TxDOT contract A00203532 bid tabulation
Construct Ramps, US 175 (Malloy Bridge Rd to Kaufman County Line). Let by Texas DOT on April 8, 2026, Dallas, Dallas District. 4 bids received; low bid $3,975,784 by Austin Bridge & Road Services, LP, +3.4% against the engineer's estimate of $3,844,434.
- Owner
- Texas DOT
- Letting
- 08 APR 2026
- Pay items
- 91
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Austin Bridge & Road Services, LP | $3,975,784 | Low | +3.0% |
| 2 | Foutsco Paving Company, LLC | $4,019,100 | +1.0% | +5.0% |
| 3 | Texas Materials Group, Inc. | $4,214,086 | +6.0% | +10% |
| 4 | Ed Bell Construction Company | $4,459,695 | +12% | +16% |
Engineer's estimate: $3,844,434.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Austin Bridge & Road Services, LP | 2. Foutsco Paving Company, LLC | 3. Texas Materials Group, Inc. | 4. Ed Bell Construction Company |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 130 | $1,777.00 | $540.00 | $500.00 | $1.00 | $850.00 |
| 2 | Removing concrete (pavement) (104-7001) | SY | 2,751 | $15.00 | $12.32 | $24.00 | $18.00 | $21.00 |
| 3 | Remove (0"-8") TRT/untrt base & asphalt pavement (105-7048) | SY | 2,751 | $15.00 | $4.63 | $7.00 | $7.98 | $7.35 |
| 4 | Remove (8"-22") TRT/untrt base & asphalt pavement (105-7122) | SY | 3,180 | $24.00 | $12.21 | $18.00 | $11.98 | $8.40 |
| 5 | Excavation (roadway) (110-7001) | CY | 2,748 | $20.00 | $16.41 | $23.00 | $50.00 | $21.00 |
| 6 | Subgr widen (OC) (112-7001) | STA | 19.88 | $600.00 | $187.25 | $855.00 | $300.00 | $1,000.00 |
| 7 | Embankment (final)(DC)(type C) (132-7006) | CY | 773 | $18.00 | $4.74 | $16.00 | $100.00 | $63.00 |
| 8 | Backfill (type A or B) (134-7004) | STA | 181.64 | $250.00 | $175.75 | $175.00 | $400.00 | $300.00 |
| 9 | Road grader work (ord comp) (152-7001) | STA | 19.88 | $175.00 | $161.41 | $100.00 | $200.00 | $1,000.00 |
| 10 | Compost manuf topsoil (4") (161-7002) | SY | 12,007 | $3.00 | $1.63 | $2.00 | $0.96 | $1.50 |
| 11 | Block sodding (162-7002) | SY | 12,007 | $7.00 | $6.33 | $4.00 | $3.82 | $5.25 |
| 12 | Drill seed (temporary_warm_cool) (164-7015) | SY | 12,007 | $0.40 | $2.00 | $0.10 | $0.21 | $0.18 |
| 13 | Vegetative watering (168-7001) | TGL | 3,572 | $5.00 | $0.01 | $0.10 | $1.00 | $1.00 |
| 14 | FL BS (compacted in place)(type D GR 1-2) (12") (247-7125) | SY | 4,689 | $27.00 | $26.52 | $50.00 | $34.00 | $50.00 |
| 15 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 1,409 | $6.00 | $5.23 | $0.10 | $4.00 | $5.50 |
| 16 | SP mixes SP-C sac-B PG64-22 (344-7011) | TON | 6,874 | $115.00 | $180.35 | $170.00 | $155.00 | $156.00 |
| 17 | Tack coat (344-7077) | GAL | 5,868 | $5.00 | $4.20 | $0.10 | $4.00 | $4.20 |
| 18 | Flexible pavement structure repair(8") (351-7007) | SY | 8,946 | $90.00 | $75.79 | $80.00 | $90.00 | $80.00 |
| 19 | Planing asphalt concrete pavement(2") (354-7051) | SY | 50,974 | $3.00 | $2.22 | $0.75 | $1.98 | $2.00 |
| 20 | Cem stabil BKFL (400-7010) | CY | 1 | $1,000.00 | $1,000.00 | $1,200.00 | $850.00 | |
| 21 | Trench excavation protection (402-7001) | LF | 428 | $25.00 | $1.00 | $18.00 | $1.00 | $15.00 |
| 22 | Temporary special shoring (403-7001) | SF | 199.50 | $28.00 | $51.02 | $55.00 | $50.00 | $150.00 |
| 23 | Drilled shaft (24 in) (416-7004) | LF | 26 | $200.00 | $222.00 | $285.00 | $222.00 | $236.50 |
| 24 | Drilled shaft (36 in) (416-7006) | LF | 100 | $225.00 | $398.32 | $250.00 | $393.00 | $525.00 |
| 25 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 48 | $425.00 | $230.00 | $320.00 | $230.00 | $258.00 |
| 26 | Class K concrete (miscellaneous) (420-7148) | CY | 33.40 | $2,000.00 | $2,015.31 | $975.00 | $1,975.00 | $2,500.00 |
