TxDOT contract A00189006 bid tabulation
Reconstruct Existing Roadway, SL 12 (US 175 to IH 30). Let by Texas DOT on September 4, 2025, Dallas, Dallas District. 6 bids received; low bid $6,104,473 by Foutsco Paving Company, LLC, -9.5% against the engineer's estimate of $6,747,051.
- Owner
- Texas DOT
- Letting
- 04 SEP 2025
- Pay items
- 71
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Foutsco Paving Company, LLC | $6,104,473 | Low | -10% |
| 2 | O. Trevino Construction, LLC | $6,246,498 | +2.0% | -7.0% |
| 3 | Austin Bridge & Road Services, LP | $6,300,294 | +3.0% | -7.0% |
| 4 | Peachtree Construction, LTD. | $6,990,352 | +15% | +4.0% |
| 5 | Texas Materials Group, Inc. | $7,332,537 | +20% | +9.0% |
| 6 | Grey Sky Construction LLC | $7,367,930 | +21% | +9.0% |
Engineer's estimate: $6,747,051.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Foutsco Paving Company, LLC | 2. O. Trevino Construction, LLC | 3. Austin Bridge & Road Services, LP | 4. Peachtree Construction, LTD. | 5. Texas Materials Group, Inc. | 6. Grey Sky Construction LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Tom-C PG76-22 sac-A (347-7001) | TON | 10,257 | $160.00 | $206.50 | $184.40 | $187.00 | $217.50 | $205.00 | $180.00 |
| 2 | Tack coat (347-7011) | GAL | 26,050 | $5.00 | $1.00 | $4.25 | $5.00 | $1.00 | $4.65 | $5.00 |
| 3 | Planing asphalt concrete pavement(0" to 3") (354-7033) | SY | 236,811 | $3.50 | $1.00 | $2.40 | $2.00 | $2.75 | $3.25 | $3.50 |
| 4 | Full-depth repair CPCD (10") (361-7051) | SY | 5,005 | $300.00 | $200.00 | $299.00 | $333.25 | $325.00 | $355.00 | $400.00 |
| 5 | Flowable backfill (401-7001) | CY | 236 | $300.00 | $600.00 | $220.00 | $463.29 | $248.00 | $285.00 | $300.00 |
| 6 | Approach slab (HPC) (422-7014) | CY | 5 | $1,000.00 | $2,500.00 | $7,000.00 | $1,052.94 | $7,500.00 | $8,100.00 | $1,500.00 |
| 7 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 32 | $275.00 | $210.00 | $580.00 | $199.00 | $375.00 | $240.00 | $500.00 |
| 8 | Riprap (concrete)(4 in) (432-7001) | CY | 1 | $700.00 | $5,000.00 | $5,000.00 | $3,838.56 | $5,500.00 | $5,769.08 | $550.00 |
| 9 | Riprap (mow strip)(4 in) (432-7013) | CY | 14 | $700.00 | $750.00 | $1,380.00 | $628.45 | $875.00 | $622.16 | $550.00 |
| 10 | Cleaning and sealing existing joints (438-7001) | LF | 2,904 | $40.00 | $18.00 | $26.00 | $26.00 | $36.75 | $32.00 | $40.00 |
| 11 | Cleaning and sealing existing joints (CL3) (438-7004) | LF | 82 | $50.00 | $160.00 | $130.00 | $37.00 | $32.50 | $41.85 | $100.00 |
| 12 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 348 | $50.00 | $23.00 | $70.00 | $36.00 | $70.00 | $40.72 | $100.00 |
| 13 | Cleaning and sealing joints (foam) (438-7010) | LF | 516 | $140.00 | $65.00 | $120.00 | $75.00 | $106.00 | $90.00 | $100.00 |
| 14 | Mobilization (500-7001) | LS | 1 | $656,860 | $600,000 | $624,800 | $693,032 | $500,000 | $730,958 | $700,000 |
| 15 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $45,000 | $99,000 | $9,000.00 | $27,654 | $35,000 | $25,000 | $10,000 |
| 16 | Portable changeable message sign (503-7002) | EACH | 4 | $25,000 | $2,500.00 | $19,000 | $5,250.00 | $20,000 | $20,000 | $20,000 |
| 17 | TMA (stationary) (505-7001) | DAY | 392 | $275.00 | $1.00 | $180.00 | $2.00 | $155.00 | $335.00 | $250.00 |
| 18 | TMA (mobile operation) (505-7003) | DAY | 10 | $275.00 | $1.00 | $60.00 | $10.00 | $250.00 | $1.00 | $550.00 |
