TxDOT contract A00138761 bid tabulation
Hazard Elimination & Safety, SH 16 (Tilley St. to Draper St.). Let by Texas DOT on June 4, 2025, Jim Hogg, Pharr District. 4 bids received; low bid $5,520,580 by Anderson Columbia Co., Inc., +45% against the engineer's estimate of $3,802,175.
- Owner
- Texas DOT
- Letting
- 04 JUN 2025
- Pay items
- 114
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Anderson Columbia Co., Inc. | $5,520,580 | Low | +45% |
| 2 | J. Carroll Weaver, Inc. | $5,742,692 | +4.0% | +51% |
| 3 | Foremost Paving, Inc. | $7,956,834 | +44% | +109% |
| 4 | Ioc Company LLC | $8,774,109 | +59% | +131% |
Engineer's estimate: $3,802,175.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Anderson Columbia Co., Inc. | 2. J. Carroll Weaver, Inc. | 3. Foremost Paving, Inc. | 4. Ioc Company LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 22 | $14,098 | $3,000.00 | $6,500.00 | $13,000 | $24,500 |
| 2 | Removing concrete (driveways) (104-7011) | SY | 334 | $13.14 | $25.00 | $7.95 | $83.37 | $50.00 |
| 3 | Removing concrete (curb) (104-7016) | LF | 10 | $8.17 | $20.00 | $7.97 | $29.05 | $300.00 |
| 4 | Removing concrete (curb & gutter) (104-7017) | LF | 2,434 | $2.50 | $20.00 | $7.95 | $29.05 | $15.00 |
| 5 | Removing concrete (gutter) (104-7019) | LF | 319 | $5.00 | $24.00 | $7.95 | $29.05 | $25.00 |
| 6 | Removing stab base & asphalt pavement(12"-27") (105-7130) | SY | 7,107 | $6.32 | $20.00 | $45.96 | $42.46 | $15.00 |
| 7 | Excavation (roadway) (110-7001) | CY | 5,544 | $8.00 | $26.00 | $15.61 | $59.37 | $30.00 |
| 8 | Excavation (special) (110-7003) | CY | 845 | $33.18 | $90.00 | $15.61 | $28.17 | $35.00 |
| 9 | Embankment (final)(DC)(type C) (132-7006) | CY | 6,898 | $5.28 | $40.00 | $15.51 | $18.63 | $30.00 |
| 10 | Hydro mulch seed (temporary_warm_cool) (164-7023) | SY | 3,575 | $1.00 | $2.00 | $1.12 | $0.82 | $1.65 |
| 11 | FL BS (compacted in place)(type E GR 4)(final pos) (247-7195) | CY | 2,139 | $110.00 | $60.00 | $40.59 | $96.87 | $100.00 |
| 12 | Cement (275-7001) | TON | 150 | $202.28 | $380.00 | $219.52 | $205.00 | $250.00 |
| 13 | Cement TRT (new base)(8") (275-7011) | SY | 3,443 | $3.50 | $8.00 | $5.40 | $18.42 | $25.00 |
| 14 | Cement TRT (new base)(12") (275-7013) | SY | 4,110 | $13.29 | $12.00 | $8.93 | $28.58 | $20.00 |
| 15 | Cement TRT (subgrade)(12") (275-7015) | SY | 7,825 | $50.38 | $8.00 | $5.18 | $22.52 | $10.00 |
| 16 | Prime coat (MC-30) (310-7004) | GAL | 1,339 | $5.00 | $9.00 | $8.26 | $23.38 | $15.00 |
| 17 | Asphalt (tier II) (316-7266) | GAL | 2,009 | $5.00 | $8.00 | $5.43 | $89.54 | $15.00 |
| 18 | Aggregate (type-D GR-4P) (sac B) (316-7280) | CY | 33 | $110.00 | $900.00 | $1,729.34 | $230.38 | $500.00 |
| 19 | SP mixes SP-B sac-B PG76-22 (344-7008) | TON | 575 | $120.00 | $250.00 | $291.20 | $282.10 | $400.00 |
| 20 | SP mixes SP-C sac-A PG76-22 (344-7030) | TON | 740 | $125.00 | $180.00 | $216.16 | $209.41 | $425.00 |
| 21 | Stone-MTRX-asphalt SMA-C sac-A PG76-22 (346-7001) | TON | 728 | $164.78 | $280.00 | $305.76 | $296.21 | $450.00 |
| 22 | Tack coat (346-7028) | GAL | 669 | $4.53 | $6.00 | $6.72 | $6.51 | $25.00 |
| 23 | Flexible pavement structure repair(10") (351-7009) | SY | 2,170 | $27.00 | $60.00 | $92.22 | $89.16 | $75.00 |
| 24 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 3,835 | $6.47 | $10.00 | $9.45 | $35.40 | $10.00 |
