TxDOT contract A00200728 bid tabulation
Bridge Replacement, COUNTY ROAD 241 (CR 238 (Sign CR 128W) at Paradise Creek to .). Let by Texas DOT on October 8, 2025, Wilbarger, Wichita Falls District. 5 bids received; low bid $1,424,111 by Skyline Bridge LLC, -7.6% against the engineer's estimate of $1,540,431.
- Owner
- Texas DOT
- Letting
- 08 OCT 2025
- Pay items
- 46
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Skyline Bridge LLC | $1,424,111 | Low | -8.0% |
| 2 | Altus Construction LLC | $1,525,501 | +7.0% | -1.0% |
| 3 | Hodges and Son Construction Company, Inc. | $1,547,216 | +9.0% | 0.0% |
| 4 | Earth Builders, L.P. | $1,693,517 | +19% | +10% |
| 5 | Coppell Construction Co., Inc. | $1,777,400 | +25% | +15% |
Engineer's estimate: $1,540,431.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Skyline Bridge LLC | 2. Altus Construction LLC | 3. Hodges and Son Construction Company, Inc. | 4. Earth Builders, L.P. | 5. Coppell Construction Co., Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 4 | $7,000.00 | $2,500.00 | $37,756 | $5,000.00 | $20,000 | $5,000.00 |
| 2 | Remove (2"-8") TRT/untrt base & asphalt pavement (105-7112) | CY | 165 | $50.00 | $80.00 | $13.96 | $30.00 | $20.00 | $58.00 |
| 3 | Excavation (roadway & channel) (110-7004) | CY | 870 | $35.00 | $16.00 | $48.88 | $30.00 | $30.00 | $38.00 |
| 4 | Embankment (final)(DC)(type B) (132-7004) | CY | 320 | $67.00 | $45.00 | $21.88 | $45.00 | $30.00 | $48.00 |
| 5 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 1,000 | $2.00 | $3.00 | $0.93 | $3.00 | $2.00 | $2.00 |
| 6 | Vegetative watering (168-7001) | TGL | 8.50 | $80.00 | $1.00 | $36.18 | $1.00 | $100.00 | $50.00 |
| 7 | Proof rolling (216-7001) | HR | 8 | $128.00 | $100.00 | $113.58 | $1.00 | $100.00 | $75.00 |
| 8 | FL BS (compacted in place)(type A GR 1-2) (6") (247-7044) | SY | 1,000 | $50.00 | $16.02 | $40.00 | $40.00 | $35.00 | |
| 9 | D-GR HMA type-B PG64-22 (341-7001) | TON | 424 | $200.00 | $300.00 | $322.74 | $280.00 | $275.00 | $260.00 |
| 10 | Tack coat (341-7082) | GAL | 39 | $10.00 | $11.00 | $2.48 | $5.00 | $25.00 | $2.00 |
| 11 | Cem stabil BKFL (400-7010) | CY | 106 | $250.00 | $300.00 | $232.74 | $300.00 | $300.00 | $325.00 |
| 12 | Temporary special shoring (403-7001) | SF | 1,500 | $30.00 | $20.00 | $60.10 | $25.00 | $10.00 | $65.00 |
| 13 | Drilled shaft (24 in) (416-7004) | LF | 210 | $250.00 | $177.44 | $225.00 | $450.00 | $275.00 | |
| 14 | Class C concrete (abutment) (420-7012) | CY | 20.40 | $1,200.00 | $1,186.29 | $1,800.00 | $2,000.00 | $1,500.00 | |
| 15 | Class C concrete (miscellaneous) (420-7067) | CY | 9 | $1,200.00 | $1,003.41 | $1,800.00 | $2,000.00 | $2,100.00 | |
| 16 | Reinforced concrete slab (422-7001) | SF | 1,300 | $31.00 | $31.84 | $35.00 | $40.00 | $40.00 | |
| 17 | Prestressed concrete slab beam (5SB15) (425-7019) | LF | 247.50 | $375.00 | $345.26 | $310.00 | $400.00 | $330.00 | |
| 18 | Riprap (mow strip)(4 in) (432-7013) | CY | 30.20 | $1,000.00 | $750.00 | $655.68 | $700.00 | $800.00 | $800.00 |
| 19 | Riprap (stone protection)(12 in) (432-7041) | CY | 302 | $236.00 | $160.00 | $175.03 | $210.00 | $150.00 | $240.00 |
| 20 | Rail (type T631LS) (450-7021) | LF | 124 | $75.00 | $115.48 | $70.00 | $150.00 | $59.00 | |
