TxDOT contract A00193149 bid tabulation
Hazard Elimination & Safety, SH 29 (SH 71 to 0.110 MI E of Zula Rd). Let by Texas DOT on August 5, 2026, Llano, Austin District. 6 bids received; low bid $2,462,865 by Big Creek Construction, LTD., -1.0% against the engineer's estimate of $2,487,668.
- Owner
- Texas DOT
- Letting
- 05 AUG 2026
- Pay items
- 76
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Big Creek Construction, LTD. | $2,462,865 | Low | -1.0% |
| 2 | Texas Materials Group, Inc. | $2,482,786 | +1.0% | 0.0% |
| 3 | Hunter Industries, LTD. | $2,542,785 | +3.0% | +2.0% |
| 4 | MPB, Inc. | $2,733,015 | +11% | +10% |
| 5 | Joe Bland Construction LLC | $2,892,090 | +17% | +16% |
| 6 | Aaron Concrete Contractors, LLC | $3,628,803 | +47% | +46% |
Engineer's estimate: $2,487,668.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Big Creek Construction, LTD. | 2. Texas Materials Group, Inc. | 3. Hunter Industries, LTD. | 4. MPB, Inc. | 5. Joe Bland Construction LLC | 6. Aaron Concrete Contractors, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 93.93 | $1,050.00 | $700.00 | $220.00 | $610.50 | $390.00 | $750.00 | $358.00 |
| 2 | Tree protection (install) (100-7013) | EACH | 10 | $280.00 | $425.00 | $272.50 | $1,100.00 | $286.00 | $300.00 | $1,356.00 |
| 3 | Removing concrete (medians) (104-7008) | SY | 33 | $45.00 | $25.00 | $60.00 | $26.40 | $40.00 | $50.00 | $36.00 |
| 4 | Removing concrete (curb & gutter) (104-7017) | LF | 80 | $11.00 | $11.00 | $40.00 | $13.20 | $11.45 | $12.00 | $15.00 |
| 5 | Remove (0"-12") TRT/untrt base & asphalt pavement (105-7052) | SY | 423 | $7.40 | $11.00 | $23.00 | $9.90 | $11.15 | $15.00 | $30.00 |
| 6 | Remove stab base and asphalt pavement (6"-20") (105-7123) | SY | 9,494 | $12.50 | $11.00 | $6.25 | $6.60 | $10.40 | $10.00 | $26.00 |
| 7 | Excavation (roadway) (110-7001) | CY | 6,948 | $13.50 | $22.00 | $19.00 | $25.30 | $12.81 | $24.00 | $40.00 |
| 8 | Embankment (final)(OC)(type B) (132-7003) | CY | 1,982 | $15.00 | $22.00 | $9.50 | $25.30 | $13.35 | $8.00 | $9.00 |
| 9 | Backfill (type A) (134-7001) | STA | 5 | $215.00 | $300.00 | $750.00 | $153.50 | $1,082.00 | $1,500.00 | $446.00 |
| 10 | Furn & place topsoil (4") (160-7002) | SY | 20,587 | $1.75 | $1.45 | $6.00 | $1.26 | $1.42 | $1.50 | $2.00 |
| 11 | Broadcast seed (temporary_warm_cool) (164-7007) | SY | 20,587 | $0.25 | $0.18 | $0.07 | $0.16 | $0.23 | $0.25 | $0.20 |
| 12 | Drill seed (permanent_rural_sand) (164-7009) | SY | 20,587 | $0.20 | $0.18 | $0.19 | $0.16 | $0.35 | $0.25 | $0.48 |
| 13 | Vegetative watering (168-7001) | TGL | 345.86 | $13.00 | $35.00 | $50.00 | $26.24 | $105.75 | $50.00 | $68.00 |
| 14 | Soil ret BLKT(SL_mod_sand_long) (169-7004) | SY | 20,587 | $1.75 | $0.65 | $1.09 | $0.59 | $1.16 | $0.75 | $1.00 |
| 15 | Wildflower seeding (180-7001) | ACRE | 4.25 | $1,100.00 | $2,400.00 | $456.50 | $2,169.00 | $480.00 | $2,500.00 | $3,261.00 |
| 16 | FL BS (compacted in place)(type A GR 5)(final pos) (247-7179) | CY | 4,394 | $65.00 | $65.00 | $55.00 | $68.24 | $74.50 | $80.00 | $86.00 |
| 17 | Prime coat (AE-P) (310-7001) | GAL | 3,450 | $5.00 | $5.00 | $5.00 | $4.76 | $5.25 | $4.00 | $6.00 |
| 18 | D-GR HMA type-B PG64-22 (341-7001) | TON | 3,535 | $95.00 | $98.00 | $110.00 | $106.82 | $110.25 | $121.00 | $126.00 |
| 19 | D-GR HMA type D PG70-28 (level-UP) (341-7055) | TON | 420 | $126.00 | $132.00 | $158.00 | $127.56 | $159.60 | $172.00 | $183.00 |
| 20 | D-GR HMA type D PG76-22 (341-7056) | TON | 1,415 | $126.00 | $116.00 | $144.00 | $115.46 | $146.00 | $151.00 | $167.00 |
| 21 | Tom-C PG76-22 sac-B (347-7002) | TON | 2,643 | $130.00 | $130.00 | $161.00 | $138.68 | $165.00 | $178.00 | $189.00 |
