TxDOT contract A00193579 bid tabulation
Hazard Elimination & Safety, BU 82H (Loop 286 to 11th NW St). Let by Texas DOT on September 5, 2025, Lamar, Paris District. 9 bids received; low bid $1,345,111 by Highway 19 Construction LLC, -24% against the engineer's estimate of $1,759,909.
- Owner
- Texas DOT
- Letting
- 05 SEP 2025
- Pay items
- 39
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Highway 19 Construction LLC | $1,345,111 | Low | -24% |
| 2 | Scout 5 Construction LLC | $1,487,006 | +11% | -16% |
| 3 | Garret Shields Infrastructure | $1,583,420 | +18% | -10% |
| 4 | STX Civil | $1,614,877 | +20% | -8.0% |
| 5 | THK Construction LLC | $1,649,862 | +23% | -6.0% |
| 6 | GHB Equipment Company, L.L.C. | $1,695,450 | +26% | -4.0% |
| 7 | RB Contracting, LLC | $1,757,931 | +31% | 0.0% |
| 8 | Ti-Zack Concrete, LLC | $1,887,110 | +40% | +7.0% |
| 9 | O. Trevino Construction, LLC | $2,072,342 | +54% | +18% |
Engineer's estimate: $1,759,909.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Highway 19 Construction LLC | 2. Scout 5 Construction LLC | 3. Garret Shields Infrastructure | 4. STX Civil | 5. THK Construction LLC | 6. GHB Equipment Company, L.L.C. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 91.98 | $2,100.00 | $750.00 | $2,800.00 | $500.00 | $1,000.00 | $650.00 | $420.00 |
| 2 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 19 | $2,000.00 | $1,000.00 | $1,275.00 | $1,500.00 | $500.00 | $880.00 | $960.00 |
| 3 | Preparation row (tree remove) (24"-36" diameter) (100-7005) | EACH | 16 | $2,500.00 | $1,500.00 | $2,200.00 | $2,000.00 | $1,000.00 | $1,650.00 | $1,800.00 |
| 4 | Preparation row (tree remove) (36"-48" diameter) (100-7006) | EACH | 2 | $3,500.00 | $3,000.00 | $4,225.00 | $3,000.00 | $1,500.00 | $2,750.00 | $3,000.00 |
| 5 | Removing concrete (driveways) (104-7011) | SY | 1,269 | $25.00 | $25.00 | $21.31 | $40.00 | $25.00 | $24.00 | $32.00 |
| 6 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 319 | $22.00 | $25.00 | $17.76 | $40.00 | $25.00 | $25.00 | $32.00 |
| 7 | Removing concrete (curb ramp) (104-7015) | SY | 144 | $25.00 | $25.00 | $16.36 | $30.00 | $25.00 | $25.00 | $37.50 |
| 8 | Remove (2"-6") TRT/untrt base & asphalt pavement (105-7002) | SY | 72 | $50.00 | $15.00 | $10.55 | $20.00 | $8.00 | $10.00 | $75.00 |
| 9 | Excavation (special) (110-7003) | CY | 1,616 | $30.00 | $25.00 | $35.00 | $20.00 | $45.00 | $25.00 | $75.00 |
| 10 | Embankment (final)(OC)(type B) (132-7003) | CY | 471 | $35.00 | $30.00 | $27.50 | $40.00 | $55.00 | $25.00 | $75.00 |
| 11 | Block sodding (162-7002) | SY | 7,645 | $8.00 | $5.00 | $14.58 | $12.00 | $2.50 | $6.67 | $7.16 |
| 12 | Vegetative watering (168-7001) | TGL | 43 | $125.00 | $100.00 | $27.68 | $50.00 | $1.00 | $10.00 | $110.00 |
| 13 | Bridge sidewalk (422-7012) | SF | 40 | $150.00 | $125.00 | $43.60 | $200.00 | $100.00 | $350.00 | $125.00 |
| 14 | Riprap (concrete)(5 in) (432-7002) | CY | 2 | $950.00 | $1,000.00 | $497.00 | $800.00 | $2,000.00 | $1,000.00 | $1,500.00 |
| 15 | Rail (handrail)(type E) (450-7062) | LF | 24 | $250.00 | $300.00 | $400.00 | $350.00 | $250.00 | $300.00 | $339.23 |