| 25 | Pavement JT underseal (18") (356-7019) | LF | 603 | $50.00 | $35.00 | $22.40 | $139.19 | $55.00 |
| 26 | Cut & restoring pavement (400-7006) | SY | 239 | $138.00 | $300.00 | $194.58 | $108.50 | $200.00 |
| 27 | Trench excavation protection (402-7001) | LF | 1,208 | $5.03 | $25.00 | $4.33 | $1.09 | $1.00 |
| 28 | Class C concrete (rail foundation) (420-7052) | CY | 8 | $795.13 | $2,000.00 | $2,639.63 | $2,712.50 | $5,000.00 |
| 29 | Retaining wall (MSE) (423-7001) | SF | 6,664 | $64.70 | $125.00 | $179.54 | $230.55 | $225.00 |
| 30 | Retaining wall (temporary wall) (423-7012) | SF | 1,200 | $42.00 | $80.00 | $157.82 | $128.60 | $150.00 |
| 31 | Riprap (mow strip)(4 in) (432-7013) | CY | 28 | $630.74 | $1,000.00 | $923.39 | $705.25 | $3,500.00 |
| 32 | Riprap (stone protection)(12 in) (432-7041) | CY | 24 | $208.34 | $400.00 | $260.64 | $434.00 | $1,000.00 |
| 33 | Rail (type C221) (450-7032) | LF | 889 | $213.08 | $180.00 | $61.60 | $469.81 | $400.00 |
| 34 | Rail (handrail)(type A) (450-7058) | LF | 138 | $275.00 | $150.00 | $128.80 | $130.20 | $100.00 |
| 35 | Retrofit rail (type C223) (451-7034) | LF | 110 | $184.00 | $400.00 | $88.48 | $813.75 | $800.00 |
| 36 | Retrofit rail (type PR11) (451-7044) | LF | 130 | $125.00 | $200.00 | $193.76 | $195.30 | $150.00 |
| 37 | RC pipe (CL III)(18 in) (464-7003) | LF | 721 | $93.03 | $150.00 | $113.80 | $222.43 | $300.00 |
| 38 | RC pipe (CL III)(24 in) (464-7005) | LF | 835 | $147.23 | $200.00 | $119.58 | $179.03 | $300.00 |
| 39 | Manh (complete)(PRM)(48IN) (465-7002) | EACH | 13 | $8,033.31 | $10,000 | $7,860.23 | $6,510.00 | $15,000 |
| 40 | Junction box(complete)(PJB)(4FTX4FT) (465-7006) | EACH | 6 | $7,935.27 | $10,000 | $7,860.24 | $6,510.00 | $15,500 |
| 41 | Inlet (complete)(pco)(6FT)(none) (465-7025) | EACH | 8 | $10,740 | $10,000 | $7,860.24 | $9,765.00 | $18,000 |
| 42 | Inlet(complete)(pazd)(FG)(4FTX4FT-4FTX4FT) (465-7160) | EACH | 4 | $11,342 | $10,000 | $7,860.24 | $11,935 | $17,000 |
| 43 | Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325) | EACH | 1 | $1,500.00 | $7,500.00 | $6,660.79 | $1,953.00 | $6,000.00 |
| 44 | Adjusting manholes (479-7001) | EACH | 2 | $3,500.00 | $4,000.00 | $1,199.48 | $5,425.00 | $8,500.00 |
| 45 | Removing structure (inlet) (496-7002) | EACH | 3 | $511.11 | $2,500.00 | $7.61 | $1,085.00 | $2,500.00 |
| 46 | Removing structure (pipe) (496-7007) | LF | 169 | $10.74 | $25.00 | $7.95 | $54.25 | $125.00 |
| 47 | Remove STR (rail) (496-7017) | LF | 130 | $14.27 | $200.00 | $7.95 | $21.70 | $100.00 |
| 48 | Removing structure (building) (496-7033) | EACH | 2 | $4,268.00 | $50,000 | $53,089 | $51,768 | $25,000 |
| 49 | Mobilization (500-7001) | LS | 1 | $211,467 | $540,000 | $523,871 | $650,000 | $1,000,000 |
| 50 | Barricades, signs and traffic handling (502-7001) | MO | 16 | $3,250.00 | $2,480.00 | $7,600.00 | $9,500.00 | $5,000.00 |
| 51 | Portable changeable message sign (503-7001) | DAY | 32 | $120.33 | $110.00 | $84.00 | $185.00 | $150.00 |
| 52 | Portable changeable message sign (503-7002) | EACH | 11 | $5,850.33 | $4,820.00 | $13,440 | $1.00 | $25,000 |
| 53 | Construction exits (install) (type 1) (506-7020) | SY | 622 | $30.00 | $48.00 | $16.80 | $43.84 | $40.00 |
| 54 | Construction exits (remove) (506-7024) | SY | 622 | $12.50 | $16.00 | $8.96 | $20.59 | $10.00 |
| 55 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 200 | $7.50 | $10.00 | $7.84 | $7.60 | $7.75 |
| 56 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 690 | $10.13 | $15.00 | $7.84 | $7.60 | $6.10 |
| 57 | Biodegradable erosion control logs (remove) (506-7046) | LF | 890 | $3.08 | $5.00 | $3.47 | $3.26 | $1.45 |
| 58 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 960 | $49.00 | $80.00 | $43.66 | $186.81 | $100.00 |
| 59 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 100 | $57.00 | $120.00 | $43.66 | $196.68 | $125.00 |
| 60 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 80 | $60.00 | $120.00 | $43.66 | $177.39 | $125.00 |
| 61 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 1,230 | $7.00 | $30.00 | $43.66 | $54.97 | $20.00 |
| 62 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 960 | $14.25 | $40.00 | $43.66 | $58.65 | $25.00 |
| 63 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 100 | $14.00 | $100.00 | $43.66 | $48.28 | $50.00 |
| 64 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 80 | $17.00 | $100.00 | $43.66 | $32.73 | $50.00 |
| 65 | Concrete C&G (valley gutter) (529-7019) | LF | 235 | $75.00 | $100.00 | $107.51 | $226.50 | $275.00 |
| 66 | Concrete curb & gutter (type B) (mountable) (529-7024) | LF | 35 | $154.98 | $100.00 | $163.50 | $235.41 | $600.00 |
| 67 | Concrete curb & gutter (type A) (barrier) (529-7025) | LF | 2,762 | $33.33 | $42.00 | $43.91 | $75.96 | $55.00 |
| 68 | Driveways (concrete) (530-7006) | SY | 84 | $100.00 | $150.00 | $948.80 | $173.60 | $725.00 |
| 69 | Driveways (ACP) (530-7010) | SY | 295 | $64.50 | $230.00 | $162.40 | $218.80 | $400.00 |
| 70 | Concrete sidewalks (4") (531-7001) | SY | 825 | $85.00 | $100.00 | $85.66 | $69.44 | $200.00 |
| 71 | Curb ramps (type 1) (531-7005) | EACH | 2 | $3,004.88 | $3,555.00 | $5,040.00 | $3,797.50 | $6,500.00 |
| 72 | Curb ramps (type 2) (531-7006) | EACH | 4 | $3,183.00 | $3,100.00 | $5,040.00 | $3,797.50 | $4,000.00 |
| 73 | Concrete sidewalks (special) (531-7025) | SY | 7 | $250.00 | $175.00 | $224.00 | $135.63 | $1,500.00 |
| 74 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 2 | $2,510.30 | $3,170.00 | $2,488.64 | $3,130.23 | $2,235.00 |
| 75 | Guardrail end treatment (install) (544-7001) | EACH | 2 | $3,341.03 | $4,025.00 | $4,368.00 | $4,182.68 | $3,040.00 |
| 76 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 6 | $1,403.00 | $6,400.00 | $4,368.00 | $4,626.37 | $3,200.00 |
| 77 | Crash cushion attenuator (remove) (545-7004) | EACH | 4 | $895.00 | $4,050.00 | $4,032.00 | $6,189.56 | $1,325.00 |
| 78 | Crash cushion attenuator (install)(L)(N)(TL3) (545-7006) | EACH | 2 | $29,540 | $38,400 | $36,960 | $49,536 | $34,400 |
| 79 | Cca (install)(N)(TL3)(work zone) (545-7018) | EACH | 4 | $10,329 | $36,900 | $36,960 | $20,121 | $34,480 |
| 80 | Aluminum signs (type A) (636-7001) | SF | 12 | $35.49 | $1.00 | $224.00 | $24.69 | $22.75 |
| 81 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 5 | $880.00 | $870.00 | $924.00 | $764.93 | $705.00 |
| 82 | Install small roadside sign support and assembly TYS80(1)SA(P-BM) (644-7026) | EACH | 4 | $1,060.00 | $970.00 | $1,036.00 | $835.45 | $770.00 |
| 83 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 10 | $980.00 | $1,100.00 | $1,176.00 | $1,003.63 | $925.00 |
| 84 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 1 | $1,230.00 | $1,470.00 | $1,568.00 | $1,166.38 | $1,075.00 |
| 85 | Install small roadside sign support and assembly TYS80(1)SA(U-1EXT) (644-7032) | EACH | 1 | $1,300.00 | $1,680.00 | $1,792.00 | $1,388.80 | $1,280.00 |