| 27 | Riprap (concrete)(CL B) (432-7005) | CY | 3 | $600.00 | $918.37 | $1,000.00 | $1,000.00 | $2,000.00 |
| 28 | Riprap (mow strip)(4 in) (432-7013) | CY | 12 | $600.00 | $800.00 | $855.00 | $2,000.00 | $1,000.00 |
| 29 | Concrete box culvert (3 FT X 2 FT) (462-7001) | LF | 4 | $1,250.00 | $1,200.00 | $1,250.00 | $900.00 | |
| 30 | Concrete box culvert (4 FT X 2 FT) (462-7003) | LF | 8 | $1,450.00 | $1,450.00 | $1,450.00 | $950.00 | |
| 31 | RC pipe (CL III)(30 in) (464-7007) | LF | 621 | $150.00 | $190.00 | $198.00 | $190.00 | $125.00 |
| 32 | Inl(CMP)(pazd-CZ)(FG)(4FTX4FT-4FTX4FT) (465-7165) | EACH | 2 | $9,500.00 | $6,300.00 | $7,200.00 | $6,300.00 | $15,000 |
| 33 | Inl(CMP)(pazd-CZ)(FG)(5FTX5FT-4FTX4FT) (465-7167) | EACH | 1 | $7,500.00 | $8,700.00 | $7,500.00 | $10,000 | |
| 34 | Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348) | EACH | 1 | $4,500.00 | $5,900.00 | $5,800.00 | $5,900.00 | $3,000.00 |
| 35 | Removing structure (inlet) (496-7002) | EACH | 2 | $1,000.00 | $1,000.00 | $2,000.00 | $1,000.00 | |
| 36 | Removing structure (headwall) (496-7006) | EACH | 3 | $1,830.00 | $1,800.00 | $1,500.00 | $1,800.00 | $1,000.00 |
| 37 | Removing structure (pipe) (496-7007) | LF | 527 | $10.00 | $10.00 | $30.00 | $10.00 | $25.00 |
| 38 | Removing structure (box culvert) (496-7008) | LF | 12 | $30.00 | $300.00 | $30.00 | $400.00 | |
| 39 | Mobilization (500-7001) | LS | 1 | $408,155 | $437,336 | $300,000 | $420,000 | $448,000 |
| 40 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $10,000 | $34,213 | $55,000 | $40,000 | $52,500 |
| 41 | Portable changeable message sign (503-7002) | EACH | 3 | $1,032.46 | $4,400.00 | $18,500 | $15,750 | |
| 42 | TMA (stationary) (505-7001) | DAY | 120 | $125.00 | $1.00 | $1.00 | $10.00 | $157.50 |
| 43 | TMA (mobile operation) (505-7003) | DAY | 5 | $300.00 | $1.50 | $1.00 | $100.00 | $1,575.00 |
| 44 | Rock filter dams (install) (type 1) (506-7001) | LF | 168 | $55.00 | $28.00 | $40.00 | $42.84 | $69.88 |
| 45 | Rock filter dams (remove) (506-7011) | LF | 168 | $12.00 | $11.00 | $5.00 | $10.00 | $37.63 |
| 46 | Construction exits (install) (type 1) (506-7020) | SY | 246 | $35.00 | $35.00 | $35.00 | $42.00 | $37.63 |
| 47 | Construction exits (remove) (506-7024) | SY | 246 | $15.00 | $9.00 | $10.00 | $9.00 | $18.81 |
| 48 | Temporary sediment control fence (install) (506-7039) | LF | 1,368 | $3.50 | $3.50 | $1.00 | $3.60 | $4.21 |
| 49 | Temporary sediment control fence (remove) (506-7041) | LF | 1,368 | $1.00 | $1.00 | $0.50 | $0.79 | $1.88 |
| 50 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 3,857 | $10.00 | $6.25 | $1.00 | $5.61 | $6.18 |
| 51 | Biodegradable erosion control logs (remove) (506-7046) | LF | 3,857 | $3.00 | $1.25 | $0.50 | $0.79 | $2.96 |
| 52 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 1,216 | $1.00 | $1.00 | $2.50 | $0.25 | $2.10 |
| 53 | Metal W-beam guard fence (steel post) (540-7002) | LF | 125 | $25.00 | $30.00 | $55.00 | $50.00 | $32.25 |
| 54 | Downstream anchor terminal section (540-7015) | EACH | 1 | $1,170.00 | $1,300.00 | $1,950.00 | $2,500.00 | $1,397.50 |
| 55 | Guardrail end treatment (install) (544-7001) | EACH | 1 | $3,200.00 | $3,000.00 | $3,500.00 | $3,000.00 | $3,225.00 |
| 56 | Remove RD IL asm (trans-base) (610-7009) | EACH | 10 | $800.00 | $672.00 | $785.00 | $672.00 | $913.75 |
| 57 | In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124) | EACH | 6 | $5,800.00 | $4,065.00 | $5,750.00 | $4,065.00 | $4,730.00 |
| 58 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 1,818 | $21.00 | $15.25 | $17.00 | $15.25 | $16.13 |
| 59 | Conduit (PVC) (schedule 40) (2") (bore) (618-7031) | LF | 330 | $35.00 | $36.05 | $48.00 | $36.05 | $35.48 |
