TxDOT contract A00197665 bid tabulation

Install/Upgrade Roadway Lighting, IH 14 (SS172 to Jasper Drive). Let by Texas DOT on June 4, 2025, Bell, Waco District. 11 bids received; low bid $2,645,698 by E-Z Bel Construction, LLC, -18% against the engineer's estimate of $3,229,406.

Owner
Texas DOT
Letting
04 JUN 2025
Pay items
50
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1E-Z Bel Construction, LLC$2,645,698Low-18%
2Florida Traffic Control Devices, Inc.$2,939,939+11%-9.0%
3The Levy Company, Inc.$2,969,977+12%-8.0%
4Highway Intelligent Traffic Solutions, Inc.$2,986,057+13%-8.0%
5Light It Up Electric$3,088,894+17%-4.0%
6WG Engineering & Construction, LLC$3,157,413+19%-2.0%
7Cross Plus Construction, LLC$3,258,074+23%+1.0%
8Sice, Inc.$3,268,658+24%+1.0%
9Mica Corporation$3,474,325+31%+8.0%
10Austin Traffic Signal Construction Co., Inc.$3,562,211+35%+10%
11Grey Sky Construction LLC$4,274,593+62%+32%
TxDOT contract A00197665: bids by rank

Engineer's estimate: $3,229,406.

Bid tabulation

LinePay itemUnitQuantityEstimate1. E-Z Bel Construction, LLC2. Florida Traffic Control Devices, Inc.3. The Levy Company, Inc.4. Highway Intelligent Traffic Solutions, Inc.5. Light It Up Electric6. WG Engineering & Construction, LLC
1Removing concrete (mowstrip) (104-7005)LF67$20.00$102.39$52.00$51.00$60.90$65.00$50.60
2Removing concrete (riprap) (104-7006)SY63$75.00$30.00$64.00$64.00$75.93$70.00$107.20
3Removing concrete (rail) (104-7036)LF330$100.00$22.00$50.00$82.00$97.58$85.00$64.50
4Drill seed (permanent_urban_clay) (164-7012)SY1,840$0.50$0.60$1.15$0.80$2.50$0.75$1.30
5Drill seed (temporary_warm_cool) (164-7015)SY1,840$0.50$0.60$1.15$0.80$2.50$0.75$1.30
6Vegetative watering (168-7001)TGL30$100.00$250.00$58.00$23.00$125.00$50.00$769.80
7Drilled shaft (high mast pole) (48 in) (416-7035)LF133$900.00$625.00$795.00$600.00$656.81$625.00$860.00
8Drilled shaft (high mast pole) (54 in) (416-7036)LF25$1,100.00$745.00$880.00$700.00$705.81$875.00$937.90
9Drilled shaft (high mast pole) (60 in) (416-7037)LF272$1,000.00$770.00$935.00$900.00$784.14$1,050.00$1,121.80
10Riprap (concrete)(4 in) (432-7001)CY7$1,300.00$2,000.00$1,735.00$1,000.00$1,199.26$1,200.00$1,827.00
11Riprap (mow strip)(4 in) (432-7013)CY42$800.00$755.76$925.00$990.00$1,176.59$765.00$998.60
12Rail (type SSTR) (450-7024)LF330$300.00$45.00$210.00$220.00$256.91$210.00$251.70
13Mobilization (500-7001)LS1$234,771$240,000$255,000$296,998$213,527$280,000$210,821
14Barricades, signs and traffic handling (502-7001)MO8$7,500.00$7,500.00$13,500$15,300$23,970$15,000$4,920.80
15Portable changeable message sign (503-7002)EACH2$15,000$1,000.00$14,460$6,900.00$8,437.50$12,000$141.90
16TMA (stationary) (505-7001)DAY161$270.00$310.00$395.00$57.00$272.34$250.00$274.10
17Temporary sediment control fence (install) (506-7039)LF1,850$6.00$3.50$4.00$5.00$3.73$4.10$5.00
18Temporary SDMT cont fence (inlet protection) (506-7040)LF150$20.00$4.50$5.80$5.50$13.26$5.00$8.50
19Temporary sediment control fence (remove) (506-7041)LF2,000$1.80$1.00$1.75$1.75$1.80$1.20$0.40
20Metal W-beam guard fence (steel post) (540-7002)LF775$35.00$27.08$38.00$27.50$34.61$38.75$44.30
21Downstream anchor terminal section (540-7015)EACH2$1,700.00$1,405.95$1,735.00$1,410.00$2,406.25$1,850.00$2,309.40
22Remove downstream anchor terminal (542-7003)EACH1$250.00$288.19$173.00$290.00$437.50$200.00$504.30
23Guardrail end treatment (install) (544-7001)EACH2$3,500.00$3,532.25$4,050.00$3,550.00$4,168.75$4,000.00$4,584.60
24Guardrail end treatment (remove) (544-7003)EACH1$400.00$404.38$232.00$410.00$437.50$250.00$886.80
25Crash cushion attenuator (remove) (545-7004)EACH3$1,250.00$810.44$1,155.00$1,220.00$981.25$1,200.00$1,432.40
26Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH2$12,000$9,917.54$8,100.00$9,920.00$9,343.75$8,200.00$9,008.40
27Crash cushion attenuator (install)(S)(W)(TL3) (545-7016)EACH1$12,000$1.00$17,350$10,730$14,031$17,650$18,913
28Remove RD IL asm (bridge mount) (610-7006)EACH1$1,000.00$560.00$570.10$290.00$654.81$725.00$964.70
29Remove RD IL asm (trans-base) (610-7009)EACH28$800.00$765.00$760.00$800.00$1,048.79$800.00$1,109.40
30Conduit (PVC) (schedule 40) (3") (618-7036)LF14,127$25.00$10.00$14.90$10.00$14.06$17.00$19.80
31Conduit (PVC) (schedule 80) (3") (bore) (618-7061)LF2,374$35.00$15.00$28.25$35.00$26.40$35.00$33.50
32Conduit (prepare) (618-7090)LF1,736$6.00$1.00$4.00$1.60$3.93$1.50$1.50
33Remove ground box (624-7013)EACH15$350.00$400.00$291.00$110.00$861.34$500.00$402.00
34Install ground box (W/secure lid) (624-7014)EACH46$2,500.00$1,600.00$2,025.00$2,500.00$2,314.53$2,500.00$2,445.80
35Retro ground box (W/secure lid) (624-7015)EACH38$1,200.00$1,000.00$2,025.00$1,600.00$936.19$1,600.00$1,609.00
36Remove electrical services (628-7002)EACH7$820.00$650.00$305.00$360.00$1,259.69$1,000.00$964.70
37Elc SRV type A 240/480 060(NS)SS(E)SP(U) (628-7049)EACH5$7,500.00$8,000.00$6,200.00$8,500.00$10,767$10,500$9,305.60
38Elc SRV type A 240/480 060(NS)SS(E)SF(U) (628-7352)EACH5$10,000$10,000$7,923.00$12,700$12,361$11,000$13,033
39Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018)EACH14$32.00$47.68$198.00$50.00$68.75$29.50$30.50
40Remove above-ground conduit (690-7144)LF218$15.00$10.00$15.25$6.50$15.96$3.00$11.10
41Remove conductor (690-7150)LF42,221$1.10$1.00$1.65$0.50$1.24$1.50$0.80
42Ground box (prepare) (6013-7006)EACH14$500.00$500.00$292.00$145.00$348.06$300.00$197.40
43Aluminum electrical cond (#4 XHHW) (6071-7001)LF8,946$2.60$1.65$1.80$1.25$2.14$1.75$2.50
44Aluminum electrical cond (#6 XHHW) (6071-7003)LF52,671$2.30$1.40$1.65$1.05$1.73$1.70$1.70
45LED HM(100 FT)(80MPH)(6FIXT)(type B) (6083-7001)EACH1$45,000$64,000$54,150$64,700$56,336$56,000$68,164
46LED HM(125 FT)(80MPH)(6FIXT)(type B) (6083-7002)EACH1$85,000$74,000$64,650$76,000$66,684$66,000$73,380
47LED HM(150 FT)(80MPH)(6FIXT)(type B) (6083-7003)EACH4$75,000$80,000$71,750$83,500$73,895$75,000$80,076
48LED HM(175 FT)(80MPH)(6FIXT)(type B) (6083-7004)EACH1$100,000$97,000$83,000$95,700$84,996$88,000$90,916
49LED HM(100 FT)(80MPH)(6FIXT)(type B)SHLD (6083-7005)EACH5$55,000$64,500$54,850$65,400$57,179$56,900$64,120
50LED HM(150 FT)(80MPH)(6FIXT)(type B)SHLD (6083-7006)EACH5$85,000$80,500$72,480$84,300$75,434$75,500$80,807
TxDOT contract A00197665: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of June 4, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way