| 86 | Install small roadside sign support and assembly (rail mount) (644-7063) | EACH | 3 | $5,140.00 | $8,140.00 | $8,680.00 | $4,464.78 | $4,115.00 |
| 87 | Relocate SM RD SN sup&AM(sign only) (644-7072) | EACH | 1 | $340.00 | $315.00 | $1,344.00 | $238.70 | $220.00 |
| 88 | Remove SM RD SN sup&AM (644-7073) | EACH | 12 | $75.00 | $95.00 | $100.80 | $629.71 | $110.00 |
| 89 | Remove lrsa (647-7003) | EACH | 1 | $947.09 | $1,260.00 | $1,344.00 | $1,437.63 | $1,325.00 |
| 90 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 12 | $26.93 | $30.00 | $31.36 | $26.59 | $24.50 |
| 91 | Install delineator assembly (D-SW)SZ 1(BRF)GF1 (BI) (658-7016) | EACH | 8 | $22.80 | $30.00 | $31.36 | $26.59 | $24.50 |
| 92 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 8 | $40.57 | $48.00 | $50.40 | $33.10 | $30.50 |
| 93 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 2,400 | $0.48 | $0.70 | $0.74 | $1.31 | $1.24 |
| 94 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 240 | $0.62 | $2.00 | $2.24 | $2.61 | $2.48 |
| 95 | Work zone pavement marking non-removing (W)(arrow) (662-7018) | EACH | 1 | $146.00 | $315.00 | $336.00 | $173.60 | $165.54 |
| 96 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 2,780 | $0.48 | $0.70 | $0.74 | $1.31 | $1.24 |
| 97 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 240 | $0.69 | $5.00 | $5.60 | $1.74 | $1.66 |
| 98 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 240 | $0.78 | $5.00 | $5.60 | $2.83 | $2.69 |
| 99 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 40 | $1.19 | $2.50 | $1.12 | $3.65 | $27.83 |
| 100 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 200 | $1.12 | $3.00 | $1.12 | $3.65 | $9.86 |
| 101 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 420 | $0.92 | $9.00 | $8.96 | $4.13 | $3.93 |
| 102 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 546 | $5.57 | $17.00 | $17.92 | $11.72 | $11.17 |
| 103 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 320 | $0.62 | $16.00 | $16.80 | $2.61 | $2.48 |
| 104 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 985 | $0.48 | $9.00 | $8.96 | $1.74 | $1.66 |
| 105 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 1,925 | $0.55 | $4.00 | $4.48 | $1.74 | $1.66 |
| 106 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 1 | $170.00 | $260.00 | $280.00 | $260.40 | $248.31 |
| 107 | Prefabricated PM type C (W)(double arrow) (668-7093) | EACH | 2 | $335.00 | $370.00 | $392.00 | $455.70 | $434.54 |
| 108 | Prefabricated PM type C (W)(RR crossing) (668-7108) | EACH | 5 | $711.25 | $526.00 | $560.00 | $672.70 | $641.47 |
| 109 | Reflectorized pavement marker type I-C (672-7002) | EACH | 62 | $5.75 | $8.00 | $8.40 | $6.30 | $6.00 |
| 110 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 90 | $10.17 | $8.00 | $7.84 | $6.30 | $6.00 |
| 111 | Eliminating existing PM & markers (12") (677-7006) | LF | 2,600 | $0.85 | $2.10 | $2.24 | $3.26 | $3.10 |
| 112 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 1 | $50.00 | $157.00 | $168.00 | $130.20 | $124.15 |
| 113 | Eliminating existing PM & markers (RR crossing) (677-7019) | EACH | 4 | $250.00 | $315.00 | $336.00 | $217.00 | $206.93 |
| 114 | Tree removal (30" - 36" diameter) (752-7009) | EACH | 3 | $674.20 | $1,500.00 | $15,927 | $12,884 | $3,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way