexible pavement structure repair(6") (351-7005)SY6,690$57.50$41.77$40.50$48.50
16Planing asphalt concrete pavement (0"- 1" edge mill) (354-7049)SY8,933$2.25$1.88$3.25$1.00
17Cem stabil BKFL (400-7010)CY281$223.68$163.25$200.00
18Drilled shaft (traffic signal pole) (36 in) (416-7044)LF13$590.00$913.25$600.00
19RC pipe (arch)(CL III)(des 2) (464-7041)LF300$251.64$214.75$225.00
20Set (type II) (des 2) (RCP) (6: 1) (C) (467-7425)EACH16$3,131.49$2,226.00$2,800.00
21Adjusting manholes (479-7001)EACH1$8,947.11$3,953.50$8,000.00
22Removing structure (set) (496-7004)EACH16$648.67$902.50$150.00
23Removing structure (pipe) (496-7007)LF300$42.50$13.25$38.00
24Mobilization (500-7001)LS1$157,125$105,308$120,000$90,000
25Barricades, signs and traffic handling (502-7001)MO5$7,500.00$3,224.33$13,132$10,000
26Portable changeable message sign (503-7002)EACH2$7,000.00$9,201.25$7,401.50$7,500.00
27TMA (stationary) (505-7001)DAY80$275.00$216.50$350.00$50.00
28TMA (mobile operation) (505-7003)DAY3$80.00$324.75$850.00$100.00
29Temporary sediment control fence (install) (506-7039)LF1,000$3.75$4.25$3.75
30Temporary sediment control fence (remove) (506-7041)LF1,000$0.50$0.50$0.50
31Biodegradable erosion control logs (install) (8") (506-7043)LF1,000$4.85$5.50$4.85
32Biodegradable erosion control logs (remove) (506-7046)LF1,000$1.00$1.25$1.00
33Concrete curb & gutter (type II) (529-7009)LF210$42.50$57.00$40.00
34Concrete curb (slotted) (529-7013)LF20$74.93$68.50$70.00
35Driveways (concrete) (530-7006)SY55$134.21$153.25$120.00
36Driveways (ACP) (type 3) (530-7013)SY375$45.50$88.25$100.00
37Concrete sidewalks (5") (531-7002)SY2,455$87.23$80.75$78.00
38Curb ramps (type 1) (531-7005)EACH1$2,795.97$2,700.25$2,500.00
39Curb ramps (type 6) (531-7009)EACH1$2,795.97$3,156.75$2,500.00
40Mailbox install-S (TWG-post) type 2 (560-7002)EACH4$374.00$393.75$400.00
41Mailbox install-D (TWG-post) type 2 (560-7003)EACH2$473.00$439.50$500.00
42Conduit (PVC) (schedule 40) (2") (618-7030)LF215$33.00$16.00$33.00
43Conduit (PVC) (schedule 40) (3") (618-7036)LF105$37.00$24.00$37.00
44Electrical conductor (no.8) bare (620-7007)LF390$2.70$1.75$2.70
45Electrical conductor (no.8) insulated (620-7008)LF960$2.70$2.50$2.70
46Electrical conductor (no.6) bare (620-7009)LF65$3.40$2.25$3.40
47Electrical conductor (no.6) insulated (620-7010)LF130$3.40$3.00$3.40
48Aluminum signs (type A) (636-7001)SF10.50$86.00$32.50$75.00
49Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031)EACH8$1,125.00$1,060.00$1,318.50$1,100.00
50Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF11,222$0.17$0.25$0.25$0.25
51Work zone pavement marking non-removing (W)8"(DOT) (662-7010)LF778$0.32$0.52$0.35$0.52
52Work zone pavement marking non-removing (W)8"(solid) (662-7012)LF4,385$0.34$0.52$0.35$0.52
53Work zone pavement marking non-removing (W)24"(solid) (662-7017)LF1,182$5.00$3.74$2.00$3.74
54Work zone pavement marking non-removing (W)(arrow) (662-7018)EACH25$75.00$70.00$28.50$70.00
55Work zone pavement marking non-removing(W)(word) (662-7030)EACH17$226.14$70.00$28.50$70.00
56Work zone pavement marking non-removing(W)18"(yld tri) (662-7031)EACH112$25.00$16.00$11.50$16.00
57Work zone pavement marking non-removing (Y)6"(broken) (662-7036)LF800$0.33$0.25$0.25$0.25
58Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF18,304$0.35$0.25$0.25$0.25
59Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH45$1.63$3.50$1.20
60Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH2,703$1.50$1.63$2.00$1.20
61Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018)LF708$1.66$0.77$1.25$0.77
62Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF3,986$1.25$0.77$1.00$0.77
63Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF1,074$9.00$7.77$7.50$7.77
64Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042)EACH25$150.00$176.00$165.50$176.00
65Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066)EACH17$175.00$250.00$177.00$250.00
66Ref pavement marking type I(W)18"(yld tri)(100MIL) (666-7087)EACH112$50.00$34.00$34.25$34.00
67Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF10,202$0.65$0.52$0.75$0.53
68Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF800$0.65$0.52$0.75$0.53
69Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF16,639$0.60$0.52$0.75$0.53
70Reflectorized pavement marker type I-C (672-7002)EACH200$5.00$4.30$4.50$4.50
71Reflectorized pavement marker type II-A-A (672-7004)EACH2,032$5.00$4.30$3.75$4.50
72Install highway traffic signal (upgrade) (680-7011)EACH1$23,000$21,186$23,500
73Vehicle signal section (12")LED(green) (682-7001)EACH2$480.00$411.00$500.00
74Vehicle signal section (12")LED(green arrow) (682-7002)EACH2$480.00$411.00$500.00
75Vehicle signal section (12")LED(yel) (682-7003)EACH2$480.00$411.00$500.00
76Vehicle signal section (12")LED(yel arrow) (682-7004)EACH4$480.00$411.00$500.00
77Vehicle signal section (12")LED(red) (682-7005)EACH2$480.00$411.00$500.00
78Vehicle signal section (12")LED(red arrow) (682-7006)EACH2$480.00$411.00$500.00
79Pedestrian signal section (LED)(countdown) (682-7018)EACH4$1,100.00$896.00$1,200.00
80Backplate W/reflectorized border(4 sec) (682-7037)EACH2$310.00$822.00$310.00
81Retrofit reflectorized border sheeting (3 sec) (682-7045)EACH6$25.00$502.25$25.00
82Backplate W/reflectorized border(3 sec) (682-7054)EACH2$220.00$730.50$220.00
83Traffic signal CBL (type A)(14 AWG)(2 conductor) (684-7028)LF640$2.20$2.00$2.20
84Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031)LF2,405$3.20$2.75$3.20
85Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033)LF430$3.80$3.50$3.80
86Ins traffic signal PL AM (S)STR(type B) (686-7007)EACH1$9,700.00$15,490$9,700.00
87Remove traffic signal PL (686-7313)EACH1$570.00$3,676.75$1,200.00
88Pedestrian pole assembly (687-7001)EACH2$4,600.00$5,091.00$4,600.00
89Pedestrian push button pole (687-7002)EACH1$4,300.00$3,276.00$4,300.00
90Pedestrian detect push button (APS) (688-7001)EACH4$1,300.00$1,061.50$1,300.00
91Bonding course (3007-7001)GAL4,029$4.50$3.54$3.75$4.00
92ITS com CBL (ethernet) (6005-7001)LF210$2.05$4.00$2.05
93VIVDS cam assy FXD LNS (6006-7002)EACH1$4,700.00$2,494.25$4,700.00
94VIVDS multi con com cax CBL(3COND16AWG) (6006-7027)LF770$3.75$2.50$3.75
95Bbu system (external battery cabinet) (6007-7001)EACH1$10,900$10,017$11,000
TxDOT contract A00135291: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of August 7, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy