TxDOT contract A00194279 bid tabulation

Construct Ramps, SL 396 (US 84 to Bagby Avenue). Let by Texas DOT on May 1, 2025, McLennan, Waco District. 6 bids received; low bid $2,695,684 by Ti-Zack Concrete, LLC, -8.8% against the engineer's estimate of $2,956,391.

Owner
Texas DOT
Letting
01 MAY 2025
Pay items
71
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Ti-Zack Concrete, LLC$2,695,684Low-9.0%
23LW Civil LLC$2,716,165+1.0%-8.0%
3STX Civil$2,793,095+4.0%-6.0%
4Talbert Companies LLC$2,837,524+5.0%-4.0%
5Cross Plus Construction, LLC$2,862,895+6.0%-3.0%
6Grey Sky Construction LLC$3,534,472+31%+20%
TxDOT contract A00194279: bids by rank

Engineer's estimate: $2,956,391.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Ti-Zack Concrete, LLC2. 3LW Civil LLC3. STX Civil4. Talbert Companies LLC5. Cross Plus Construction, LLC6. Grey Sky Construction LLC
1Preparation row (tree prune and trim) (100-7010)STA5$1,000.00$137.50$1,000.00$2,200.00$2,430.00$2,500.00$30,000
2Removing concrete (driveways) (104-7011)SY3,690$20.00$27.80$30.00$13.00$19.73$22.50$20.00
3Removing concrete (sidewalk, ramp or shared use path) (104-7013)SY521$25.00$30.63$25.00$30.00$20.39$45.00$20.00
4Removing concrete (curb or curb & gutter) (104-7018)LF2,093$12.00$11.44$22.50$16.00$18.42$10.00$20.00
5Removing concrete (miscellaneous) (104-7046)SY222$41.00$35.95$25.00$30.00$25.30$12.00$50.00
6Remove (4"-8") TRT/untrt base & asphalt pavement (105-7004)SY1,720$10.00$23.20$25.00$7.00$6.64$24.00$20.00
7Excavation (special) (110-7003)CY320$30.00$74.81$65.00$110.00$27.90$25.00$50.00
8Embankment (final)(OC)(type B) (132-7003)CY2,370$45.00$51.17$55.00$45.00$39.22$42.00$40.00
9Block sodding (162-7002)SY12,748$6.50$5.50$8.50$7.00$6.47$8.00$8.00
10Vegetative watering (168-7001)TGL115$200.00$110.00$87.39$50.00$168.75$152.00$50.00
11Rdside amenity (wheel stop) (194-7007)EACH15$300.00$165.00$150.00$260.00$393.75$250.00$500.00
12Rdside amenity (wheel stop removing&reset) (194-7008)EACH25$250.00$110.00$125.00$245.00$393.75$150.00$500.00
13D-GR HMA type D PG 76-22 (exempt) (341-7065)TON50$180.00$330.00$450.00$400.00$509.96$250.00$500.00
14Plane & text asphalt concrete pavement(0" to 2") (354-7002)SY100$5.00$22.00$4.39$5.00$56.25$25.00$50.00
15Cut & restoring pavement (400-7006)SY1,939$165.00$115.50$148.50$250.00$39.38$89.00$150.00
16Riprap (concrete)(4 in) (432-7001)CY57$500.00$824.66$660.25$800.00$602.01$750.00$550.00
17Rail (handrail)(type E) (450-7062)LF251$250.00$187.00$190.33$130.00$225.00$256.00$185.00
18Inlet (complete)(armor curb slot) (465-7335)EACH2$4,430.00$5,500.00$5,186.65$9,500.00$2,253.96$4,212.00$15,000
19Inlet (comp)(type sidewalk bridge) (465-7336)EACH4$6,000.00$13,750$14,218$15,000$9,311.90$9,124.00$20,000
20Adjusting manholes (479-7001)EACH10$2,000.00$798.00$1,450.00$1,500.00$3,937.50$529.00$2,000.00
21Adjusting inlets (479-7002)EACH1$1,300.00$798.00$3,030.00$2,000.00$3,943.13$1,250.00$5,000.00
22Adjusting manholes (utility box) (479-7004)EACH16$400.00$498.75$750.00$900.00$1,687.50$612.00$2,500.00
23Adjusting manholes (water valve box) (479-7007)EACH18$2,000.00$443.33$528.97$800.00$1,912.50$981.00$2,500.00
24Mobilization (500-7001)LS1$288,000$219,982$176,000$225,000$374,063$210,000$340,000
25Barricades, signs and traffic handling (502-7001)MO12$8,500.00$2,750.00$8,568.60$2,170.00$9,562.50$8,000.00$8,500.00
26Portable changeable message sign (503-7002)EACH2$12,000$1.10$8,500.00$8,000.00$18,000$1,200.00$16,500
27TMA (stationary) (505-7001)DAY176$500.00$1.10$165.00$65.00$393.75$350.00$250.00
28TMA (mobile operation) (505-7002)HR16$500.00$1.10$0.01$80.00$281.25$500.00$55.00
29Construction perimeter fence (506-7034)LF4,000$4.00$0.11$0.01$2.00$5.34$19.00$30.00
30Temporary sediment control fence (install) (506-7039)LF4,454$5.00$0.11$0.01$5.00$4.39$5.00$4.00
31Temporary sediment control fence (remove) (506-7041)LF4,454$2.50$0.11$0.01$2.00$1.01$1.00$2.00
32Biodegradable erosion control logs (install) (8") (506-7043)LF757$8.00$0.11$0.01$8.00$5.63$12.00$18.00