| 16 | Mobilization (500-7001) | LS | 1 | $164,104 | $170,000 | $10,000 | $140,000 | $150,000 | $150,000 | $135,000 |
| 17 | Barricades, signs and traffic handling (502-7001) | MO | 10 | $6,000.00 | $5,000.00 | $0.01 | $5,000.00 | $3,800.00 | $7,000.00 | $6,000.00 |
| 18 | Portable changeable message sign (503-7002) | EACH | 2 | $12,000 | $10,000 | $15,000 | $1,000.00 | $10,000 | $25,000 | $10,000 |
| 19 | TMA (stationary) (505-7001) | DAY | 100 | $175.00 | $250.00 | $0.01 | $300.00 | $1.00 | $300.00 | $500.00 |
| 20 | Temporary sediment control fence (install) (506-7039) | LF | 20 | $20.00 | $5.00 | $4.16 | $5.00 | $10.00 | $82.78 | $12.29 |
| 21 | Temporary sediment control fence (remove) (506-7041) | LF | 20 | $10.00 | $1.00 | $1.16 | $1.00 | $1.00 | $26.88 | $12.29 |
| 22 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 220 | $10.00 | $10.00 | $6.53 | $6.00 | $10.00 | $6.67 | $12.29 |
| 23 | Biodegradable erosion control logs (remove) (506-7046) | LF | 220 | $1.04 | $1.00 | $1.37 | $1.00 | $1.00 | $2.46 | $6.29 |
| 24 | Concrete curb & gutter (type II) (529-7009) | LF | 253 | $80.00 | $55.00 | $34.34 | $40.00 | $60.00 | $60.00 | $84.00 |
| 25 | Driveways (concrete) (530-7006) | SY | 1,264 | $125.00 | $110.00 | $120.00 | $120.00 | $150.00 | $105.00 | $124.00 |
| 26 | Driveways (ACP) (530-7010) | SY | 72 | $65.00 | $75.00 | $65.09 | $100.00 | $130.00 | $100.00 | $150.00 |
| 27 | Driveways (base) (530-7015) | SY | 231 | $35.00 | $35.00 | $23.75 | $30.00 | $70.00 | $60.00 | $80.00 |
| 28 | Concrete sidewalks (5") (531-7002) | SY | 6,488 | $95.00 | $73.63 | $78.66 | $100.00 | $115.00 | $100.00 | $90.50 |
| 29 | Curb ramps (type 3) (531-7007) | EACH | 1 | $3,700.00 | $1,800.00 | $1,300.00 | $3,000.00 | $2,500.00 | $4,000.00 | $7,500.00 |
| 30 | Curb ramps (type 7) (531-7010) | EACH | 42 | $3,700.00 | $1,500.00 | $4,150.00 | $3,000.00 | $2,200.00 | $4,000.00 | $3,750.00 |
| 31 | Curb ramps (type 21) (531-7013) | EACH | 1 | $3,900.00 | $2,500.00 | $3,088.86 | $3,000.00 | $3,000.00 | $4,000.00 | $7,500.00 |
| 32 | Concrete sidewalks (special) (531-7025) | SY | 2 | $400.00 | $350.00 | $139.26 | $200.00 | $500.00 | $1,000.00 | $2,500.00 |
| 33 | Concrete sidewalk (retaining wall) (531-7026) | CY | 27 | $750.00 | $1,150.00 | $200.00 | $1,000.00 | $550.00 | $500.00 | $1,000.00 |
| 34 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 12 | $740.00 | $750.00 | $713.00 | $800.00 | $900.00 | $1,500.00 | $726.00 |
| 35 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 30 | $650.00 | $350.00 | $470.00 | $500.00 | $100.00 | $1,000.00 | $714.00 |
| 36 | Install OM SM RD sign (1-OM-con)Y (658-7079) | EACH | 14 | $15.00 | $750.00 | $15.00 | $20.00 | $40.00 | $100.00 | $30.90 |
| 37 | Install OM SM RD sign (1-OM-con)R (658-7080) | EACH | 34 | $15.00 | $750.00 | $13.00 | $20.00 | $40.00 | $100.00 | $30.90 |
| 38 | Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035) | LF | 105 | $8.00 | $30.00 | $7.08 | $25.00 | $12.00 | $26.88 | $53.15 |
| 39 | Pavement surface preparation for marking (24") (678-7008) | LF | 105 | $4.00 | $20.00 | $1.03 | $25.00 | $8.00 | $26.88 | $41.15 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 5, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.