| 19 | Temporary sediment control fence (install) (506-7039) | LF | 1,000 | $3.50 | $1.00 | $3.70 | $3.60 | $5.25 | $5.66 | $4.00 |
| 20 | Temporary SDMT cont fence (inlet protection) (506-7040) | LF | 2,000 | $8.25 | $1.00 | $8.90 | $8.50 | $11.50 | $12.44 | $6.00 |
| 21 | Temporary sediment control fence (remove) (506-7041) | LF | 3,000 | $1.00 | $0.50 | $1.15 | $1.10 | $1.55 | $1.70 | $2.00 |
| 22 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 2,000 | $4.25 | $1.00 | $6.02 | $5.75 | $6.25 | $6.79 | $10.00 |
| 23 | Biodegradable erosion control logs (remove) (506-7046) | LF | 2,000 | $1.25 | $0.50 | $1.31 | $1.25 | $1.60 | $1.70 | $5.00 |
| 24 | Concrete curb (type I) (529-7001) | LF | 250 | $55.00 | $25.00 | $70.00 | $17.98 | $75.00 | $79.18 | $65.00 |
| 25 | Concrete curb (type II) (529-7002) | LF | 500 | $55.00 | $25.00 | $72.00 | $19.68 | $80.00 | $84.84 | $75.00 |
| 26 | Metal W-beam guard fence (timber post) (540-7001) | LF | 300 | $25.00 | $23.00 | $34.55 | $22.50 | $31.50 | $25.45 | $30.00 |
| 27 | Downstream anchor terminal section (540-7015) | EACH | 2 | $1,500.00 | $1,200.00 | $1,417.02 | $1,200.00 | $1,300.00 | $1,357.43 | $1,850.00 |
| 28 | Remove metal beam guard fence (542-7001) | LF | 240 | $4.00 | $3.00 | $3.51 | $2.75 | $3.25 | $3.11 | $3.00 |
| 29 | Remove terminal anchor section (542-7002) | EACH | 2 | $350.00 | $200.00 | $257.65 | $200.00 | $235.00 | $226.24 | $500.00 |
| 30 | Guardrail end treatment (install) (544-7001) | EACH | 2 | $3,200.00 | $3,000.00 | $4,040.27 | $2,950.00 | $3,700.00 | $3,337.01 | $3,850.00 |
| 31 | Guardrail end treatment (remove) (544-7003) | EACH | 2 | $600.00 | $250.00 | $386.46 | $250.00 | $355.00 | $282.80 | $1,500.00 |
| 32 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 7 | $35.00 | $25.00 | $35.13 | $25.00 | $32.50 | $28.28 | $100.00 |
| 33 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 25,866 | $1.00 | $0.20 | $0.23 | $0.20 | $0.60 | $0.23 | $0.75 |
| 34 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 59,474 | $1.00 | $0.20 | $0.23 | $0.20 | $0.60 | $0.23 | $0.75 |
| 35 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 59,474 | $1.00 | $0.20 | $0.23 | $0.20 | $0.60 | $0.23 | $0.75 |
| 36 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 15,520 | $1.25 | $0.10 | $3.91 | $0.50 | $2.75 | $1.38 | $6.00 |
| 37 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 12,688 | $2.00 | $0.85 | $0.99 | $0.85 | $1.35 | $0.96 | $4.00 |
| 38 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 4,363 | $6.00 | $3.00 | $3.50 | $3.00 | $4.50 | $3.39 | $6.00 |
| 39 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 2,588 | $7.00 | $6.25 | $7.29 | $6.25 | $6.75 | $7.07 | $12.00 |
| 40 | Reflectorized pavement marking type I(W)(U-LT arrow)(100 mil) (666-7054) | EACH | 71 | $85.00 | $225.00 | $262.26 | $225.00 | $170.00 | $254.52 | $500.00 |
| 41 | Reflectorized pavement marking type I (W)(number)(100MIL) (666-7063) | EACH | 28 | $80.00 | $110.00 | $128.22 | $110.00 | $165.00 | $124.43 | $500.00 |
| 42 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 92 | $85.00 | $150.00 | $174.84 | $150.00 | $190.00 | $169.68 | $500.00 |
| 43 | Pavement sler 6" (666-7347) | LF | 4,000 | $0.75 | $0.19 | $0.22 | $0.19 | $0.55 | $0.22 | $1.00 |
| 44 | Pavement sler 8" (666-7348) | LF | 1,269 | $0.75 | $0.32 | $0.37 | $0.32 | $1.05 | $0.36 | $6.00 |
| 45 | Pavement sler 12" (666-7350) | LF | 220 | $1.00 | $0.70 | $0.82 | $0.70 | $2.70 | $0.79 | $8.00 |
