TxDOT contract A00196689 bid tabulation
Remove/Replace Bridge Rail, Various (DISTRICTWIDE to .). Let by Texas DOT on March 4, 2025, Webb, Laredo District. 6 bids received; low bid $3,111,940 by Delgado'S Contractors, LLC, +1.0% against the engineer's estimate of $3,082,512.
- Owner
- Texas DOT
- Letting
- 04 MAR 2025
- Pay items
- 48
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Delgado'S Contractors, LLC | $3,111,940 | Low | +1.0% |
| 2 | Icos Management, LLC | $3,147,250 | +1.0% | +2.0% |
| 3 | 3LW Civil LLC | $3,298,802 | +6.0% | +7.0% |
| 4 | Relmco, Inc. | $3,323,094 | +7.0% | +8.0% |
| 5 | STX Civil | $4,074,753 | +31% | +32% |
| 6 | Built Right Construction of Oklahoma, LLC | $5,423,560 | +74% | +76% |
Engineer's estimate: $3,082,512.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Delgado'S Contractors, LLC | 2. Icos Management, LLC | 3. 3LW Civil LLC | 4. Relmco, Inc. | 5. STX Civil | 6. Built Right Construction of Oklahoma, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (mowstrip) (104-7005) | LF | 3,020 | $15.00 | $6.00 | $15.00 | $17.24 | $25.00 | $22.00 | $50.00 |
| 2 | Embankment (final)(OC)(type A) (132-7001) | CY | 72 | $100.00 | $100.00 | $120.00 | $331.97 | $200.00 | $75.00 | $300.00 |
| 3 | Backfill (type B) (134-7002) | STA | 125 | $300.00 | $125.00 | $80.00 | $373.52 | $1,500.00 | $263.00 | $500.00 |
| 4 | Spec excavation work (backhoe) (158-7001) | HR | 28 | $125.00 | $125.00 | $500.00 | $78.31 | $100.00 | $196.00 | $200.00 |
| 5 | Riprap (concrete)(4 in) (432-7001) | CY | 72 | $500.00 | $625.00 | $800.00 | $699.74 | $525.00 | $714.00 | $1,700.00 |
| 6 | Riprap (mow strip)(4 in) (432-7013) | CY | 466 | $600.00 | $625.00 | $700.00 | $798.19 | $525.00 | $777.00 | $1,300.00 |
| 7 | Retrofit rail (type T402) (451-7012) | LF | 3,062 | $220.00 | $180.00 | $260.00 | $166.81 | $150.00 | $281.00 | $350.00 |
| 8 | Retrofit rail (type T631) (451-7020) | LF | 3,950 | $100.00 | $115.00 | $160.00 | $98.95 | $104.50 | $139.00 | $225.00 |
| 9 | Retrofit rail (add HSS) (451-7052) | LF | 170 | $100.00 | $125.00 | $500.00 | $159.77 | $187.00 | $139.00 | $300.00 |
| 10 | Clean existing culverts (480-7001) | EACH | 9 | $2,500.00 | $4,000.00 | $7,000.00 | $16,663 | $3,500.00 | $4,500.00 | $5,000.00 |
| 11 | Mobilization (500-7001) | LS | 1 | $227,076 | $155,000 | $47,000 | $311,944 | $300,000 | $336,000 | $500,000 |
| 12 | Barricades, signs and traffic handling (502-7001) | MO | 20 | $5,000.00 | $5,000.00 | $1.00 | $2,101.67 | $6,500.00 | $5,500.00 | $2,500.00 |
| 13 | Portable changeable message sign (503-7002) | EACH | 2 | $10,000 | $9,500.00 | $10,000 | $8,453.19 | $17,500 | $12,500 | $20,000 |
| 14 | TMA (stationary) (505-7001) | DAY | 388 | $150.00 | $300.00 | $1.00 | $183.50 | $250.00 | $260.00 | $325.00 |
| 15 | Rock filter dams (install) (type 3) (506-7003) | LF | 273 | $50.00 | $75.00 | $10.00 | $46.80 | $50.00 | $110.00 | $125.00 |
| 16 | Rock filter dams (remove) (506-7011) | LF | 273 | $15.00 | $7.00 | $5.00 | $21.60 | $25.00 | $25.00 | $35.00 |
| 17 | Construction exits (install) (type 1) (506-7020) | SY | 156 | $15.00 | $35.00 | $20.00 | $33.60 | $30.00 | $45.00 | $55.00 |
| 18 | Construction exits (remove) (506-7024) | SY | 156 | $10.00 | $7.00 | $5.00 | $18.00 | $15.00 | $20.00 | $25.00 |
| 19 | Backhoe work (erosion & sediment control) (506-7030) | HR | 4 | $100.00 | $150.00 | $600.00 | $97.88 | $100.00 | $116.00 | $200.00 |
| 20 | Temporary sediment control fence (install) (506-7039) | LF | 160 | $3.00 | $7.00 | $5.00 | $5.70 | $6.00 | $8.00 | $7.00 |
| 21 | Temporary sediment control fence (remove) (506-7041) | LF | 160 | $1.00 | $1.00 | $2.00 | $2.40 | $4.00 | $2.00 | $5.00 |
