TxDOT contract A00189581 bid tabulation
EROSION REPAIR, FM0306 (AT SUCHE CREEK to AND AT POTTER CREEK). Let by Texas DOT on February 20, 2025, Comal, San Antonio District. 13 bids received; low bid $135,300 by BK Field Operations LLC, -29% against the engineer's estimate of $190,731.
- Owner
- Texas DOT
- Letting
- 20 FEB 2025
- Pay items
- 21
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | BK Field Operations LLC | $135,300 | Low | -29% |
| 2 | USA DT Services, Inc. | $182,110 | +35% | -5.0% |
| 3 | Diamond R Contracting, LLC | $190,223 | +41% | 0.0% |
| 4 | Aad Contracting Inc. | $193,159 | +43% | +1.0% |
| 5 | Beck-Reit & Sons, LTD. | $196,259 | +45% | +3.0% |
| 6 | Delgado'S Contractors, LLC | $198,084 | +46% | +4.0% |
| 7 | Texas Road Construction, LLC | $209,402 | +55% | +10% |
| 8 | Lakey, Inc. | $226,613 | +67% | +19% |
| 9 | Icos Management, LLC | $228,555 | +69% | +20% |
| 10 | Rhino Equity, LLC | $232,778 | +72% | +22% |
| 11 | Crackseal of Texas, LLC | $233,750 | +73% | +23% |
| 12 | Taylor Contracting LLC | $230,177 | +70% | +21% |
| 13 | Structural Integrity Group LLC | $285,687 | +111% | +50% |
Engineer's estimate: $190,731.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. BK Field Operations LLC | 2. USA DT Services, Inc. | 3. Diamond R Contracting, LLC | 4. Aad Contracting Inc. | 5. Beck-Reit & Sons, LTD. | 6. Delgado'S Contractors, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Excavation (channel) (110-7002) | CY | 30 | $94.33 | $30.00 | $50.00 | $100.00 | $20.00 | $100.00 | $40.00 |
| 2 | Embankment (final)(OC)(type B) (132-7003) | CY | 240 | $61.50 | $1.00 | $50.00 | $65.00 | $55.00 | $50.00 | $55.00 |
| 3 | Compost manuf topsoil (4") (161-7002) | SY | 500 | $1.50 | $10.00 | $20.00 | $5.00 | $8.00 | $5.00 | $15.00 |
| 4 | Broadcast seed (permanent_urban_clay) (164-7004) | SY | 500 | $0.24 | $1.00 | $1.00 | $1.00 | $2.00 | $1.00 | $3.50 |
| 5 | Soil ret BLKT(SL_mod_clay_long) (169-7002) | SY | 500 | $4.79 | $2.00 | $2.00 | $1.00 | $6.00 | $5.00 | $5.00 |
| 6 | Flowable backfill (401-7001) | CY | 35 | $323.91 | $50.00 | $300.00 | $100.00 | $275.00 | $288.00 | $325.00 |
| 7 | Riprap (concrete)(5 in) (432-7002) | CY | 120 | $650.00 | $515.00 | $300.00 | $650.00 | $300.00 | $711.00 | $630.00 |
| 8 | Riprap (mow strip)(4 in) (432-7013) | CY | 7 | $755.25 | $475.00 | $300.00 | $1,000.00 | $400.00 | $800.00 | $725.00 |
| 9 | Riprap (stone common)(dry)(6 in) (432-7029) | CY | 89 | $238.75 | $30.00 | $138.00 | $100.00 | $140.00 | $165.00 | $120.00 |
| 10 | Gabion mattresses (galvanized)(12 in) (459-7007) | SY | 118 | $103.26 | $100.00 | $139.42 | $100.00 | $200.00 | $150.00 | $105.00 |
| 11 | Gabion (1.5' X 3')(galvanized) (459-7014) | CY | 33 | $210.00 | $230.00 | $200.00 | $100.00 | $200.00 | $255.00 | $365.00 |
| 12 | Mobilization (500-7001) | LS | 1 | $12,000 | $25,000 | $63,700 | $10,000 | $25,000 | $10,000 | $15,500 |
| 13 | Barricades, signs and traffic handling (502-7001) | MO | 2 | $3,500.00 | $1.00 | $2,000.00 | $10,000 | $10,000 | $2,500.00 | $2,750.00 |
| 14 | TMA (stationary) (505-7001) | DAY | 25 | $196.61 | $1.00 | $100.00 | $1.00 | $350.00 | $1.00 | $225.00 |
| 15 | Rock filter dams (remove) (506-7012) | CY | 4 | $14.20 | $100.00 | $1.00 | $1,000.00 | $12.00 | $1.00 | $50.00 |
| 16 | Construction exits (install) (type 1) (506-7020) | SY | 224 | $22.80 | $1.00 | $0.10 | $1.00 | $8.00 | $15.00 | $24.00 |
| 17 | Construction exits (remove) (506-7024) | SY | 224 | $7.45 | $1.00 | $0.10 | $1.00 | $4.00 | $5.00 | $7.00 |
| 18 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 325 | $6.31 | $4.00 | $7.00 | $1.00 | $4.50 | $5.00 | $7.00 |
| 19 | Biodegradable erosion control logs (remove) (506-7046) | LF | 325 | $1.51 | $2.00 | $2.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 20 | Driftwood removal (735-7061) | LS | 2 | $500.00 | $200.00 | $1.00 | $5,000.00 | $8,000.00 | $2,500.00 | $3,000.00 |
| 21 | Tree trimming / brush removal(channels) (752-7003) | ACRE | 0.30 | $2,000.00 | $35,000 | $1.00 | $35,000 | $20,000 | $25,000 | $8,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 20, 2025. Compiled by Mirage Metrics.