| 60 | Electrical conductor (no.8) bare (620-7007) | LF | 2,148 | $3.00 | $2.40 | $2.00 | $2.40 | $2.15 |
| 61 | Electrical conductor (no.8) insulated (620-7008) | LF | 4,296 | $4.00 | $2.40 | $2.50 | $2.40 | $2.69 |
| 62 | Ground box type A (122311)W/apron (624-7002) | EACH | 5 | $2,000.00 | $1,840.00 | $2,000.00 | $1,840.00 | $1,505.00 |
| 63 | Remove ground box (624-7013) | EACH | 2 | $360.00 | $435.00 | $660.00 | $435.00 | $483.75 |
| 64 | Aluminum signs (type G) (636-7002) | SF | 204 | $42.00 | $32.75 | $30.00 | $32.75 | $32.25 |
| 65 | Aluminum signs (type O) (636-7003) | SF | 242.50 | $33.00 | $37.15 | $30.00 | $37.15 | $32.25 |
| 66 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 53 | $705.00 | $660.00 | $600.00 | $800.00 | $645.00 |
| 67 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 50 | $790.00 | $720.00 | $750.00 | $958.00 | $806.25 |
| 68 | Install small roadside sign support and assembly type 10BWG(2)SB(P-exal) (644-7020) | EACH | 3 | $850.00 | $1,500.00 | $1,900.00 | $2,473.00 | $2,042.50 |
| 69 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 6 | $1,000.00 | $890.00 | $960.00 | $1,160.00 | $1,032.00 |
| 70 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 1 | $1,200.00 | $940.00 | $1,200.00 | $1,456.00 | $1,290.00 |
| 71 | Install small roadside sign support and assembly TYS80(1)SA(U-BM) (644-7034) | EACH | 2 | $1,050.00 | $1,500.00 | $1,536.00 | $1,612.50 | |
| 72 | Install small roadside sign support and assembly TYS80(2)SA(P-exal) (644-7049) | EACH | 1 | $1,700.00 | $1,950.00 | $2,695.00 | $3,550.00 | $2,902.50 |
| 73 | In bridge MNT clearance sign assembly(type N) (644-7061) | EACH | 3 | $3,118.00 | $3,200.00 | $3,118.00 | $3,440.00 | |
| 74 | Install LRSS (struct steel) (647-7001) | LB | 1,351 | $7.00 | $7.30 | $10.00 | $7.30 | $10.75 |
| 75 | Remove lrsa (647-7003) | EACH | 3 | $880.00 | $888.00 | $1,150.00 | $888.00 | $1,236.25 |
| 76 | Install overhead sign support(40 FT cant)(span only) (650-7048) | EACH | 1 | $29,000 | $27,680 | $20,000 | $27,680 | $40,000 |
| 77 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 3 | $55.00 | $25.00 | $60.00 | $50.00 | $26.88 |
| 78 | Install object marker assembly (OM-2Z)(WFLX)GNDLL (658-7248) | EACH | 4 | $75.00 | $85.00 | $170.00 | $50.00 | $75.25 |
| 79 | Work zone pavement marking removing (W)8"(solid) (662-7072) | LF | 348 | $1.50 | $2.50 | $1.50 | $8.15 | $8.76 |
| 80 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 700 | $1.00 | $1.25 | $1.30 | $8.15 | $8.76 |
| 81 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 1,198 | $2.50 | $1.30 | $0.79 | $1.50 | $1.61 |
| 82 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 222 | $4.00 | $4.00 | $3.05 | $7.25 | $7.79 |
| 83 | Pavement sler 6" (666-7347) | LF | 494 | $2.00 | $0.18 | $1.00 | $1.08 | |
| 84 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 4,522 | $1.00 | $0.70 | $0.54 | $1.00 | $1.08 |
| 85 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 19,657 | $1.50 | $0.65 | $0.53 | $0.95 | $1.02 |
| 86 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 17,929 | $1.00 | $0.65 | $0.53 | $0.95 | $1.02 |
| 87 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 294 | $8.00 | $6.00 | $4.00 | $6.25 | $6.72 |
| 88 | Eliminating existing PM & markers (6") (677-7002) | LF | 298 | $0.58 | $0.89 | $5.00 | $5.38 | |
| 89 | Eliminating existing PM & markers (8") (677-7004) | LF | 376 | $1.15 | $1.00 | $6.00 | $6.45 | |
| 90 | Pavement surface preparation for marking (6") (678-7002) | LF | 494 | $2.00 | $0.25 | $2.00 | $2.15 | |
| 91 | Full - width mowing (730-7019) | CYC | 2 | $2,500.00 | $5,000.00 | $2,500.00 | $6,000.00 | $5,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 8, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.