TxDOT contract A00206051 bid tabulation
MOWING HIGHWAY RIGHT OF WAY, US0069 (Various roadways in to Cherokee County.). Let by Texas DOT on December 9, 2025, Cherokee, Tyler District. 8 bids received; low bid $667,923 by Servin Mowing Contractors, LLC, -6.7% against the engineer's estimate of $715,628.
- Owner
- Texas DOT
- Letting
- 09 DEC 2025
- Pay items
- 5
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Servin Mowing Contractors, LLC | $667,923 | Low | -7.0% |
| 2 | S G Company, LLC | $706,982 | +6.0% | -1.0% |
| 3 | UMD Construction | $794,926 | +19% | +11% |
| 4 | Cross Plus Construction, LLC | $834,269 | +25% | +17% |
| 5 | Cehand Services LLC | $975,302 | +46% | +36% |
| 6 | Jasco | $1,131,385 | +69% | +58% |
| 7 | T&L Cleaning Services LLC | $1,200,031 | +80% | +68% |
| 8 | Central North Construction, LLC | $1,276,870 | +91% | +78% |
Engineer's estimate: $715,628.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Servin Mowing Contractors, LLC | 2. S G Company, LLC | 3. UMD Construction | 4. Cross Plus Construction, LLC | 5. Cehand Services LLC | 6. Jasco |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mobilization (callout) (500-7002) | EACH | 4 | $2,000.00 | $28.00 | $1.00 | $15,500 | $1.00 | $100.00 | $1,000.00 |
| 2 | Strip mowing (730-7020) | ACRE | 100 | $22.00 | $27.99 | $30.00 | $80.00 | $23.00 | $100.00 | $50.00 |
| 3 | Spot mowing (730-7021) | ACRE | 50 | $30.00 | $28.00 | $1.00 | $100.00 | $1.00 | $100.00 | $50.00 |
| 4 | Full - width mowing (730-7022) | ACRE | 15,998.36 | $32.00 | $27.98 | $30.00 | $35.00 | $38.00 | $40.00 | $50.00 |
| 5 | Litter removal (734-7001) | ACRE | 15,998.36 | $12.00 | $13.50 | $14.00 | $10.00 | $14.00 | $20.00 | $20.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of December 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.