Reconstruct Existing Roadway, US 81 (Near Fruitland Road to Wise County Line). Let by Texas DOT on October 9, 2025, Montague, Wichita Falls District. 7 bids received; low bid $20,093,159 by Ed Bell Construction Company, -7.4% against the engineer's estimate of $21,707,026.
- Owner
- Texas DOT
- Letting
- 09 OCT 2025
- Pay items
- 57
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ed Bell Construction Company | $20,093,159 | Low | -7.0% |
| 2 | Indus Road & Bridge, Inc. | $20,559,782 | +2.0% | -5.0% |
| 3 | Mario Sinacola & Sons Excavating, Inc. | $20,723,141 | +3.0% | -5.0% |
| 4 | Webber, LLC | $20,899,111 | +4.0% | -4.0% |
| 5 | Grey Sky Construction LLC | $21,675,093 | +8.0% | 0.0% |
| 6 | Ragle Construction, Inc. | $23,994,098 | +19% | +11% |
| 7 | A. L. Helmcamp, Inc. | $28,485,271 | +42% | +31% |
Engineer's estimate: $21,707,026.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Ed Bell Construction Company | 2. Indus Road & Bridge, Inc. | 3. Mario Sinacola & Sons Excavating, Inc. | 4. Webber, LLC | 5. Grey Sky Construction LLC | 6. Ragle Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (pavement) (104-7001) | SY | 71,090 | $10.00 | $12.50 | $11.00 | $15.00 | $13.00 | $10.00 | $13.40 |
| 2 | Removing concrete (mowstrip) (104-7005) | LF | 350 | $17.00 | $21.00 | $15.00 | $15.00 | $13.40 | $50.00 | $11.00 |
| 3 | Remove (4") TRT/untrt base & asphalt pavement (105-7024) | SY | 71,090 | $3.50 | $3.15 | $2.80 | $2.00 | $3.00 | $10.00 | $4.43 |
| 4 | Remove (0"-12") TRT/untrt base & asphalt pavement (105-7052) | SY | 52,970 | $8.00 | $5.25 | $7.00 | $10.00 | $7.90 | $10.00 | $10.00 |
| 5 | Excavation (roadway) (110-7001) | CY | 4,788 | $15.00 | $12.50 | $21.00 | $33.00 | $23.30 | $20.00 | $110.00 |
| 6 | Embankment (final)(OC)(type A) (132-7001) | CY | 7,367 | $30.00 | $25.00 | $19.00 | $30.00 | $25.00 | $30.00 | $35.00 |
| 7 | Backfill (type A) (134-7001) | STA | 266 | $245.00 | $800.00 | $335.00 | $500.00 | $156.40 | $350.00 | $118.00 |
| 8 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 14,794 | $1.00 | $0.75 | $0.30 | $0.12 | $0.30 | $1.00 | $0.29 |
| 9 | Vegetative watering (168-7001) | TGL | 2.30 | $165.00 | $600.00 | $30.00 | $500.00 | $90.70 | $100.00 | $1,000.00 |
| 10 | Cement (275-7001) | TON | 1,371 | $280.00 | $225.00 | $235.00 | $210.00 | $231.90 | $300.00 | $335.00 |
| 11 | Cement TRT (existing material)(8") (275-7003) | SY | 136,874 | $2.50 | $1.50 | $3.10 | $3.65 | $4.30 | $4.00 | $3.90 |
| 12 | Cem TRT(PLNT MX)(CL L)(tya)(GR1-2)(6") (276-7117) | SY | 132,933 | $13.50 | $18.00 | $18.92 | $16.00 | $9.00 | $12.00 | $15.50 |
| 13 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 33,198 | $7.00 | $4.00 | $4.20 | $3.90 | $4.00 | $5.00 | $3.70 |
| 14 | D-GR HMA type D PG64-22 (341-7043) | TON | 7,151 | $125.50 | $115.00 | $150.00 | $107.00 | $101.00 | $125.00 | $113.00 |
| 15 | Planing asphalt concrete pavement (0" to 1.5") (354-7073) | SY | 71,090 | $5.00 | $2.00 | $0.60 | $2.00 | $4.00 | $3.00 | $2.00 |