| 22 | One-way traffic control (flagger cont) (510-7001) | HR | 848 | $100.00 | $75.00 | $1.00 | $113.72 | $100.00 | $132.00 | $35.00 |
| 23 | One-way traffic control (port traffic signal) (510-7003) | MO | 6 | $5,000.00 | $6,000.00 | $10,000 | $4,200.00 | $5,500.00 | $7,630.00 | $6,000.00 |
| 24 | PTB (fur&inst)(SSCB or CSB)(type 1)or(steel) (512-7085) | LF | 1,170 | $60.00 | $90.00 | $90.00 | $38.26 | $60.00 | $75.00 | $105.00 |
| 25 | PTB (move)(SSCB or CSB)(type 1)or(steel) (512-7086) | LF | 5,670 | $15.00 | $12.00 | $25.00 | $8.62 | $30.00 | $25.00 | $25.00 |
| 26 | PTB (remove)(SSCB or CSB)(type 1)or(steel) (512-7088) | LF | 1,170 | $20.00 | $17.00 | $25.00 | $25.46 | $30.00 | $30.00 | $40.00 |
| 27 | Metal W-beam guard fence (timber post) (540-7001) | LF | 9,975 | $28.00 | $27.50 | $19.00 | $28.64 | $30.80 | $33.00 | $33.00 |
| 28 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 12 | $2,500.00 | $2,500.00 | $3,800.00 | $3,242.16 | $2,420.00 | $3,200.00 | $5,500.00 |
| 29 | Transition adjustment (540-7012) | EACH | 1 | $500.00 | $1,250.00 | $5,000.00 | $2,184.65 | $1,210.00 | $128.00 | $1,500.00 |
| 30 | Remove metal beam guard fence (542-7001) | LF | 7,625 | $3.00 | $2.50 | $2.00 | $9.18 | $2.75 | $4.00 | $5.00 |
| 31 | Remove terminal anchor section (542-7002) | EACH | 4 | $200.00 | $250.00 | $500.00 | $1,143.94 | $275.00 | $422.00 | $300.00 |
| 32 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 12 | $250.00 | $325.00 | $500.00 | $762.63 | $275.00 | $469.00 | $300.00 |
| 33 | RM metal beam guard fence trans (T101) (542-7005) | EACH | 33 | $200.00 | $250.00 | $500.00 | $1,109.28 | $275.00 | $426.00 | $300.00 |
| 34 | Guardrail end treatment (install) (544-7001) | EACH | 47 | $3,000.00 | $3,150.00 | $3,500.00 | $3,791.80 | $3,520.00 | $3,500.00 | $4,500.00 |
| 35 | Guardrail end treatment (remove) (544-7003) | EACH | 43 | $200.00 | $250.00 | $500.00 | $744.89 | $275.00 | $523.00 | $300.00 |
| 36 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 42 | $1,500.00 | $2,000.00 | $2,000.00 | $1,089.47 | $800.00 | $2,272.00 | $3,500.00 |
| 37 | Crash cushion attenuator (remove) (545-7004) | EACH | 6 | $1,000.00 | $2,000.00 | $2,000.00 | $1,162.63 | $600.00 | $1,136.00 | $1,500.00 |
| 38 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 6 | $15,000 | $9,000.00 | $10,000 | $8,417.94 | $9,000.00 | $11,135 | $13,000 |
| 39 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 267 | $50.00 | $40.00 | $40.00 | $60.41 | $40.70 | $45.00 | $65.00 |
| 40 | Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059) | EACH | 56 | $100.00 | $100.00 | $100.00 | $71.98 | $40.70 | $127.00 | $25.00 |
| 41 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 16,920 | $2.00 | $3.00 | $0.50 | $1.80 | $1.65 | $2.00 | $3.50 |
| 42 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 288 | $10.00 | $20.00 | $0.50 | $24.00 | $22.00 | $28.00 | $25.00 |
| 43 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 32,080 | $2.00 | $3.00 | $0.50 | $1.10 | $1.21 | $2.00 | $3.25 |
| 44 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 1,692 | $2.00 | $2.00 | $0.50 | $4.66 | $5.00 | $3.00 | $0.50 |
| 45 | Work zone pavement marking SHT terminal (tab)type Y (662-7113) | EACH | 3,208 | $2.00 | $2.00 | $0.50 | $4.63 | $5.00 | $3.00 | $0.50 |
| 46 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 8,020 | $1.00 | $3.00 | $0.50 | $3.00 | $3.30 | $4.00 | $3.25 |
| 47 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 32,080 | $1.50 | $3.00 | $0.50 | $1.28 | $1.41 | $2.00 | $3.25 |
| 48 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 802 | $8.00 | $11.00 | $10.00 | $20.00 | $22.00 | $28.00 | $20.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of March 4, 2025. Compiled by Mirage Metrics.