TxDOT contract A00194279 bid tabulation
Construct Ramps, SL 396 (US 84 to Bagby Avenue). Let by Texas DOT on May 1, 2025, McLennan, Waco District. 6 bids received; low bid $2,695,684 by Ti-Zack Concrete, LLC, -8.8% against the engineer's estimate of $2,956,391.
- Owner
- Texas DOT
- Letting
- 01 MAY 2025
- Pay items
- 71
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ti-Zack Concrete, LLC | $2,695,684 | Low | -9.0% |
| 2 | 3LW Civil LLC | $2,716,165 | +1.0% | -8.0% |
| 3 | STX Civil | $2,793,095 | +4.0% | -6.0% |
| 4 | Talbert Companies LLC | $2,837,524 | +5.0% | -4.0% |
| 5 | Cross Plus Construction, LLC | $2,862,895 | +6.0% | -3.0% |
| 6 | Grey Sky Construction LLC | $3,534,472 | +31% | +20% |
Engineer's estimate: $2,956,391.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Ti-Zack Concrete, LLC | 2. 3LW Civil LLC | 3. STX Civil | 4. Talbert Companies LLC | 5. Cross Plus Construction, LLC | 6. Grey Sky Construction LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparation row (tree prune and trim) (100-7010) | STA | 5 | $1,000.00 | $137.50 | $1,000.00 | $2,200.00 | $2,430.00 | $2,500.00 | $30,000 |
| 2 | Removing concrete (driveways) (104-7011) | SY | 3,690 | $20.00 | $27.80 | $30.00 | $13.00 | $19.73 | $22.50 | $20.00 |
| 3 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 521 | $25.00 | $30.63 | $25.00 | $30.00 | $20.39 | $45.00 | $20.00 |
| 4 | Removing concrete (curb or curb & gutter) (104-7018) | LF | 2,093 | $12.00 | $11.44 | $22.50 | $16.00 | $18.42 | $10.00 | $20.00 |
| 5 | Removing concrete (miscellaneous) (104-7046) | SY | 222 | $41.00 | $35.95 | $25.00 | $30.00 | $25.30 | $12.00 | $50.00 |
| 6 | Remove (4"-8") TRT/untrt base & asphalt pavement (105-7004) | SY | 1,720 | $10.00 | $23.20 | $25.00 | $7.00 | $6.64 | $24.00 | $20.00 |
| 7 | Excavation (special) (110-7003) | CY | 320 | $30.00 | $74.81 | $65.00 | $110.00 | $27.90 | $25.00 | $50.00 |
| 8 | Embankment (final)(OC)(type B) (132-7003) | CY | 2,370 | $45.00 | $51.17 | $55.00 | $45.00 | $39.22 | $42.00 | $40.00 |
| 9 | Block sodding (162-7002) | SY | 12,748 | $6.50 | $5.50 | $8.50 | $7.00 | $6.47 | $8.00 | $8.00 |
| 10 | Vegetative watering (168-7001) | TGL | 115 | $200.00 | $110.00 | $87.39 | $50.00 | $168.75 | $152.00 | $50.00 |
| 11 | Rdside amenity (wheel stop) (194-7007) | EACH | 15 | $300.00 | $165.00 | $150.00 | $260.00 | $393.75 | $250.00 | $500.00 |
| 12 | Rdside amenity (wheel stop removing&reset) (194-7008) | EACH | 25 | $250.00 | $110.00 | $125.00 | $245.00 | $393.75 | $150.00 | $500.00 |
| 13 | D-GR HMA type D PG 76-22 (exempt) (341-7065) | TON | 50 | $180.00 | $330.00 | $450.00 | $400.00 | $509.96 | $250.00 | $500.00 |
| 14 | Plane & text asphalt concrete pavement(0" to 2") (354-7002) | SY | 100 | $5.00 | $22.00 | $4.39 | $5.00 | $56.25 | $25.00 | $50.00 |
| 15 | Cut & restoring pavement (400-7006) | SY | 1,939 | $165.00 | $115.50 | $148.50 | $250.00 | $39.38 | $89.00 | $150.00 |
| 16 | Riprap (concrete)(4 in) (432-7001) | CY | 57 | $500.00 | $824.66 | $660.25 | $800.00 | $602.01 | $750.00 | $550.00 |
| 17 | Rail (handrail)(type E) (450-7062) | LF | 251 | $250.00 | $187.00 | $190.33 | $130.00 | $225.00 | $256.00 | $185.00 |
| 18 | Inlet (complete)(armor curb slot) (465-7335) | EACH | 2 | $4,430.00 | $5,500.00 | $5,186.65 | $9,500.00 | $2,253.96 | $4,212.00 | $15,000 |
| 19 | Inlet (comp)(type sidewalk bridge) (465-7336) | EACH | 4 | $6,000.00 | $13,750 | $14,218 | $15,000 | $9,311.90 | $9,124.00 | $20,000 |