| 16 | Concrete pavement (CRCP) (12") (360-7006) | SY | 123,564 | $93.25 | $92.00 | $85.00 | $87.00 | $87.00 | $90.00 | $105.00 |
| 17 | Concrete pavement(transition slab) (12") (360-7035) | SY | 462 | $270.00 | $175.00 | $165.00 | $150.00 | $313.00 | $200.00 | $97.60 |
| 18 | Riprap (concrete)(4 in) (432-7001) | CY | 17 | $710.00 | $1,000.00 | $607.88 | $850.00 | $577.00 | $550.00 | $834.35 |
| 19 | Mobilization (500-7001) | LS | 1 | $1,976,174 | $1,800,000 | $2,000,000 | $2,070,000 | $2,089,911 | $2,000,000 | $2,400,000 |
| 20 | Barricades, signs and traffic handling (502-7001) | MO | 18 | $7,000.00 | $11,000 | $18,500 | $40,000 | $103,844 | $12,500 | $56,250 |
| 21 | Portable changeable message sign (503-7002) | EACH | 18 | $7,000.00 | $800.00 | $18,500 | $10,000 | $117.00 | $20,000 | $100.00 |
| 22 | TMA (stationary) (505-7001) | DAY | 110 | $350.00 | $200.00 | $200.00 | $200.00 | $245.00 | $250.00 | $244.00 |
| 23 | TMA (mobile operation) (505-7003) | DAY | 40 | $400.00 | $800.00 | $550.00 | $1,200.00 | $811.00 | $550.00 | $576.00 |
| 24 | Construction exits (install) (type 1) (506-7020) | SY | 1,060 | $30.00 | $30.00 | $45.00 | $33.00 | $40.80 | $30.00 | $40.00 |
| 25 | Construction exits (remove) (506-7024) | SY | 1,060 | $12.00 | $15.00 | $14.00 | $1.00 | $14.30 | $10.00 | $14.00 |
| 26 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 360 | $12.00 | $12.00 | $9.00 | $3.45 | $8.20 | $12.00 | $8.00 |
| 27 | Biodegradable erosion control logs (remove) (506-7046) | LF | 360 | $2.00 | $6.00 | $2.00 | $0.10 | $2.10 | $8.00 | $2.00 |
| 28 | Portable concrete traffic barrier (furnish and install)(F-shape)(type 1) (512-7005) | LF | 6,480 | $65.00 | $25.00 | $50.00 | $45.00 | $25.00 | $85.00 | $24.00 |
| 29 | Portable concrete traffic barrier (move)(F-shape)(type 1) (512-7029) | LF | 48,060 | $20.00 | $4.00 | $8.00 | $2.00 | $6.80 | $10.00 | $5.60 |
| 30 | Portable concrete traffic barrier (remove)(F-shape)(type 1) (512-7053) | LF | 6,480 | $20.00 | $12.50 | $6.00 | $5.00 | $10.60 | $20.00 | $13.50 |
| 31 | Mill rumble strips (concrete) (shoulder) (533-7003) | LF | 45,080 | $3.00 | $0.67 | $0.75 | $0.42 | $0.80 | $1.00 | $0.42 |
| 32 | Metal W-beam guard fence (steel post) (540-7002) | LF | 250 | $40.00 | $32.32 | $34.00 | $35.00 | $30.90 | $35.00 | $34.00 |
| 33 | Downstream anchor terminal section (540-7015) | EACH | 1 | $1,650.00 | $1,751.93 | $1,900.00 | $1,500.00 | $1,686.19 | $1,850.00 | $1,500.00 |
| 34 | Remove metal beam guard fence (542-7001) | LF | 250 | $6.00 | $2.93 | $3.50 | $3.00 | $2.80 | $3.00 | $5.00 |
| 35 | Remove downstream anchor terminal (542-7003) | EACH | 1 | $300.00 | $292.88 | $320.00 | $500.00 | $280.00 | $500.00 | $300.00 |
| 36 | Guardrail end treatment (install) (544-7001) | EACH | 1 | $3,250.00 | $3,694.49 | $3,900.00 | $4,000.00 | $3,532.00 | $3,850.00 | $3,500.00 |
| 37 | Guardrail end treatment (remove) (544-7003) | EACH | 1 | $330.00 | $292.88 | $340.00 | $500.00 | $280.00 | $1,500.00 | $300.00 |
| 38 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 9 | $2,400.00 | $2,500.00 | $2,600.00 | $1,197.97 | $1,298.00 | $6,500.00 | $1,600.00 |
| 39 | Crash cushion attenuator (remove) (545-7004) | EACH | 1 | $1,350.00 | $1,250.00 | $1,800.00 | $1,732.88 | $912.00 | $2,500.00 | $1,650.00 |
| 40 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 1 | $11,000 | $10,000 | $13,500 | $9,185.94 | $7,813.00 | $21,000 | $9,300.00 |
| 41 | In bridge MNT clearance sign assembly(type N) (644-7061) | EACH | 4 | $3,100.00 | $3,828.68 | $4,000.00 | $3,500.00 | $3,660.00 | $5,000.00 | $3,500.00 |
| 42 | Remove BRDG MNT clearance sign assembly (644-7074) | EACH | 4 | $1,300.00 | $569.78 | $600.00 | $3,500.00 | $545.00 | $2,500.00 | $500.00 |
| 43 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 18,236 | $1.50 | $0.91 | $1.20 | $0.85 | $1.00 | $1.00 | $0.85 |
| 44 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 26,700 | $1.50 | $0.91 | $1.20 | $0.85 | $1.00 | $1.00 | $0.85 |
| 45 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 3,010 | $2.00 | $1.28 | $1.60 | $1.20 | $2.20 | $1.00 | $1.20 |
| 46 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 730 | $5.00 | $3.20 | $4.00 | $3.00 | $5.10 | $6.00 | $3.00 |
| 47 | Reflectorized pavement marking type II (W) (entr gore) (666-7195) | EACH | 5 | $2,000.00 | $213.00 | $250.00 | $200.00 | $662.00 | $2,500.00 | $200.00 |
| 48 | Reflectorized pavement marking type II (W) (exit gore) (666-7196) | EACH | 5 | $2,000.00 | $372.75 | $440.00 | $350.00 | $662.00 | $2,500.00 | $350.00 |
| 49 | Type I high perf PM (W)6"(broken)(100MIL) (666-7290) | LF | 6,670 | $2.00 | $0.80 | $1.00 | $0.75 | $0.70 | $0.75 | $0.75 |
| 50 | Type I high perf PM (W)6"(solid)(100MIL) (666-7293) | LF | 18,250 | $1.50 | $0.56 | $0.70 | $0.53 | $0.70 | $0.75 | $0.53 |
| 51 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 26,660 | $1.50 | $0.56 | $0.70 | $0.53 | $0.70 | $0.75 | $0.53 |
| 52 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 651 | $7.50 | $5.06 | $6.00 | $4.75 | $5.10 | $6.00 | $4.75 |
| 53 | Traffic button type W (672-7007) | EACH | 1,440 | $6.00 | $1.97 | $2.40 | $1.85 | $5.10 | $6.00 | $1.85 |
| 54 | Traffic button type Y (672-7008) | EACH | 1,440 | $4.50 | $1.97 | $2.40 | $1.85 | $5.10 | $6.00 | $1.85 |
| 55 | Pavement surface preparation for marking (6") (678-7002) | LF | 79,980 | $0.40 | $0.16 | $0.20 | $0.15 | $0.05 | $0.75 | $0.15 |
| 56 | Pavement surface preparation for marking (entr gore) (678-7017) | EACH | 5 | $150.00 | $159.75 | $200.00 | $150.00 | $204.00 | $1,500.00 | $150.00 |
| 57 | Pavement surface preparation for marking (exit gore) (678-7018) | EACH | 5 | $150.00 | $186.38 | $220.00 | $175.00 | $204.00 | $1,500.00 | $175.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of October 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.