| 21 | Concrete box culvert (11 FT X 8 FT) (462-7043) | LF | 160 | $2,250.00 | $2,200.00 | $2,121.27 | $2,300.00 | $2,800.00 | $2,500.00 |
| 22 | RC pipe (CL III)(12 in) (464-7001) | LF | 60 | $100.00 | $93.10 | $120.00 | $100.00 | $150.00 | |
| 23 | Wingwall (PW - 2) (HW=10 FT) (466-7194) | EACH | 2 | $85,000 | $95,000 | $38,145 | $70,000 | $70,000 | $65,000 |
| 24 | Set (type II) (12 in) (RCP) (6: 1) (P) (467-7292) | EACH | 2 | $1,000.00 | $903.05 | $3,000.00 | $4,000.00 | $5,500.00 | |
| 25 | Removing structure (wingwall) (496-7005) | EACH | 4 | $2,100.00 | $2,500.00 | $2,327.44 | $4,000.00 | $2,500.00 | $6,000.00 |
| 26 | Removing structure (headwall) (496-7006) | EACH | 2 | $2,500.00 | $2,500.00 | $2,001.05 | $2,000.00 | $2,500.00 | $2,500.00 |
| 27 | Removing structure (box culvert) (496-7008) | LF | 130 | $150.00 | $100.00 | $93.10 | $435.00 | $50.00 | $500.00 |
| 28 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 1 | $15,000 | $27,320 | $55,000 | $25,000 | $40,000 | |
| 29 | Mobilization (500-7001) | LS | 1 | $134,357 | $100,000 | $151,788 | $130,000 | $180,000 | $160,000 |
| 30 | Barricades, signs and traffic handling (502-7001) | MO | 8 | $8,000.00 | $2,500.00 | $3,723.91 | $9,500.00 | $5,000.00 | $15,000 |
| 31 | Rock filter dams (install) (type 2) (506-7002) | LF | 160 | $55.00 | $45.00 | $49.86 | $1.00 | $50.00 | $50.00 |
| 32 | Rock filter dams (remove) (506-7011) | LF | 160 | $25.00 | $5.00 | $17.32 | $1.00 | $10.00 | $25.00 |
| 33 | Temporary sediment control fence (install) (506-7039) | LF | 1,200 | $3.85 | $4.00 | $4.45 | $1.00 | $5.00 | $7.00 |
| 34 | Temporary sediment control fence (remove) (506-7041) | LF | 1,200 | $1.36 | $1.75 | $1.11 | $1.00 | $1.00 | $1.00 |
| 35 | Driveways (base) (530-7015) | SY | 120 | $65.00 | $150.12 | $50.00 | $50.00 | $36.00 | |
| 36 | Metal W-beam guard fence (timber post) (540-7001) | LF | 50 | $30.00 | $32.00 | $27.65 | $28.00 | $100.00 | $30.00 |
| 37 | Metal W - beam guard fence (low fill culvert) (540-7018) | LF | 150 | $80.00 | $115.00 | $123.34 | $100.00 | $100.00 | $85.00 |
| 38 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $2,600.00 | $3,400.00 | $3,118.77 | $3,300.00 | $3,000.00 | $2,900.00 |
| 39 | Remove and install existing gate (550-7017) | EACH | 1 | $2,000.00 | $2,094.70 | $500.00 | $5,000.00 | $2,500.00 | |
| 40 | Wire fence (type C) (552-7003) | LF | 470 | $16.00 | $28.00 | $27.93 | $20.00 | $40.00 | $40.00 |
| 41 | Wire fence (water gap) (552-7010) | LF | 166 | $200.00 | $150.00 | $46.55 | $40.00 | $60.00 | $100.00 |
| 42 | Wire fence (remove) (552-7011) | LF | 636 | $4.00 | $5.00 | $10.15 | $8.00 | $2.00 | $5.00 |
| 43 | Remove SM RD SN sup&AM (644-7073) | EACH | 2 | $320.00 | $200.00 | $124.95 | $50.00 | $100.00 | $145.00 |
| 44 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 16 | $49.00 | $50.00 | $32.58 | $25.00 | $100.00 | $31.00 |
| 45 | Spot mowing (730-7021) | ACRE | 1 | $50.00 | $1.00 | $0.93 | $1.00 | $1,000.00 | $2,500.00 |
| 46 | Gen debris remove from under bridges (7020-7003) | CY | 20 | $200.00 | $100.00 | $27.93 | $125.00 | $50.00 | $125.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of October 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way