TxDOT contract A00194280 bid tabulation

Construct Pedestrian Infrastructure, FM 3470 (SH 201 to IH 14). Let by Texas DOT on August 6, 2026, Bell, Waco District. 8 bids received; low bid $4,094,515 by Rucoba & Maya Construction, LLC, -8.3% against the engineer's estimate of $4,466,140.

Owner
Texas DOT
Letting
06 AUG 2026
Pay items
91
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Rucoba & Maya Construction, LLC$4,094,515Low-8.0%
2Yoko Excavating, LLC$4,347,032+6.0%-3.0%
3Texas Steel Industrial Placing, LLC$4,372,041+7.0%-2.0%
4Ti-Zack Concrete, LLC$4,887,385+19%+9.0%
5Joe Bland Construction LLC$4,935,019+21%+10%
6STX Civil$5,007,508+22%+12%
7Garret Shields Infrastructure$5,347,359+31%+20%
8Cross Plus Construction, LLC$5,835,648+43%+31%
TxDOT contract A00194280: bids by rank

Engineer's estimate: $4,466,140.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Rucoba & Maya Construction, LLC2. Yoko Excavating, LLC3. Texas Steel Industrial Placing, LLC4. Ti-Zack Concrete, LLC5. Joe Bland Construction LLC6. STX Civil
1Preparing row (100-7002)STA359$950.00$230.00$483.13$400.00$660.00$1,125.00$300.00
2Removing concrete (driveways) (104-7011)SY266$20.00$28.00$19.06$60.00$53.14$30.00$25.00
3Removing concrete (sidewalk, ramp or shared use path) (104-7013)SY86$215.00$28.00$18.95$100.00$41.09$50.00$25.00
4Remove (3") TRT/untrt base & asphalt pavement (105-7023)SY3,097$5.00$18.00$3.40$20.00$27.39$10.00$8.00
5Excavation (roadway) (110-7001)CY333$11.00$62.00$16.22$30.00$42.45$120.00$45.00
6Embankment (final)(OC)(type B) (132-7003)CY1,123$18.00$77.00$23.75$30.00$31.47$30.00$40.00
7Hydro mulch seed (permanent_urban_clay) (164-7020)SY59,846$0.13$0.55$0.87$0.43$1.10$2.00$0.55
8Vegetative watering (168-7001)TGL324$22.00$58.00$33.61$30.00$1.10$20.00$50.00
9Drilled shaft (traffic signal pole) (24 in) (416-7042)LF354$285.00$497.70$258.75$225.00$247.50$265.00$315.00
10Riprap (concrete)(5 in) (432-7002)CY45$610.00$550.00$532.39$550.00$621.51$775.00$650.00
11Rail (handrail)(type D) (450-7061)LF1,597$180.00$200.00$218.38$201.41$214.50$250.00$205.00
12RC pipe (CL IV)(15 in) (464-7018)LF52$170.00$100.00$337.08$90.00$104.50$250.00$100.00
13RC pipe (CL IV)(18 in) (464-7019)LF264$95.00$120.00$144.91$110.00$115.50$275.00$100.00
14RC pipe (CL IV)(24 in) (464-7021)LF152$134.00$160.00$216.55$120.00$159.50$300.00$140.00
15Set (type II) (15 in) (RCP) (3: 1) (C) (467-7297)EACH2$1,900.00$950.00$1,490.00$1,000.00$1,650.00$2,500.00$2,000.00
16Set (type II) (15 in) (RCP) (4: 1) (C) (467-7298)EACH2$2,013.00$1,200.00$1,490.00$1,000.00$1,980.00$2,500.00$2,100.00
17Set (type II) (15 in) (RCP) (6: 1) (P) (467-7300)EACH4$2,000.00$1,600.00$1,400.00$1,000.00$2,420.00$2,500.00$2,300.00
18Set (type II) (18 in) (RCP) (3: 1) (C) (467-7305)EACH2$900.00$1,100.00$1,550.00$2,000.00$2,530.00$2,800.00$2,400.00
19Set (type II) (18 in) (RCP) (6: 1) (C) (467-7307)EACH8$1,600.00$2,500.00$1,555.00$2,000.00$2,604.80$2,800.00$2,800.00
20Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH5$1,100.00$1,800.00$1,840.00$2,000.00$2,750.00$3,500.00$2,800.00
21Set (type II) (24 in) (CMP) (3: 1) (C) (467-7321)EACH2$2,140.00$2,100.00$2,280.00$2,000.00$1,650.00$3,000.00$3,000.00
22Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325)EACH2$1,400.00$1,300.00$2,280.00$2,000.00$1,705.00$3,000.00$3,100.00
23Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327)EACH1$1,750.00$2,600.00$3,695.00$2,000.00$1,980.00$5,000.00$3,800.00
24Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH4$1,500.00$2,300.00$2,070.00$2,000.00$2,530.00$4,000.00$3,800.00
25Adjusting manholes (479-7001)EACH1$1,200.00$1,200.00$1,500.00$1,300.00$706.80$2,500.00$4,500.00
26Adjusting manholes (utility box) (479-7004)EACH5$510.00$500.00$800.00$1,000.00$424.08$2,500.00$750.00
27Adjusting manholes (water valve box) (479-7007)EACH28$680.00$150.00$500.00$700.00$252.43$1,000.00$750.00
28Removing structure (set) (496-7004)EACH24$380.00$400.00$200.00$500.00$275.00$750.00$450.00
29Removing structure (pipe) (496-7007)LF340$16.00$30.00$15.00$20.00$13.20$75.00$14.00
30Mobilization (500-7001)LS1$431,339$340,000$206,425$437,165$222,245$225,000$350,000
31Barricades, signs and traffic handling (502-7001)MO15$6,550.00$4,500.00$3,256.24$2,500.00$8,250.00$1,750.00$4,500.00
32Portable changeable message sign (503-7002)EACH2$10,000$18,900$14,000$30,000$1,320.00$21,750$10,000
33TMA (stationary) (505-7001)DAY223$160.00$240.45$278.00$175.00$127.60$275.00$160.00
34TMA (mobile operation) (505-7003)DAY7$160.00$350.00$498.52$200.00$275.00$415.00$250.00
35Temporary sediment control fence (install) (506-7039)LF5,860$4.15$3.90$4.71$4.00$0.11$5.00$4.00
36Temporary sediment control fence (remove) (506-7041)LF5,860$0.99$1.70$1.35$1.00$0.11$2.00$2.00
37Driveways (concrete) (hes) (530-7007)SY2,814$120.00$78.63$102.11$110.00$121.40$150.00$110.00
38Concrete sidewalks (5") (531-7002)SY19,714$61.00$59.27$81.00$75.00$101.11$65.00$80.00
39Curb ramps (type 1) (531-7005)EACH24$2,850.00$1,600.00$1,597.88$2,500.00$1,883.38$2,150.00$1,150.00
40Curb ramps (type 2) (531-7006)EACH5$2,590.00$1,600.00$1,535.99$2,500.00$1,883.38$2,150.00$2,000.00
41Curb ramps (type 3) (531-7007)EACH1$2,145.00$2,000.00$2,007.30$2,500.00$1,883.38$3,000.00$2,800.00
42Curb ramps (type 5) (531-7008)EACH4$4,500.00$3,200.00$2,577.85$2,800.00$1,883.38$3,750.00$2,800.00
43Curb ramps (type 7) (531-7010)EACH44$2,800.00$1,800.00$2,003.12$3,000.00$1,883.38$3,500.00$1,850.00
44Curb ramps (type 22) (531-7014)EACH4$5,500.00$4,200.00$3,050.09$5,000.00$1,883.38$5,300.00$2,800.00
45Conduit (PVC) (schedule 40) (3") (618-7036)LF1,129$20.00$22.47$18.40$16.00$17.60$20.00$30.00
46Conduit (PVC) (schedule 80) (3") (bore) (618-7061)LF2,824$38.00$33.49$39.00$30.00$33.00$40.00$30.00
47Conduit (prepare) (618-7090)LF1,285$5.00$2.52$3.45$3.00$3.30$5.00$8.50
48Electrical conductor (no.8) bare (620-7007)LF5,597$1.85$1.99$1.61$1.40$1.54$2.00$2.00
49Electrical conductor (no.8) insulated (620-7008)LF2,760$2.00$2.52$1.78$1.55$1.71$2.00$1.50
50Ground box type D (162922) (624-7007)EACH24$1,200.00$1,155.00$1,265.00$1,100.00$1,210.00$1,295.00$1,650.00
51Ground box type D (162922)W/apron (624-7008)EACH30$1,600.00$2,008.65$1,380.00$1,200.00$1,320.00$1,400.00$1,850.00
52Aluminum signs (type A) (636-7001)SF299$80.00$84.00$29.33$25.00$28.05$30.00$55.00
53Relocate SM RD SN sup&AM type TWT (644-7068)EACH26$900.00$440.00$375.00$375.00$753.50$475.00$500.00
54Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF4,144$10.00$7.35$6.56$6.40$7.04$8.00$7.25
55Reflectorized pavement marking type I (Y)24"(solid)(100MIL) (666-7123)LF44$11.00$7.35$8.20$8.00$8.80$8.00$7.25
56Pavement sler 6" (666-7347)LF73$2.00$0.52$0.51$0.50$0.55$1.00$0.80
57Pavement sler 24" (666-7352)LF4,188$5.00$3.15$0.56$0.55$0.61$3.50$3.25
58Pavement sler (arrow) (666-7353)EACH15$40.00$52.50$18.45$18.00$19.80$60.00$60.00
59Pavement sler (double arrow) (666-7356)EACH1$45.00$78.75$18.45$18.00$19.80$88.00$95.00
60Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF73$1.00$1.05$1.03$1.00$1.10$1.25$1.25
61Prefabricated PM type C (W)(arrow) (668-7091)EACH15$250.00$288.75$202.95$198.00$217.80$325.00$280.00
62Prefabricated PM type C (W)(double arrow) (668-7093)EACH1$275.00$393.75$369.00$360.00$396.00$440.00$400.00
63Eliminating existing PM & markers (6") (677-7002)LF505$2.00$1.05$2.05$2.00$2.20$1.25$1.25
64Eliminating existing PM & markers (8") (677-7004)LF237$2.50$2.10$3.08$3.00$3.30$2.50$2.10
65Eliminating existing PM & markers (12") (677-7006)LF221$3.00$3.15$3.08$3.00$3.30$3.50$3.10
66Eliminating existing PM & markers (24") (677-7008)LF2,290$6.00$6.30$3.08$3.00$3.30$7.00$6.10
67Eliminating existing PM & markers (arrow) (677-7009)EACH18$50.00$157.50$61.50$60.00$66.00$175.00$160.00
68Eliminating existing PM & markers (double arrow) (677-7010)EACH2$55.00$210.00$71.75$70.00$77.00$235.00$220.00
69Pavement surface preparation for marking (6") (678-7002)LF73$1.00$0.26$0.21$0.20$0.22$0.50$0.45
70Pavement surface preparation for marking (24") (678-7008)LF4,188$3.00$1.05$0.51$0.50$0.55$1.25$1.10
71Pavement surface preparation for marking (arrow) (678-7009)EACH15$20.00$52.50$20.50$20.00$22.00$60.00$60.00
72Pavement surface preparation for marking (double arrow) (678-7010)EACH1$25.00$52.50$20.50$20.00$22.00$60.00$60.00
73Install highway traffic signal (system) (680-7003)EACH4$35,000$34,267$45,885$39,900$43,890$47,500$70,500
74Removing traffic signals (680-7004)EACH4$5,000.00$3,575.25$6,555.00$5,700.00$6,270.00$6,750.00$13,500
75Install highway traffic signal (upgrade) (680-7011)EACH5$7,000.00$3,491.36$8,000.00$6,400.00$7,040.00$7,500.00$37,000
76Vehicle signal section (12")LED(green arrow) (682-7002)EACH22$340.00$367.50$356.50$310.00$341.00$365.00$500.00
77Vehicle signal section (12")LED(yel arrow) (682-7004)EACH44$340.00$367.50$356.50$310.00$341.00$365.00$400.00
78Vehicle signal section (12")LED(red arrow) (682-7006)EACH22$340.00$367.50$356.50$310.00$341.00$365.00$400.00
79Pedestrian signal section (LED)(countdown) (682-7018)EACH68$750.00$819.00$759.00$660.00$726.00$775.00$1,000.00
80Backplate W/reflectorized border(3 sec)aluminum (682-7039)EACH65$250.00$514.50$178.25$155.00$170.50$185.00$250.00
81Backplate W/reflectorized border(4 sec)aluminum (682-7040)EACH23$275.00$493.50$253.00$220.00$242.00$255.00$330.00
82Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007)LF11,261$2.00$2.10$2.13$1.85$2.04$2.50$2.75
83Traffic signal CBL (type A)(12 AWG)(5 conductor) (684-7010)LF14,430$3.00$3.47$3.05$2.65$2.92$3.50$5.25
84Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012)LF2,597$3.75$5.25$3.68$3.20$3.52$4.00$5.00
85Pedestrian pole assembly (687-7001)EACH61$3,000.00$2,075.85$1,495.00$1,300.00$1,430.00$1,650.00$5,000.00
86Pedestrian detect push button (APS) (688-7001)EACH68$1,000.00$1,176.00$1,138.50$990.00$1,089.00$1,250.00$1,000.00
87Pedestrian detector controller unit (688-7003)EACH9$3,000.00$4,935.00$5,060.00$4,400.00$4,840.00$5,500.00$4,500.00
88Install of cables (690-7011)LF291$5.00$2.36$5.06$4.40$4.84$5.00$6.00
89VIVDS cable (install) (690-7137)LF2,667$5.00$3.94$3.91$3.40$3.74$4.25$4.00
90Bbu system (external battery cabinet) (6007-7001)EACH4$9,500.00$10,574$12,625$10,100$11,110$12,750$2,800.00
91Ground box (prepare) (6013-7006)EACH13$500.00$238.35$281.75$245.00$269.50$315.00$750.00
TxDOT contract A00194280: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of August 6, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy