TxDOT contract A00203671 bid tabulation
Bridge Maintenance, SH 29 (AT SAN GABRIEL RIVER to .). Let by Texas DOT on February 6, 2025, Williamson, Austin District. 10 bids received; low bid $279,317 by BK Field Operations LLC, -29% against the engineer's estimate of $394,699.
- Owner
- Texas DOT
- Letting
- 06 FEB 2025
- Pay items
- 25
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | BK Field Operations LLC | $279,317 | Low | -29% |
| 2 | Garret Shields Infrastructure | $442,714 | +58% | +12% |
| 3 | Taylor Contracting LLC | $458,686 | +64% | +16% |
| 4 | Restek, Inc. | $462,900 | +66% | +17% |
| 5 | Structural Integrity Group LLC | $469,565 | +68% | +19% |
| 6 | MB Western Industrial Contracting Co. | $482,806 | +73% | +22% |
| 7 | Macias Specialty Contracting LLC | $534,220 | +91% | +35% |
| 8 | Cekra Inc. | $591,575 | +112% | +50% |
| 9 | Built Right Construction of Oklahoma, LLC | $596,989 | +114% | +51% |
| 10 | Icos Management, LLC | $745,470 | +167% | +89% |
Engineer's estimate: $394,699.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. BK Field Operations LLC | 2. Garret Shields Infrastructure | 3. Taylor Contracting LLC | 4. Restek, Inc. | 5. Structural Integrity Group LLC | 6. MB Western Industrial Contracting Co. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 6 | $5,000.00 | $11,000 | $5,000.00 | $1,000.00 | $3,500.00 | $3,200.00 | $3,000.00 |
| 2 | Penetrating concrete surface treatment (428-7001) | SY | 1,200 | $30.00 | $15.00 | $20.00 | $16.00 | $12.00 | $19.50 | $21.00 |
| 3 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 200 | $400.00 | $150.00 | $200.00 | $225.00 | $255.00 | $190.00 | $255.00 |
| 4 | Concrete structure repair (standard) (429-7009) | SF | 10 | $500.00 | $190.00 | $200.00 | $2,000.00 | $110.00 | $450.00 | $385.00 |
| 5 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 212 | $62.50 | $50.00 | $50.00 | $75.00 | $40.00 | $43.75 | $69.00 |
| 6 | Clean and paint existing STR (ref no. 1) (446-7020) | EACH | 88 | $1,000.00 | $600.00 | $2,600.00 | $2,050.00 | $2,520.00 | $2,650.00 | $2,750.00 |
| 7 | Mobilization (500-7001) | LS | 1 | $37,500 | $20,000 | $30,000 | $45,000 | $50,000 | $40,000 | $35,000 |
| 8 | Barricades, signs and traffic handling (502-7001) | MO | 3 | $10,000 | $500.00 | $5,000.00 | $7,500.00 | $4,075.00 | $5,500.00 | $3,000.00 |
| 9 | Portable changeable message sign (503-7001) | DAY | 24 | $250.00 | $75.00 | $1.00 | $100.00 | $67.50 | $125.00 | $200.00 |
| 10 | TMA (stationary) (505-7001) | DAY | 15 | $325.00 | $1.00 | $300.00 | $2,500.00 | $230.00 | $400.00 | $300.00 |
| 11 | Rock filter dams (install) (type 1) (506-7001) | LF | 280 | $50.00 | $30.00 | $50.00 | $35.00 | $54.00 | $57.00 | $64.50 |
| 12 | Rock filter dams (remove) (506-7011) | LF | 280 | $25.00 | $10.00 | $10.00 | $5.00 | $30.00 | $13.00 | $14.30 |
| 13 | Temporary sediment control fence (install) (506-7039) | LF | 1,400 | $8.00 | $3.50 | $5.00 | $6.00 | $4.75 | $4.00 | $4.65 |
| 14 | Temporary sediment control fence (remove) (506-7041) | LF | 1,400 | $3.50 | $1.00 | $1.00 | $1.00 | $0.60 | $1.00 | $1.43 |
| 15 | Guardrail end treatment (install) (544-7001) | EACH | 2 | $4,250.00 | $2,800.00 | $3,500.00 | $3,500.00 | $4,525.00 | $4,600.00 | $5,005.00 |
| 16 | Guardrail end treatment (remove) (544-7003) | EACH | 2 | $400.00 | $1.00 | $500.00 | $1.00 | $735.00 | $785.00 | $858.00 |
| 17 | Install delineator assembly (D-SW)SZ 1(WFLX)SRF(BI) (658-7007) | EACH | 7 | $123.00 | $400.00 | $50.00 | $250.00 | $185.00 | $225.00 | $358.00 |
| 18 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 14 | $25.00 | $15.00 | $10.00 | $50.00 | $13.50 | $30.00 | $72.00 |
| 19 | Remove delin & object marker assms (658-7078) | EACH | 21 | $50.00 | $40.00 | $100.00 | $1.00 | $28.00 | $25.00 | $72.00 |
| 20 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 1,000 | $2.50 | $3.00 | $4.00 | $3.25 | $4.00 | $1.10 | $4.65 |
| 21 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 1,000 | $2.50 | $3.00 | $4.00 | $3.25 | $4.00 | $1.00 | $4.65 |
| 22 | Reflectorized profile pavement marking type I(Y)6"(broken)(100MIL) (666-7274) | LF | 250 | $2.50 | $4.00 | $3.00 | $4.25 | $5.25 | $1.00 | $6.10 |
| 23 | Eliminating existing PM & markers (4") (677-7001) | LF | 2,250 | $0.75 | $3.00 | $1.00 | $3.00 | $4.00 | $1.00 | $4.30 |
| 24 | Driftwood removal (735-7061) | LS | 1 | $5,000.00 | $32,000 | $10,000 | $15,000 | $11,200 | $15,000 | $5,000.00 |
| 25 | Tree trimming / brush removal(channels) (752-7003) | ACRE | 0.20 | $15,500 | $20,000 | $5,000.00 | $25,000 | $23,750 | $85,000 | $10,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 6, 2025. Compiled by Mirage Metrics.