| 20 | Adjusting manholes (479-7001) | EACH | 10 | $2,000.00 | $798.00 | $1,450.00 | $1,500.00 | $3,937.50 | $529.00 | $2,000.00 |
| 21 | Adjusting inlets (479-7002) | EACH | 1 | $1,300.00 | $798.00 | $3,030.00 | $2,000.00 | $3,943.13 | $1,250.00 | $5,000.00 |
| 22 | Adjusting manholes (utility box) (479-7004) | EACH | 16 | $400.00 | $498.75 | $750.00 | $900.00 | $1,687.50 | $612.00 | $2,500.00 |
| 23 | Adjusting manholes (water valve box) (479-7007) | EACH | 18 | $2,000.00 | $443.33 | $528.97 | $800.00 | $1,912.50 | $981.00 | $2,500.00 |
| 24 | Mobilization (500-7001) | LS | 1 | $288,000 | $219,982 | $176,000 | $225,000 | $374,063 | $210,000 | $340,000 |
| 25 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $8,500.00 | $2,750.00 | $8,568.60 | $2,170.00 | $9,562.50 | $8,000.00 | $8,500.00 |
| 26 | Portable changeable message sign (503-7002) | EACH | 2 | $12,000 | $1.10 | $8,500.00 | $8,000.00 | $18,000 | $1,200.00 | $16,500 |
| 27 | TMA (stationary) (505-7001) | DAY | 176 | $500.00 | $1.10 | $165.00 | $65.00 | $393.75 | $350.00 | $250.00 |
| 28 | TMA (mobile operation) (505-7002) | HR | 16 | $500.00 | $1.10 | $0.01 | $80.00 | $281.25 | $500.00 | $55.00 |
| 29 | Construction perimeter fence (506-7034) | LF | 4,000 | $4.00 | $0.11 | $0.01 | $2.00 | $5.34 | $19.00 | $30.00 |
| 30 | Temporary sediment control fence (install) (506-7039) | LF | 4,454 | $5.00 | $0.11 | $0.01 | $5.00 | $4.39 | $5.00 | $4.00 |
| 31 | Temporary sediment control fence (remove) (506-7041) | LF | 4,454 | $2.50 | $0.11 | $0.01 | $2.00 | $1.01 | $1.00 | $2.00 |
| 32 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 757 | $8.00 | $0.11 | $0.01 | $8.00 | $5.63 | $12.00 | $18.00 |
| 33 | Biodegradable erosion control logs (remove) (506-7046) | LF | 757 | $2.50 | $0.11 | $0.01 | $2.00 | $2.25 | $1.00 | $9.00 |
| 34 | Permanent CTB (F-shape) (type 1) (514-7013) | LF | 280 | $85.00 | $220.00 | $151.60 | $140.00 | $253.13 | $152.00 | $300.00 |
| 35 | Concrete curb (type II) (529-7002) | LF | 1,010 | $25.00 | $54.66 | $45.00 | $30.00 | $15.00 | $45.00 | $65.00 |
| 36 | Concrete curb & gutter (type II) (529-7009) | LF | 2,786 | $50.00 | $54.66 | $62.52 | $45.00 | $39.06 | $41.00 | $65.00 |
| 37 | Driveways (concrete) (hes) (530-7007) | SY | 3,448 | $125.00 | $110.77 | $107.08 | $110.00 | $100.81 | $121.00 | $125.00 |
| 38 | Concrete sidewalks (4") (531-7001) | SY | 7,058 | $80.00 | $98.35 | $72.00 | $75.00 | $89.46 | $99.00 | $60.00 |
| 39 | Curb ramps (type 1) (531-7005) | EACH | 23 | $2,750.00 | $2,143.77 | $1,783.00 | $2,500.00 | $2,368.16 | $1,500.00 | $3,850.00 |
| 40 | Curb ramps (type 2) (531-7006) | EACH | 3 | $2,750.00 | $2,143.77 | $1,783.00 | $2,500.00 | $2,889.24 | $1,500.00 | $3,850.00 |
| 41 | Curb ramps (type 3) (531-7007) | EACH | 6 | $2,800.00 | $2,143.77 | $1,783.00 | $2,200.00 | $2,965.03 | $1,500.00 | $3,850.00 |
| 42 | Curb ramps (type 7) (531-7010) | EACH | 4 | $2,800.00 | $2,143.77 | $1,607.83 | $2,000.00 | $2,585.08 | $1,500.00 | $3,850.00 |
| 43 | Curb ramps (type 10) (531-7011) | EACH | 3 | $2,800.00 | $2,143.77 | $1,885.00 | $2,600.00 | $3,049.11 | $1,500.00 | $3,850.00 |
| 44 | Curb ramps (type 21) (531-7013) | EACH | 9 | $2,750.00 | $2,143.77 | $1,983.14 | $3,600.00 | $3,003.20 | $1,500.00 | $3,850.00 |
| 45 | Curb ramps (type 22) (531-7014) | EACH | 1 | $4,000.00 | $1,999.19 | $2,183.14 | $3,100.00 | $3,547.28 | $1,500.00 | $3,850.00 |
| 46 | Remove metal beam guard fence (542-7001) | LF | 350 | $2.00 | $16.50 | $2.50 | $3.25 | $8.16 | $7.00 | $3.00 |
