TxDOT contract A00184668 bid tabulation
Hazard Elimination & Safety, FM 24 (1.5 MI N OF SH 44 to 1.75 MI N OF SH 44). Let by Texas DOT on January 8, 2025, Nueces, Corpus Christi District. 7 bids received; low bid $846,576 by Salinas Construction Technologies, LTD., -3.5% against the engineer's estimate of $877,733.
- Owner
- Texas DOT
- Letting
- 08 JAN 2025
- Pay items
- 55
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Salinas Construction Technologies, LTD. | $846,576 | Low | -4.0% |
| 2 | Bay LTD. | $895,502 | +6.0% | +2.0% |
| 3 | LCR Total Transport LLC | $939,071 | +11% | +7.0% |
| 4 | J E Construction Services, LLC | $959,554 | +13% | +9.0% |
| 5 | Anderson Columbia Co., Inc. | $982,402 | +16% | +12% |
| 6 | CK Newberry, LLC | $998,390 | +18% | +14% |
| 7 | J. Carroll Weaver, Inc. | $1,076,293 | +27% | +23% |
Engineer's estimate: $877,733.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Salinas Construction Technologies, LTD. | 2. Bay LTD. | 3. LCR Total Transport LLC | 4. J E Construction Services, LLC | 5. Anderson Columbia Co., Inc. | 6. CK Newberry, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7007) | CY | 5 | $520.00 | $482.99 | $3,300.00 | $445.00 | $114.00 | $402.00 | $750.00 |
| 2 | Remove (16"-20") TRT/untrt base & asphalt pavement (105-7016) | SY | 1,134 | $10.00 | $21.62 | $11.00 | $11.50 | $33.00 | $25.00 | $25.00 |
| 3 | Excavation (roadway) (110-7001) | CY | 1,703 | $20.00 | $22.19 | $11.75 | $18.00 | $16.00 | $14.00 | $30.00 |
| 4 | Embankment (final)(DC)(type C) (132-7006) | CY | 1,167 | $30.00 | $10.14 | $10.75 | $28.00 | $19.00 | $59.00 | $20.00 |
| 5 | Compost manuf topsoil (4") (161-7002) | SY | 5,724 | $4.00 | $3.96 | $8.10 | $11.50 | $5.00 | $6.15 | $2.00 |
| 6 | Drill seed (permanent_rural_clay) (164-7010) | SY | 5,724 | $0.50 | $0.55 | $0.65 | $1.00 | $0.50 | $0.55 | $0.50 |
| 7 | Vegetative watering (168-7001) | TGL | 105 | $50.00 | $36.58 | $19.25 | $84.00 | $40.00 | $51.00 | $20.00 |
| 8 | FL BS (cip)(type A GR 1-2 or 5) final pos (247-7348) | CY | 1,181 | $140.00 | $107.90 | $150.00 | $168.00 | $128.00 | $103.00 | $150.00 |
| 9 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 90 | $350.00 | $379.66 | $460.00 | $330.00 | $340.00 | $393.00 | $375.00 |
| 10 | Lime TRT (existing material)(8") (260-7007) | SY | 4,534 | $5.00 | $4.77 | $6.30 | $8.00 | $11.00 | $6.25 | $7.00 |
| 11 | Prime coat (MC-30) (310-7004) | GAL | 794 | $8.00 | $7.45 | $6.20 | $6.50 | $8.00 | $6.30 | $8.00 |
| 12 | Asphalt (CRS-2) (316-7011) | GAL | 1,864 | $8.00 | $5.15 | $4.60 | $5.00 | $5.00 | $3.60 | $5.00 |
| 13 | Aggregate (type-PB, GR-3 or 3S)(sac-B) (316-7209) | CY | 57 | $700.00 | $305.50 | $260.00 | $203.00 | $330.00 | $341.00 | $450.00 |
| 14 | D-GR HMA type-B sac-B PG64-22 (341-7002) | TON | 468 | $175.00 | $145.17 | $210.00 | $146.00 | $128.00 | $163.00 | $230.00 |
| 15 | D-GR HMA type D sac-B PG70-22 (341-7050) | TON | 737 | $160.00 | $116.51 | $140.00 | $159.00 | $132.00 | $153.00 | $180.00 |
| 16 | D-GR HMA type D PG70-22 (level-UP) (341-7051) | TON | 99 | $350.00 | $146.33 | $371.50 | $158.00 | $340.00 | $500.00 | $325.00 |
| 17 | Tack coat (341-7082) | GAL | 715 | $12.00 | $5.97 | $4.80 | $5.40 | $8.00 | $4.10 | $4.00 |
| 18 | Flexible pavement structure repair(3") (351-7002) | SY | 468 | $75.00 | $90.70 | $49.50 | $65.00 | $131.00 | $71.00 | $85.00 |
| 19 | Planing asphalt concrete pavement(0" to 3") (354-7033) | SY | 791 | $4.00 | $12.41 | $3.60 | $4.50 | $13.00 | $21.00 | $8.50 |
| 20 | Planing asphalt concrete pavement (0" to 1.5") (354-7073) | SY | 1,000 | $4.00 | $9.22 | $9.10 | $1.50 | $13.00 | $16.00 | $8.50 |
| 21 | Clean existing culverts (480-7001) | EACH | 3 | $1,000.00 | $3,297.41 | $3,900.00 | $985.00 | $4,100.00 | $1,610.00 | $3,000.00 |
| 22 | Mobilization (500-7001) | LS | 1 | $78,976 | $143,750 | $23,000 | $90,400 | $86,480 | $90,000 | $95,000 |
| 23 | Barricades, signs and traffic handling (502-7001) | MO | 3 | $3,000.00 | $3,824.74 | $18,000 | $7,700.00 | $12,140 | $15,000 | $15,000 |
| 24 | Portable changeable message sign (503-7001) | DAY | 96 | $100.00 | $99.54 | $130.00 | $118.00 | $66.00 | $122.00 | $75.00 |