| 46 | Pavement sler 24" (666-7352) | LF | 259 | $1.25 | $0.75 | $0.87 | $0.75 | $3.75 | $0.85 | $20.00 |
| 47 | Pavement sler (arrow) (666-7353) | EACH | 10 | $40.00 | $20.00 | $23.31 | $20.00 | $108.00 | $22.62 | $250.00 |
| 48 | Pavement sler (word) (666-7354) | EACH | 10 | $35.00 | $20.00 | $23.31 | $20.00 | $108.00 | $22.62 | $250.00 |
| 49 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 42,911 | $1.00 | $0.53 | $0.62 | $0.53 | $0.80 | $0.60 | $0.75 |
| 50 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 60,912 | $1.00 | $0.53 | $0.62 | $0.53 | $0.80 | $0.60 | $0.75 |
| 51 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 60,912 | $1.00 | $0.53 | $0.62 | $0.53 | $0.80 | $0.60 | $0.75 |
| 52 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 2,600 | $6.00 | $3.70 | $4.31 | $3.70 | $5.25 | $4.19 | $6.00 |
| 53 | Eliminating existing PM & markers (6") (677-7002) | LF | 4,000 | $0.75 | $1.00 | $1.17 | $1.00 | $1.05 | $1.13 | $0.75 |
| 54 | Eliminating existing PM & markers (8") (677-7004) | LF | 1,269 | $1.00 | $1.10 | $1.28 | $1.10 | $2.15 | $1.24 | $6.00 |
| 55 | Eliminating existing PM & markers (12") (677-7006) | LF | 220 | $1.25 | $2.00 | $2.33 | $2.00 | $3.25 | $2.26 | $8.00 |
| 56 | Eliminating existing PM & markers (24") (677-7008) | LF | 259 | $3.50 | $3.00 | $3.50 | $3.00 | $5.25 | $3.39 | $20.00 |
| 57 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 10 | $60.00 | $75.00 | $87.42 | $75.00 | $215.00 | $84.84 | $250.00 |
| 58 | Eliminating existing PM & markers (word) (677-7015) | EACH | 10 | $60.00 | $75.00 | $87.42 | $75.00 | $215.00 | $84.84 | $250.00 |
| 59 | Pavement surface preparation for marking (6") (678-7002) | LF | 4,000 | $1.00 | $0.29 | $0.34 | $0.29 | $0.05 | $0.33 | $1.00 |
| 60 | Pavement surface preparation for marking (8") (678-7004) | LF | 1,269 | $1.00 | $0.40 | $0.47 | $0.40 | $0.05 | $0.45 | $6.00 |
| 61 | Pavement surface preparation for marking (12") (678-7006) | LF | 220 | $1.25 | $0.70 | $0.82 | $0.70 | $0.05 | $0.79 | $8.00 |
| 62 | Pavement surface preparation for marking (24") (678-7008) | LF | 259 | $1.50 | $0.75 | $0.87 | $0.75 | $0.05 | $0.85 | $20.00 |
| 63 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 10 | $25.00 | $25.00 | $28.92 | $25.00 | $0.05 | $28.28 | $250.00 |
| 64 | Pavement surface preparation for marking (word) (678-7016) | EACH | 10 | $25.00 | $25.00 | $28.92 | $25.00 | $0.05 | $28.28 | $250.00 |
| 65 | Vehicle LP detect (sawcut) (688-7004) | LF | 5,731 | $15.00 | $17.00 | $50.17 | $36.00 | $52.00 | $57.53 | $12.00 |
| 66 | JT cleaning and sealing (expansion JTS) (713-7003) | LF | 322 | $50.00 | $32.00 | $61.00 | $33.00 | $44.00 | $37.33 | $100.00 |
| 67 | Longt crack cleaning and sealing (CRCP) (713-7005) | LF | 749 | $30.00 | $21.00 | $44.50 | $31.00 | $22.75 | $35.07 | $100.00 |
| 68 | Fiber reinforced polymer patching materials (721-7001) | LB | 10,000 | $7.50 | $7.50 | $4.75 | $7.25 | $5.00 | $5.37 | $12.00 |
| 69 | Spot tree trimming / brush removal (752-7002) | LF | 60 | $30.00 | $50.00 | $150.00 | $31.92 | $21.50 | $113.12 | $500.00 |
| 70 | CNC crack repair (discrete)(inject) (780-7002) | LF | 1,701 | $100.00 | $87.00 | $90.00 | $96.00 | $94.00 | $108.59 | $100.00 |
| 71 | Ground box (prepare) (6013-7006) | EACH | 44 | $400.00 | $800.00 | $534.92 | $780.00 | $555.00 | $582.56 | $50.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.