TxDOT contract A00196130 bid tabulation
Rehabilitate Existing Roadway, SL 12 (SS 408 to West Fork Trinity River). Let by Texas DOT on June 2, 2026, Dallas, Dallas District. 4 bids received; low bid $19,588,668 by Austin Bridge & Road Services, LP, +9.0% against the engineer's estimate of $17,965,405.
- Owner
- Texas DOT
- Letting
- 02 JUN 2026
- Pay items
- 94
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Austin Bridge & Road Services, LP | $19,588,668 | Low | +9.0% |
| 2 | Gibson & Associates, Inc. | $20,276,047 | +4.0% | +13% |
| 3 | Texas Materials Group, Inc. | $20,590,186 | +5.0% | +15% |
| 4 | Ragle Construction, Inc. | $20,731,701 | +6.0% | +15% |
Engineer's estimate: $17,965,405.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Austin Bridge & Road Services, LP | 2. Gibson & Associates, Inc. | 3. Texas Materials Group, Inc. | 4. Ragle Construction, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7006) | SY | 172 | $25.00 | $21.00 | $23.10 | $21.94 | $30.00 |
| 2 | Removing concrete (wingwall) (104-7028) | CY | 3 | $1,000.00 | $1,800.00 | $1,980.00 | $1,880.57 | $450.00 |
| 3 | Removing concrete (traffic barrier) (104-7035) | LF | 375 | $25.00 | $40.00 | $34.00 | $41.79 | $30.00 |
| 4 | Embankment (final)(DC)(type C2) (132-7010) | CY | 67 | $150.00 | $65.00 | $215.00 | $67.91 | $65.00 |
| 5 | Stone-MTRX-asphalt SMA-C sac-A PG76-22 (346-7001) | TON | 40,297 | $150.00 | $165.66 | $181.98 | $188.50 | $178.45 |
| 6 | Tack coat (346-7028) | GAL | 68,229 | $1.00 | $4.60 | $4.97 | $3.80 | $5.20 |
| 7 | Flexible pavement structure repair(8") (351-7007) | SY | 11,215 | $85.00 | $76.00 | $82.08 | $81.52 | $80.00 |
| 8 | Planing asphalt concrete pavement(0" to 3") (354-7033) | SY | 127,786 | $2.00 | $2.90 | $2.75 | $3.54 | $2.75 |
| 9 | Full-depth rep(BR appr slab)(9"-13") (361-7047) | CY | 45.50 | $1,000.00 | $3,900.00 | $2,000.00 | $1,619.38 | $1,650.00 |
| 10 | Full - depth repair CRCP (8") (361-7049) | SY | 5,500 | $250.00 | $198.00 | $217.80 | $206.86 | $230.00 |
| 11 | Cem stabil BKFL (400-7010) | CY | 5.50 | $250.00 | $400.00 | $450.00 | $417.75 | $350.00 |
| 12 | Flowable backfill (401-7001) | CY | 84.50 | $375.00 | $250.00 | $300.00 | $261.19 | $400.00 |
| 13 | Temporary special shoring (403-7001) | SF | 60 | $30.00 | $75.00 | $82.50 | $78.36 | $100.00 |
| 14 | Class C concrete (wingwalls) (420-7146) | CY | 1.50 | $3,000.00 | $5,000.00 | $5,500.00 | $5,223.81 | $3,000.00 |
| 15 | Concrete structure repair(clean & coat WTH epoxy) (429-7001) | SF | 69 | $150.00 | $119.00 | $165.00 | $172.39 | $175.00 |
| 16 | Concrete structure repair(rapid deck rep(PRT DPT) (429-7004) | SF | 146 | $100.00 | $86.00 | $170.00 | $177.61 | $65.00 |
| 17 | Concrete structure repair(rapid deck rep(full DPT)) (429-7006) | SF | 29 | $200.00 | $248.00 | $425.00 | $444.02 | $215.00 |
| 18 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 1,749 | $90.00 | $160.00 | $176.00 | $183.88 | $150.00 |
| 19 | Riprap (concrete)(4 in) (432-7001) | CY | 36 | $600.00 | $670.00 | $737.00 | $699.99 | $675.00 |
| 20 | Riprap (concrete)(5 in) (432-7002) | CY | 6.50 | $650.00 | $690.00 | $759.00 | $720.89 | $760.00 |
| 21 | Riprap (mow strip)(4 in) (432-7013) | CY | 15 | $700.00 | $700.00 | $770.00 | $731.33 | $600.00 |
| 22 | Riprap (stone protection)(12 in) (432-7041) | CY | 22 | $250.00 | $250.00 | $275.00 | $261.19 | $220.00 |
| 23 | Riprap (concrete)(8 in) (432-7056) | CY | 33 | $650.00 | $700.00 | $770.00 | $731.33 | $600.00 |
| 24 | Cleaning and sealing existing joints (438-7001) | LF | 264 | $20.00 | $45.00 | $49.50 | $28.73 | $55.00 |
| 25 | Cleaning and sealing existing joints (CL3) (438-7004) | LF | 189 | $30.00 | $20.00 | $22.00 | $22.98 | $18.00 |
| 26 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 6,363 | $25.00 | $25.00 | $27.50 | $28.73 | $23.00 |
| 27 | Cleaning existing joints (438-7008) | LF | 1,002 | $15.00 | $25.00 | $27.50 | $28.73 | $61.34 |
| 28 | Cleaning and sealing joints (foam) (438-7010) | LF | 957 | $45.00 | $72.00 | $79.20 | $83.58 | $59.38 |
| 29 | Spot clean & paint existing structure(special protection sys) (446-7019) | LS | 1 | $50,000 | $22,500 | $24,000 | $25,074 | $100,000 |
| 30 | Retrofit rail (type SSTR) (451-7024) | LF | 12,428 | $138.00 | $118.00 | $129.80 | $123.28 | $110.00 |
| 31 | Joint sealant (454-7010) | LF | 1 | $30.00 | $17.00 | $150.00 | $261.19 | $100.00 |
| 32 | Clean existing culverts (480-7001) | EACH | 2 | $3,000.00 | $2,000.00 | $10,000 | $5,000.00 | $42,000 |
| 33 | Mobilization (500-7001) | LS | 1 | $1,175,000 | $2,154,754 | $1,000,000 | $1,158,390 | $2,000,000 |
| 34 | Barricades, signs and traffic handling (502-7001) | MO | 15 | $25,000 | $32,997 | $56,000 | $68,014 | $70,000 |
| 35 | Portable changeable message sign (503-7002) | EACH | 4 | $20,000 | $9,652.56 | $25,000 | $9,794.65 | $25,000 |
| 36 | TMA (stationary) (505-7001) | DAY | 484 | $250.00 | $1.00 | $350.00 | $300.00 | $350.00 |
| 37 | TMA (mobile operation) (505-7003) | DAY | 100 | $300.00 | $1.00 | $350.00 | $100.00 | $350.00 |
| 38 | Temporary sediment control fence (install) (506-7039) | LF | 1,050 | $4.00 | $5.00 | $4.26 | $5.22 | $3.60 |
| 39 | Temporary sediment control fence (remove) (506-7041) | LF | 1,050 | $1.25 | $1.00 | $1.10 | $1.04 | $1.20 |
| 40 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 2,100 | $7.00 | $5.00 | $6.60 | $5.22 | $6.25 |
| 41 | Biodegradable erosion control logs (remove) (506-7046) | LF | 2,100 | $1.25 | $1.00 | $1.10 | $1.04 | $1.25 |
| 42 | PTB (furnish and install)(steel) (512-7072) | LF | 3,820 | $100.00 | $39.17 | $28.50 | $31.34 | $122.00 |
| 43 | PTB (move)(steel) (512-7074) | LF | 11,460 | $25.00 | $14.14 | $6.50 | $10.45 | $25.00 |
| 44 | PTB (remove)(steel) (512-7076) | LF | 3,820 | $25.00 | $1.17 | $10.00 | $10.45 | $5.00 |
| 45 | Permanent CTB (single slope) (type 1) (42 ) (514-7001) | LF | 1,204 | $120.00 | $88.00 | $96.80 | $79.40 | $90.00 |