| 25 | TMA (stationary) (505-7001) | DAY | 31 | $200.00 | $322.42 | $390.00 | $200.00 | $490.00 | $379.00 | $325.00 |
| 26 | TMA (mobile operation) (505-7003) | DAY | 10 | $300.00 | $653.59 | $760.00 | $350.00 | $840.00 | $572.00 | $100.00 |
| 27 | Temporary sediment control fence (install) (506-7039) | LF | 260 | $5.00 | $4.66 | $7.60 | $8.50 | $9.00 | $7.40 | $8.00 |
| 28 | Temporary sediment control fence (remove) (506-7041) | LF | 260 | $10.00 | $1.77 | $6.20 | $3.40 | $7.00 | $4.15 | $4.00 |
| 29 | Driveways (ACP) (type 1) (530-7011) | SY | 254 | $75.00 | $52.15 | $12.25 | $37.00 | $86.00 | $59.00 | $40.00 |
| 30 | Driveways (ACP) (type 2) (530-7012) | SY | 28 | $110.00 | $206.18 | $38.00 | $108.00 | $222.00 | $306.00 | $150.00 |
| 31 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 3,925 | $0.10 | $0.71 | $0.80 | $1.85 | $2.00 | $1.35 | $0.50 |
| 32 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 955 | $0.10 | $2.50 | $3.20 | $5.80 | $3.00 | $3.65 | $2.25 |
| 33 | Remove RD IL asm (trans-base) (610-7009) | EACH | 12 | $680.00 | $1,196.36 | $1,700.00 | $1,420.00 | $1,640.00 | $2,110.00 | $1,250.00 |
| 34 | Remove ground box (624-7013) | EACH | 1 | $400.00 | $779.84 | $930.00 | $1,108.00 | $720.00 | $748.00 | $700.00 |
| 35 | Remove electrical services (628-7002) | EACH | 1 | $660.00 | $1,378.34 | $1,800.00 | $1,705.00 | $1,370.00 | $1,420.00 | $1,300.00 |
| 36 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 1 | $750.00 | $1,534.33 | $2,000.00 | $1,650.00 | $1,660.00 | $1,720.00 | $1,600.00 |
| 37 | Relocate SM RD SN sup&AM type S80 (644-7067) | EACH | 3 | $500.00 | $1,114.33 | $1,500.00 | $1,200.00 | $1,210.00 | $1,250.00 | $1,200.00 |
| 38 | Install delineator assembly (D-DW)SZ 1(WFLX)GND(BI) (658-7046) | EACH | 9 | $125.00 | $221.83 | $280.00 | $230.00 | $230.00 | $237.00 | $225.00 |
| 39 | Remove delin & object marker assms (658-7078) | EACH | 3 | $20.00 | $64.33 | $70.00 | $57.00 | $58.00 | $59.00 | $60.00 |
| 40 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 185 | $4.00 | $8.51 | $10.50 | $8.50 | $9.00 | $8.90 | $8.00 |
| 41 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 14,650 | $1.00 | $0.53 | $0.65 | $0.55 | $0.60 | $0.55 | $0.50 |
| 42 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 14,650 | $1.00 | $0.53 | $0.65 | $0.55 | $0.60 | $0.55 | $0.50 |
| 43 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 163 | $2.00 | $3.00 | $3.70 | $2.75 | $4.00 | $3.30 | $1.00 |
| 44 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 170 | $2.00 | $2.90 | $3.60 | $2.75 | $4.00 | $3.20 | $2.00 |
| 45 | Reflectorized pavement marking type I (W)8"(DOT)(090MIL) (666-7017) | LF | 204 | $0.90 | $1.74 | $1.55 | $1.25 | $1.00 | $1.30 | $1.15 |
| 46 | Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023) | LF | 150 | $0.90 | $1.94 | $1.55 | $1.25 | $2.00 | $1.30 | $1.15 |
| 47 | Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410) | LF | 3,924 | $0.50 | $0.95 | $1.25 | $1.00 | $1.00 | $1.05 | $1.00 |
| 48 | Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422) | LF | 5,220 | $0.50 | $0.95 | $1.25 | $1.00 | $1.00 | $1.05 | $1.00 |
| 49 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 17 | $35.00 | $30.72 | $22.00 | $18.00 | $17.00 | $19.00 | $20.00 |
| 50 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 2 | $250.00 | $269.17 | $280.00 | $228.00 | $230.00 | $237.00 | $225.00 |
| 51 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 2 | $250.00 | $321.67 | $350.00 | $284.00 | $290.00 | $297.00 | $275.00 |
| 52 | Prefabricated PM type C (Y)(12")(solid) (668-7125) | LF | 338 | $7.00 | $9.45 | $11.25 | $9.00 | $9.00 | $9.50 | $10.00 |
| 53 | Reflectorized pavement marker type I-C (672-7002) | EACH | 8 | $6.00 | $15.27 | $10.50 | $8.50 | $8.00 | $8.90 | $8.00 |
| 54 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 239 | $7.00 | $8.37 | $10.50 | $8.50 | $9.00 | $8.90 | $8.00 |
| 55 | Removal of cables (690-7009) | LF | 7,500 | $1.00 | $2.01 | $2.70 | $2.85 | $2.00 | $2.20 | $2.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.