| 22 | Flexible pavement structure repair(4") (351-7003) | SY | 5,056 | $32.50 | $32.00 | $35.00 | $33.82 | $36.75 | $40.00 | $42.00 |
| 23 | Plane & text asphalt concrete pavement(1") (354-7017) | SY | 1,222 | $4.00 | $3.50 | $4.00 | $5.50 | $5.25 | $6.00 | $6.00 |
| 24 | Plane & text asphalt concrete pavement(2") (354-7019) | SY | 2,260 | $2.00 | $4.50 | $3.76 | $4.40 | $3.57 | $4.00 | $4.00 |
| 25 | Planing asphalt concrete pavement(0" to 1" micro) (354-7045) | SY | 3,593 | $1.65 | $3.50 | $2.50 | $4.40 | $2.52 | $3.50 | $3.00 |
| 26 | Riprap (stone protection)(18 in) (432-7043) | CY | 5 | $200.00 | $440.00 | $662.17 | $424.04 | $530.00 | $375.00 | $397.00 |
| 27 | RC pipe (CL III)(18 in) (464-7003) | LF | 171 | $90.00 | $90.00 | $150.00 | $90.00 | $155.00 | $125.00 | $442.00 |
| 28 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 8 | $1,500.00 | $1,750.00 | $3,000.00 | $2,700.00 | $2,350.00 | $3,250.00 | $2,506.00 |
| 29 | Clean existing culverts (480-7001) | EACH | 3 | $1,500.00 | $2,700.00 | $3,200.00 | $2,200.00 | $6,355.00 | $5,500.00 | $33,624 |
| 30 | Removing structure (set) (496-7004) | EACH | 8 | $525.00 | $385.00 | $275.00 | $850.00 | $250.00 | $2,500.00 | $1,492.00 |
| 31 | Removing structure (pipe) (496-7007) | LF | 165 | $25.00 | $18.00 | $15.00 | $35.00 | $16.00 | $45.00 | $39.00 |
| 32 | Mobilization (500-7001) | LS | 1 | $184,275 | $103,500 | $55,000 | $228,181 | $225,000 | $125,000 | $279,000 |
| 33 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $7,500.00 | $5,000.00 | $6,000.00 | $3,252.22 | $1,500.00 | $1,500.00 | $1,694.00 |
| 34 | Portable changeable message sign (503-7001) | DAY | 540 | $40.00 | $70.00 | $30.00 | $54.13 | $78.00 | $100.00 | $84.00 |
| 35 | TMA (stationary) (505-7001) | DAY | 270 | $200.00 | $200.00 | $100.00 | $81.19 | $150.00 | $165.00 | $264.00 |
| 36 | TMA (mobile operation) (505-7003) | DAY | 30 | $225.00 | $500.00 | $1.00 | $119.08 | $350.00 | $375.00 | $264.00 |
| 37 | Rock filter dams (install) (type 2) (506-7002) | LF | 227 | $50.00 | $41.00 | $51.15 | $50.97 | $59.50 | $60.00 | $65.00 |
| 38 | Rock filter dams (remove) (506-7011) | LF | 227 | $13.00 | $5.00 | $40.70 | $17.89 | $11.87 | $20.00 | $37.00 |
| 39 | Construction exits (install) (type 1) (506-7020) | SY | 312 | $30.00 | $26.00 | $38.00 | $41.14 | $24.68 | $50.00 | $37.00 |
| 40 | Construction exits (remove) (506-7024) | SY | 312 | $9.00 | $5.00 | $12.00 | $15.36 | $7.82 | $15.00 | $30.00 |
| 41 | Temporary sediment control fence (install) (506-7039) | LF | 6,606 | $4.50 | $3.50 | $3.97 | $4.39 | $4.26 | $6.00 | $5.00 |
| 42 | Temporary sediment control fence (remove) (506-7041) | LF | 6,606 | $1.00 | $1.00 | $0.79 | $1.03 | $0.63 | $1.00 | $2.00 |
| 43 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 2,488 | $6.00 | $5.50 | $5.68 | $6.23 | $7.12 | $9.00 | $6.00 |
| 44 | Biodegradable erosion control logs (remove) (506-7046) | LF | 2,488 | $1.30 | $2.00 | $0.76 | $1.03 | $1.05 | $3.00 | $2.00 |
| 45 | Concrete curb & gutter (type II) (529-7009) | LF | 80 | $35.00 | $110.00 | $100.00 | $52.00 | $35.00 | $50.00 | $40.00 |
| 46 | Intrsct, drvways, & turnout (ACP) (530-7022) | SY | 881 | $49.00 | $80.00 | $80.45 | $39.42 | $91.50 | $40.00 | $96.00 |
| 47 | Concrete median (536-7001) | LF | 29 | $73.00 | $310.00 | $230.00 | $120.00 | $195.00 | $325.00 | $374.00 |
| 48 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 2 | $400.00 | $300.00 | $275.00 | $340.00 | $288.75 | $315.00 | $331.00 |
| 49 | Mailbox install-M (TWW-post) type 4 (560-7010) | EACH | 2 | $850.00 | $630.00 | $575.00 | $610.00 | $603.75 | $650.00 | $692.00 |
| 50 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 7 | $700.00 | $715.00 | $651.49 | $725.00 | $685.00 | $725.00 | $784.00 |
| 51 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 2 | $750.00 | $1,125.00 | $1,021.00 | $777.00 | $1,075.00 | $1,150.00 | $1,228.00 |
| 52 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 2 | $800.00 | $975.00 | $885.00 | $1,060.00 | $930.00 | $1,000.00 | $1,065.00 |
| 53 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 1 | $900.00 | $1,325.00 | $1,204.33 | $1,265.00 | $1,265.00 | $1,350.00 | $1,449.00 |
| 54 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 2 | $1,000.00 | $1,325.00 | $1,204.33 | $1,265.00 | $1,265.00 | $1,350.00 | $1,449.00 |
| 55 | Remove SM RD SN sup&AM (644-7073) | EACH | 13 | $110.00 | $95.00 | $87.00 | $100.00 | $91.35 | $95.00 | $105.00 |
| 56 | Install delineator assembly (D-SW)SZ 1(WFLX)GND(BI) (658-7004) | EACH | 37 | $70.00 | $95.00 | $87.00 | $124.00 | $91.35 | $95.00 | $105.00 |
| 57 | Install object marker assembly (OM-1)(WFLX)GND (658-7054) | EACH | 7 | $225.00 | $95.00 | $87.00 | $160.00 | $91.35 | $95.00 | $105.00 |
| 58 | Remove delin & object marker assms (658-7078) | EACH | 6 | $25.00 | $11.00 | $200.00 | $50.00 | $10.50 | $12.00 | $12.00 |
| 59 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 18,704 | $0.30 | $0.33 | $0.30 | $0.21 | $0.32 | $0.50 | $0.36 |
| 60 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 2,291 | $0.30 | $0.33 | $0.30 | $0.23 | $0.32 | $0.50 | $0.36 |
| 61 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 18,786 | $0.30 | $0.33 | $0.30 | $0.21 | $0.32 | $0.50 | $0.36 |
| 62 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 1,282 | $1.50 | $1.50 | $1.00 | $1.63 | $2.50 | $1.25 | $2.00 |
| 63 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 866 | $1.50 | $1.50 | $1.00 | $1.63 | $2.50 | $1.25 | $2.00 |
| 64 | Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023) | LF | 121 | $0.90 | $1.10 | $1.00 | $1.50 | $1.05 | $1.25 | $1.00 |
| 65 | Reflectorized pavement marking type II (W) 6" (broken) (666-7172) | LF | 500 | $0.50 | $0.33 | $0.30 | $0.45 | $0.32 | $0.50 | $0.36 |
| 66 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 2,000 | $0.19 | $0.33 | $0.30 | $0.45 | $0.32 | $0.50 | $0.36 |
| 67 | Reflectorized pavement marking type II (W) 8" (solid) (666-7179) | LF | 121 | $0.45 | $0.33 | $0.30 | $0.75 | $0.32 | $0.50 | $0.36 |
| 68 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 2,000 | $0.19 | $0.33 | $0.30 | $0.45 | $0.32 | $0.50 | $0.36 |
| 69 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 18,978 | $0.70 | $0.90 | $0.83 | $0.78 | $0.87 | $1.00 | $1.00 |
| 70 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 19,311 | $0.70 | $0.90 | $0.83 | $0.78 | $0.87 | $1.00 | $1.00 |
| 71 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 4,830 | $0.65 | $0.65 | $0.61 | $0.60 | $0.65 | $0.75 | $1.00 |
| 72 | Reflectorized pavement marker type I-C (672-7002) | EACH | 224 | $4.40 | $5.50 | $5.11 | $6.00 | $5.37 | $6.00 | $6.00 |
| 73 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 224 | $4.40 | $5.50 | $5.11 | $6.50 | $5.37 | $6.00 | $6.00 |
| 74 | Eliminating existing PM & markers (6") (677-7002) | LF | 25,830 | $1.00 | $0.62 | $0.50 | $0.75 | $0.55 | $0.75 | $1.00 |
| 75 | Bonding course (3007-7001) | GAL | 7,494 | $3.50 | $5.00 | $4.00 | $3.46 | $4.20 | $4.00 | $5.00 |
| 76 | Temporary speed monitor sys (6016-7001) | EACH | 2 | $15,000 | $10,000 | $6,500.00 | $9,201.25 | $6,905.00 | $7,500.00 | $7,928.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 5, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.