33Biodegradable erosion control logs (remove) (506-7046)LF757$2.50$0.11$0.01$2.00$2.25$1.00$9.00
34Permanent CTB (F-shape) (type 1) (514-7013)LF280$85.00$220.00$151.60$140.00$253.13$152.00$300.00
35Concrete curb (type II) (529-7002)LF1,010$25.00$54.66$45.00$30.00$15.00$45.00$65.00
36Concrete curb & gutter (type II) (529-7009)LF2,786$50.00$54.66$62.52$45.00$39.06$41.00$65.00
37Driveways (concrete) (hes) (530-7007)SY3,448$125.00$110.77$107.08$110.00$100.81$121.00$125.00
38Concrete sidewalks (4") (531-7001)SY7,058$80.00$98.35$72.00$75.00$89.46$99.00$60.00
39Curb ramps (type 1) (531-7005)EACH23$2,750.00$2,143.77$1,783.00$2,500.00$2,368.16$1,500.00$3,850.00
40Curb ramps (type 2) (531-7006)EACH3$2,750.00$2,143.77$1,783.00$2,500.00$2,889.24$1,500.00$3,850.00
41Curb ramps (type 3) (531-7007)EACH6$2,800.00$2,143.77$1,783.00$2,200.00$2,965.03$1,500.00$3,850.00
42Curb ramps (type 7) (531-7010)EACH4$2,800.00$2,143.77$1,607.83$2,000.00$2,585.08$1,500.00$3,850.00
43Curb ramps (type 10) (531-7011)EACH3$2,800.00$2,143.77$1,885.00$2,600.00$3,049.11$1,500.00$3,850.00
44Curb ramps (type 21) (531-7013)EACH9$2,750.00$2,143.77$1,983.14$3,600.00$3,003.20$1,500.00$3,850.00
45Curb ramps (type 22) (531-7014)EACH1$4,000.00$1,999.19$2,183.14$3,100.00$3,547.28$1,500.00$3,850.00
46Remove metal beam guard fence (542-7001)LF350$2.00$16.50$2.50$3.25$8.16$7.00$3.00
47Guardrail end treatment (remove) (544-7003)EACH2$300.00$165.00$750.00$450.00$337.50$400.00$500.00
48Chain link fence (remove) (550-7007)LF28$24.00$16.50$20.00$15.00$39.38$25.00$20.00
49Gate (remove) (550-7016)EACH1$788.00$165.00$250.00$500.00$337.50$522.00$1,500.00
50Conduit (PVC) (schedule 40) (3") (618-7036)LF135$15.00$27.50$24.00$30.15$33.75$35.00$50.00
51Conduit (PVC) (schedule 40) (3") (bore) (618-7037)LF494$50.00$60.50$60.00$67.00$41.96$42.00$100.00
52Electrical conductor (no.8) bare (620-7007)LF622$2.50$1.76$2.40$2.00$3.71$4.30$3.00
53Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH19$900.00$495.00$792.00$700.00$810.00$1,200.00$1,500.00
54Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH2$900.00$605.00$907.50$700.00$928.13$1,400.00$1,500.00
55Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007)EACH1$900.00$825.00$1,182.50$700.00$1,209.38$1,428.00$1,500.00
56Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF1,936$15.00$9.08$9.90$9.95$9.28$9.23$20.00
57Pavement sler 24" (666-7352)LF1,936$3.50$1.10$1.20$1.21$1.13$2.00$5.00
58Eliminating existing PM & markers (24") (677-7008)LF1,689$5.50$3.29$3.59$3.62$3.36$5.00$5.00
59Pavement surface preparation for marking (24") (678-7008)LF1,936$2.50$1.02$1.12$1.21$1.05$2.00$5.00
60Pedestrian signal section (LED)(countdown) (682-7018)EACH9$1,250.00$880.00$1,200.00$964.88$963.79$1,000.00$6,500.00
61Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007)LF211$4.00$1.93$2.40$2.11$3.94$4.00$3.00
62Traffic signal CBL (type A)(16 AWG)(3 conductor) (684-7049)LF192$4.00$1.54$2.40$1.69$4.05$5.00$3.00
63Pedestrian pole assembly (687-7001)EACH5$3,500.00$3,960.00$4,560.00$4,341.98$4,755.04$5,000.00$5,000.00
64Relocate pedestrian pole assembly (687-7003)EACH1$3,000.00$5,720.00$3,000.00$6,271.75$3,948.75$4,000.00$5,000.00
65Remove pedestrian pole assembly (687-7005)EACH1$3,000.00$368.50$1,200.00$404.04$1,957.50$1,800.00$2,500.00
66Pedestrian detect push button (APS) (688-7001)EACH12$1,000.00$990.00$1,440.00$1,085.49$1,882.58$1,900.00$1,850.00
67Pedestrian detector controller unit (688-7003)EACH1$4,000.00$7,639.50$5,400.00$8,376.40$6,499.58$7,825.00$6,500.00
68Removal of signal head assembly (690-7024)EACH3$100.00$77.00$480.00$84.43$326.25$399.00$500.00
69Install of signal head assembly (690-7026)EACH7$200.00$368.50$1,200.00$404.05$1,935.00$1,900.00$500.00
70Removal of pedestrian push buttons (690-7030)EACH11$200.00$27.50$120.00$30.15$108.79$125.00$250.00
71Ground box (prepare) (6013-7006)EACH9$2,000.00$220.00$300.00$241.22$401.29$778.00$500.00
TxDOT contract A00194279: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of May 1, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy