TxDOT contract A00190867 bid tabulation
Bridge Replacement, PRESCOTT RD (At Draw to .). Let by Texas DOT on July 1, 2025, Grayson, Paris District. 11 bids received; low bid $2,294,027 by RB Contracting, LLC, -15% against the engineer's estimate of $2,710,840.
- Owner
- Texas DOT
- Letting
- 01 JUL 2025
- Pay items
- 39
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | RB Contracting, LLC | $2,294,027 | Low | -15% |
| 2 | THK Construction LLC | $2,427,098 | +6.0% | -10% |
| 3 | Highway 19 Construction LLC | $2,459,769 | +7.0% | -9.0% |
| 4 | Hodges and Son Construction Company, Inc. | $2,473,129 | +8.0% | -9.0% |
| 5 | STX Civil | $2,605,424 | +14% | -4.0% |
| 6 | L & N Bridge, LLC | $2,695,837 | +18% | -1.0% |
| 7 | East Texas Bridge, Inc. | $2,768,436 | +21% | +2.0% |
| 8 | Skyline Bridge LLC | $2,968,416 | +29% | +10% |
| 9 | Talbert Companies LLC | $3,037,219 | +32% | +12% |
| 10 | Grey Sky Construction LLC | $3,400,910 | +48% | +25% |
| 11 | Indus Road & Bridge, Inc. | $6,945,677 | +203% | +156% |
Engineer's estimate: $2,710,840.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. RB Contracting, LLC | 2. THK Construction LLC | 3. Highway 19 Construction LLC | 4. Hodges and Son Construction Company, Inc. | 5. STX Civil | 6. L & N Bridge, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 20.51 | $3,000.00 | $3,500.00 | $1,500.00 | $2,500.00 | $5,800.00 | $3,600.00 | $5,000.00 |
| 2 | Excavation (roadway) (110-7001) | CY | 1,076 | $20.00 | $25.00 | $20.00 | $25.00 | $15.00 | $30.00 | $40.00 |
| 3 | Excavation (channel) (110-7002) | CY | 1,628 | $20.00 | $25.00 | $20.00 | $25.00 | $15.00 | $40.00 | $25.00 |
| 4 | Embankment (final)(OC)(type B) (132-7003) | CY | 1,320 | $32.00 | $14.00 | $20.00 | $24.00 | $25.00 | $38.00 | $40.00 |
| 5 | Broadcast seed (temporary_warm) (164-7005) | SY | 2,605 | $1.00 | $0.67 | $2.34 | $0.15 | $1.50 | $1.00 | $0.50 |
| 6 | Broadcast seed (temporary_cool) (164-7006) | SY | 2,605 | $1.00 | $0.67 | $2.44 | $0.15 | $1.50 | $1.00 | $0.50 |
| 7 | Hydro mulch seed (permanent_rural_clay) (164-7018) | SY | 5,207 | $1.60 | $0.81 | $2.68 | $1.00 | $2.50 | $2.00 | $0.60 |
| 8 | Vegetative watering (168-7001) | TGL | 32 | $30.00 | $100.00 | $10.00 | $10.00 | $1.00 | $50.00 | $250.00 |
| 9 | FL BS (compacted in place)(type A GR 4) (6") (247-7046) | SY | 2,801 | $35.00 | $40.00 | $27.00 | $40.00 | $18.00 | $30.00 | |
| 10 | FL BS (compacted in place)(type D GR 4) (6") (247-7058) | SY | 1,521 | $45.00 | $35.00 | $40.00 | $27.00 | $40.00 | $18.00 | $30.00 |
| 11 | Cem stabil BKFL (400-7010) | CY | 273 | $275.00 | $225.00 | $300.00 | $350.00 | $300.00 | $250.00 | $350.00 |
| 12 | Drilled shaft (24 in) (416-7004) | LF | 1,137 | $290.00 | $170.00 | $173.35 | $194.00 | $130.00 | $240.00 | $200.00 |
| 13 | Drilled shaft (30 in) (416-7005) | LF | 239.10 | $210.00 | $243.93 | $255.00 | $190.00 | $280.00 | $250.00 | |
| 14 | Drilled shaft (36 in) (416-7006) | LF | 312 | $225.00 | $249.76 | $295.00 | $215.00 | $320.00 | $290.00 | |
| 15 | Class C concrete (abutment) (420-7012) | CY | 140.60 | $1,270.00 | $1,170.00 | $1,100.00 | $1,500.00 | $2,000.00 | $1,300.00 | $1,800.00 |
| 16 | Reinforced concrete slab (422-7001) | SF | 1,430 | $30.00 | $34.00 | $30.00 | $30.00 | $30.00 | $30.00 | |
| 17 | Reinforced concrete slab (box beam) (422-7005) | SF | 1,701 | $30.00 | $24.00 | $20.00 | $26.00 | $26.00 | $25.00 | |
| 18 | Reinforced concrete slab (slab beam) (422-7007) | SF | 4,420 | $24.00 | $29.00 | $21.00 | $20.00 | $26.00 | $26.00 | $25.00 |
| 19 | Shear key (422-7020) | CY | 8.60 | $1,000.00 | $800.00 | $350.00 | $850.00 | $520.00 | $1,000.00 | |
| 20 | Prestressed concrete girder (TX28) (425-7001) | LF | 218 | $435.00 | $309.03 | $355.00 | $310.00 | $290.00 | $450.00 | |
| 21 | Prestressed concrete slab beam (5SB12) (425-7017) | LF | 345 | $340.00 | $360.00 | $339.14 | $331.00 | $290.00 | $220.00 | $450.00 |
| 22 | Prestressed concrete slab beam (5SB15) (425-7019) | LF | 494.91 | $330.00 | $316.40 | $331.00 | $290.00 | $240.00 | $450.00 | |
| 23 | Prestressed concrete box beam (4B20) (425-7026) | LF | 258 | $365.00 | $363.02 | $409.00 | $370.00 | $290.00 | $450.00 | |
| 24 | Prestressed concrete box beam (5B20) (425-7027) | LF | 129 | $355.00 | $414.18 | $409.00 | $370.00 | $310.00 | $450.00 | |
| 25 | Riprap (stone protection)(18 in) (432-7043) | CY | 1,378 | $190.00 | $175.00 | $170.00 | $180.00 | $200.00 | $215.00 | $200.00 |
| 26 | Rail (type T631LS) (450-7021) | LF | 740 | $75.00 | $77.00 | $74.45 | $80.00 | $70.00 | $100.00 | $80.00 |
| 27 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 6 | $15,000 | $3,000.00 | $30,000 | $10,000 | $20,000 | $35,000 | $7,500.00 |
| 28 | Mobilization (500-7001) | LS | 1 | $261,311 | $100,000 | $220,000 | $300,000 | $210,000 | $204,112 | $200,000 |
| 29 | Barricades, signs and traffic handling (502-7001) | MO | 22 | $1,500.00 | $4,000.00 | $1,381.50 | $1,700.00 | $2,000.00 | $3,500.00 | $622.44 |
| 30 | Rock filter dams (install) (type 2) (506-7002) | LF | 344 | $60.00 | $76.00 | $33.00 | $55.00 | $1.00 | $50.00 | $45.00 |
| 31 | Rock filter dams (remove) (506-7011) | LF | 344 | $17.00 | $27.00 | $10.00 | $10.00 | $1.00 | $25.00 | $9.00 |
| 32 | Construction exits (install) (type 1) (506-7020) | SY | 635 | $25.00 | $28.00 | $33.00 | $1.00 | $1.00 | $28.00 | $32.00 |
| 33 | Construction exits (remove) (506-7024) | SY | 635 | $6.00 | $10.00 | $10.00 | $1.00 | $1.00 | $13.00 | $6.00 |
| 34 | Temporary sediment control fence (install) (506-7039) | LF | 525 | $5.00 | $4.40 | $5.00 | $1.00 | $4.00 | $3.60 | |
| 35 | Temporary sediment control fence (remove) (506-7041) | LF | 525 | $1.00 | $1.65 | $1.00 | $1.00 | $1.50 | $1.25 | |
| 36 | Metal W-beam guard fence (steel post) (540-7002) | LF | 730 | $32.00 | $34.00 | $29.98 | $26.00 | $28.00 | $30.00 | $27.25 |
| 37 | Guardrail end treatment (install) (544-7001) | EACH | 24 | $3,250.00 | $3,635.00 | $3,300.00 | $2,990.00 | $3,050.00 | $3,300.00 | $3,000.00 |
| 38 | Remove SM RD SN sup&AM (644-7073) | EACH | 6 | $100.00 | $50.00 | $250.00 | $100.00 | $50.00 | $80.00 | $50.00 |
| 39 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 56 | $40.00 | $38.00 | $27.50 | $25.00 | $25.00 | $25.00 | $25.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 1, 2025. Compiled by Mirage Metrics.