| 46 | Permanent CTB (single slope) (type 3) (42 ) (514-7002) | LF | 356 | $250.00 | $250.00 | $275.00 | $84.63 | $285.00 |
| 47 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 78,258 | $0.25 | $0.21 | $0.28 | $0.22 | $0.32 |
| 48 | Metal W-beam guard fence (timber post) (540-7001) | LF | 50 | $75.00 | $65.00 | $28.05 | $25.86 | $25.50 |
| 49 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 2 | $2,000.00 | $2,069.00 | $1,870.00 | $1,880.57 | $1,700.00 |
| 50 | Downstream anchor terminal section (540-7015) | EACH | 3 | $1,000.00 | $1,645.00 | $1,485.00 | $1,253.71 | $1,350.00 |
| 51 | Metal beam guard fence (long span system) (540-7027) | EACH | 1 | $1,450.00 | $1,420.00 | $1,347.50 | $1,201.48 | $1,225.00 |
| 52 | Remove metal beam guard fence (542-7001) | LF | 1,665 | $2.75 | $2.75 | $2.75 | $3.13 | $2.50 |
| 53 | Remove terminal anchor section (542-7002) | EACH | 3 | $200.00 | $275.00 | $220.00 | $156.71 | $200.00 |
| 54 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 4 | $250.00 | $275.00 | $165.00 | $261.19 | $150.00 |
| 55 | Guardrail end treatment (install) (544-7001) | EACH | 1 | $3,000.00 | $3,355.00 | $3,657.50 | $3,082.05 | $3,325.00 |
| 56 | Guardrail end treatment (remove) (544-7003) | EACH | 1 | $250.00 | $275.00 | $220.00 | $261.19 | $200.00 |
| 57 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 6 | $2,000.00 | $1,155.00 | $2,750.00 | $1,290.28 | $1,500.00 |
| 58 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $1,250.00 | $775.00 | $1,100.00 | $861.93 | $1,200.00 |
| 59 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 2 | $8,500.00 | $7,500.00 | $9,900.00 | $7,261.10 | $9,500.00 |
| 60 | Install delineator assembly (D-SW)SZ 1(WFLX)GF2 (658-7001) | EACH | 9 | $20.00 | $25.00 | $35.00 | $26.12 | $25.00 |
| 61 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (BI) (658-7032) | EACH | 11 | $50.00 | $15.00 | $35.00 | $20.90 | $25.00 |
| 62 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 4,437 | $1.00 | $0.50 | $5.00 | $2.06 | $1.00 |
| 63 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 2,010 | $2.00 | $0.50 | $5.00 | $2.09 | $1.00 |
| 64 | Reflectorized pavement marking type I(W)(entr gore)(100MIL) (666-7069) | EACH | 11 | $800.00 | $1,100.00 | $1,485.00 | $1,149.24 | $1,350.00 |
| 65 | Reflectorized pavement marking type I(W)(exit gore)(100MIL) (666-7072) | EACH | 12 | $1,000.00 | $1,100.00 | $1,842.50 | $1,149.24 | $1,675.00 |
| 66 | Reflectorized pavement marking type III (W)(6")(solid) (666-7236) | LF | 51,364 | $0.50 | $0.62 | $0.66 | $0.65 | $0.60 |
| 67 | Reflectorized pavement marking type III (W)(6")(broken) (666-7237) | LF | 38,523 | $0.50 | $0.72 | $0.72 | $0.75 | $0.65 |
| 68 | Reflectorized pavement marking type III (W)(6")(DOT) (666-7238) | LF | 2,980 | $0.55 | $1.60 | $0.72 | $1.67 | $0.65 |
| 69 | Reflectorized pavement marking type III (W)(12")(solid) (666-7242) | LF | 2,005 | $0.70 | $4.25 | $1.65 | $4.44 | $1.50 |
| 70 | Reflectorized pavement marking type III (W)(12")(DOT) (666-7243) | LF | 900 | $0.75 | $2.00 | $1.32 | $2.09 | $1.20 |
| 71 | Reflectorized pavement marking type III (Y)(6")(solid) (666-7248) | LF | 51,364 | $0.50 | $0.62 | $0.66 | $0.65 | $0.60 |
| 72 | Pavement sler 6" (666-7347) | LF | 19,280 | $0.20 | $0.17 | $0.14 | $0.18 | $0.13 |
| 73 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 2,157 | $4.00 | $4.60 | $4.68 | $4.81 | $4.25 |
| 74 | Eliminating existing PM & markers (6") (677-7002) | LF | 19,280 | $1.00 | $0.52 | $0.69 | $0.54 | $0.63 |
| 75 | Eliminating existing PM & markers (entr gore) (677-7016) | EACH | 1 | $300.00 | $644.00 | $385.00 | $672.83 | $350.00 |
| 76 | Fiber reinforced polymer patching materials (721-7001) | LB | 6,000 | $10.00 | $6.65 | $7.32 | $6.95 | $7.50 |
| 77 | Driftwood removal (735-7060) | CY | 18.50 | $100.00 | $100.00 | $150.00 | $105.03 | $70.00 |
| 78 | Tree trimming / brush removal (752-7001) | MI | 0.80 | $2,000.00 | $64,000 | $11,500 | $10,448 | $72,000 |
| 79 | Repair (steel post W/base plate) (776-7002) | EACH | 16 | $2,500.00 | $600.00 | $585.00 | $626.86 | $690.00 |
| 80 | Concrete rail repair (in-kind) (778-7001) | LF | 40 | $500.00 | $820.00 | $250.00 | $856.70 | $450.00 |
| 81 | CNC crack repair (discrete)(gravity) (780-7001) | LF | 326 | $30.00 | $26.00 | $41.00 | $42.84 | $22.00 |
| 82 | CNC crack repair (discrete)(inject) (780-7002) | LF | 281 | $100.00 | $84.00 | $66.00 | $68.95 | $22.00 |
| 83 | Concrete CRCK repair(discrete)(rout and seal) (780-7003) | LF | 161 | $50.00 | $28.00 | $50.00 | $52.24 | $22.00 |
| 84 | CNC crack repair (discrete)(surface seal) (780-7004) | LF | 70 | $50.00 | $50.00 | $50.00 | $52.24 | $25.00 |
| 85 | CNC crack repair (flood)(gravity) (780-7005) | SF | 603 | $20.00 | $18.00 | $26.00 | $31.34 | $8.00 |
| 86 | Rep steel bridge member (beam) (784-7002) | EACH | 7 | $20,000 | $1,600.00 | $1,450.00 | $1,671.62 | $650.00 |
| 87 | Bridge joint repair (armor) (785-7004) | LF | 247 | $250.00 | $200.00 | $190.00 | $208.95 | $70.00 |
| 88 | Bridge joint repair (SEJ) (785-7005) | LF | 316 | $300.00 | $230.00 | $230.00 | $240.30 | $70.00 |
| 89 | Bridge joint replacement (armor) (785-7010) | LF | 40 | $550.00 | $860.00 | $860.00 | $898.50 | $295.00 |
| 90 | Bridge joint replacement (SEJ) (785-7011) | LF | 765 | $400.00 | $775.00 | $800.00 | $809.69 | $410.00 |
| 91 | Replacing elastomeric bearing pads (787-7001) | EACH | 34 | $3,500.00 | $6,300.00 | $6,300.00 | $6,582.00 | $3,000.00 |
| 92 | Cam PG76-22 sac-B (3000-7001) | TON | 17,041 | $165.00 | $188.08 | $202.88 | $202.50 | $175.00 |
| 93 | Continuous grinding-concrete pavement (3017-7001) | SY | 15,615 | $5.50 | $5.74 | $6.69 | $6.35 | $8.74 |
| 94 | Bent cap/abutment cap cleaning (7001-7002) | EACH | 7 | $10,000 | $1,600.00 | $1,600.00 | $1,671.62 | $850.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 2, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.