| 47 | Guardrail end treatment (remove) (544-7003) | EACH | 2 | $300.00 | $165.00 | $750.00 | $450.00 | $337.50 | $400.00 | $500.00 |
| 48 | Chain link fence (remove) (550-7007) | LF | 28 | $24.00 | $16.50 | $20.00 | $15.00 | $39.38 | $25.00 | $20.00 |
| 49 | Gate (remove) (550-7016) | EACH | 1 | $788.00 | $165.00 | $250.00 | $500.00 | $337.50 | $522.00 | $1,500.00 |
| 50 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 135 | $15.00 | $27.50 | $24.00 | $30.15 | $33.75 | $35.00 | $50.00 |
| 51 | Conduit (PVC) (schedule 40) (3") (bore) (618-7037) | LF | 494 | $50.00 | $60.50 | $60.00 | $67.00 | $41.96 | $42.00 | $100.00 |
| 52 | Electrical conductor (no.8) bare (620-7007) | LF | 622 | $2.50 | $1.76 | $2.40 | $2.00 | $3.71 | $4.30 | $3.00 |
| 53 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 19 | $900.00 | $495.00 | $792.00 | $700.00 | $810.00 | $1,200.00 | $1,500.00 |
| 54 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 2 | $900.00 | $605.00 | $907.50 | $700.00 | $928.13 | $1,400.00 | $1,500.00 |
| 55 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 1 | $900.00 | $825.00 | $1,182.50 | $700.00 | $1,209.38 | $1,428.00 | $1,500.00 |
| 56 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 1,936 | $15.00 | $9.08 | $9.90 | $9.95 | $9.28 | $9.23 | $20.00 |
| 57 | Pavement sler 24" (666-7352) | LF | 1,936 | $3.50 | $1.10 | $1.20 | $1.21 | $1.13 | $2.00 | $5.00 |
| 58 | Eliminating existing PM & markers (24") (677-7008) | LF | 1,689 | $5.50 | $3.29 | $3.59 | $3.62 | $3.36 | $5.00 | $5.00 |
| 59 | Pavement surface preparation for marking (24") (678-7008) | LF | 1,936 | $2.50 | $1.02 | $1.12 | $1.21 | $1.05 | $2.00 | $5.00 |
| 60 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 9 | $1,250.00 | $880.00 | $1,200.00 | $964.88 | $963.79 | $1,000.00 | $6,500.00 |
| 61 | Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007) | LF | 211 | $4.00 | $1.93 | $2.40 | $2.11 | $3.94 | $4.00 | $3.00 |
| 62 | Traffic signal CBL (type A)(16 AWG)(3 conductor) (684-7049) | LF | 192 | $4.00 | $1.54 | $2.40 | $1.69 | $4.05 | $5.00 | $3.00 |
| 63 | Pedestrian pole assembly (687-7001) | EACH | 5 | $3,500.00 | $3,960.00 | $4,560.00 | $4,341.98 | $4,755.04 | $5,000.00 | $5,000.00 |
| 64 | Relocate pedestrian pole assembly (687-7003) | EACH | 1 | $3,000.00 | $5,720.00 | $3,000.00 | $6,271.75 | $3,948.75 | $4,000.00 | $5,000.00 |
| 65 | Remove pedestrian pole assembly (687-7005) | EACH | 1 | $3,000.00 | $368.50 | $1,200.00 | $404.04 | $1,957.50 | $1,800.00 | $2,500.00 |
| 66 | Pedestrian detect push button (APS) (688-7001) | EACH | 12 | $1,000.00 | $990.00 | $1,440.00 | $1,085.49 | $1,882.58 | $1,900.00 | $1,850.00 |
| 67 | Pedestrian detector controller unit (688-7003) | EACH | 1 | $4,000.00 | $7,639.50 | $5,400.00 | $8,376.40 | $6,499.58 | $7,825.00 | $6,500.00 |
| 68 | Removal of signal head assembly (690-7024) | EACH | 3 | $100.00 | $77.00 | $480.00 | $84.43 | $326.25 | $399.00 | $500.00 |
| 69 | Install of signal head assembly (690-7026) | EACH | 7 | $200.00 | $368.50 | $1,200.00 | $404.05 | $1,935.00 | $1,900.00 | $500.00 |
| 70 | Removal of pedestrian push buttons (690-7030) | EACH | 11 | $200.00 | $27.50 | $120.00 | $30.15 | $108.79 | $125.00 | $250.00 |
| 71 | Ground box (prepare) (6013-7006) | EACH | 9 | $2,000.00 | $220.00 | $300.00 | $241.22 | $401.29 | $778.00 | $500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 1, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.