TxDOT contract A00206416 bid tabulation
Widen Road - Add Shoulders, FM 974 (3 Mi S of FM 2776 to FM 2776). Let by Texas DOT on July 1, 2026, Brazos, Bryan District. 8 bids received; low bid $3,771,592 by Big Creek Construction, LTD., -13% against the engineer's estimate of $4,315,846.
- Owner
- Texas DOT
- Letting
- 01 JUL 2026
- Pay items
- 77
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Big Creek Construction, LTD. | $3,771,592 | Low | -13% |
| 2 | Knife River Corporation - South | $4,272,476 | +13% | -1.0% |
| 3 | Larry Young Paving, Inc. | $4,285,538 | +14% | -1.0% |
| 4 | Brazos Paving, Inc. | $4,384,483 | +16% | +2.0% |
| 5 | Texas Materials Group, Inc. | $5,400,124 | +43% | +25% |
| 6 | Clark Construction of Texas, Inc. | $5,517,932 | +46% | +28% |
| 7 | STX Civil | $5,665,104 | +50% | +31% |
| 8 | A. L. Helmcamp, Inc. | $6,311,852 | +67% | +46% |
Engineer's estimate: $4,315,846.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Big Creek Construction, LTD. | 2. Knife River Corporation - South | 3. Larry Young Paving, Inc. | 4. Brazos Paving, Inc. | 5. Texas Materials Group, Inc. | 6. Clark Construction of Texas, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 159 | $1,216.08 | $750.00 | $370.00 | $380.00 | $690.00 | $545.00 | $496.99 |
| 2 | Removing concrete (mowstrip) (104-7003) | SY | 18 | $16.00 | $150.00 | $25.00 | $27.00 | $140.00 | $43.00 | $40.00 |
| 3 | Removing concrete (driveways) (104-7011) | SY | 87 | $31.33 | $50.00 | $17.00 | $18.00 | $21.00 | $54.00 | $50.00 |
| 4 | Remove (2"-8") TRT/untrt base & asphalt pavement (105-7053) | SY | 144 | $1.66 | $20.00 | $20.00 | $6.75 | $20.00 | $35.00 | $2.08 |
| 5 | Excavation (roadway) (110-7001) | CY | 11,856.40 | $15.00 | $15.00 | $12.00 | $18.00 | $16.50 | $37.00 | $29.39 |
| 6 | Embankment (final)(DC)(type C) (132-7006) | CY | 2,424.90 | $20.00 | $15.00 | $11.00 | $10.00 | $11.55 | $16.00 | $28.74 |
| 7 | Backfill (type A or B) (134-7004) | STA | 159 | $160.00 | $225.00 | $75.00 | $200.00 | $350.00 | $492.00 | $769.52 |
| 8 | Furn & place topsoil (4") (160-7002) | SY | 42,397 | $1.60 | $0.75 | $0.75 | $0.50 | $1.05 | $1.29 | $5.35 |
| 9 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 42,397 | $0.20 | $0.16 | $0.18 | $0.25 | $0.20 | $0.22 | $0.28 |
| 10 | Broadcast seed (temporary_warm) (164-7005) | SY | 21,195 | $0.19 | $0.14 | $0.15 | $0.25 | $0.20 | $0.16 | $0.22 |
| 11 | Broadcast seed (temporary_cool) (164-7006) | SY | 21,195 | $0.20 | $0.14 | $0.15 | $0.25 | $0.20 | $0.16 | $0.22 |
| 12 | Vegetative watering (168-7001) | TGL | 426 | $42.32 | $10.00 | $58.00 | $31.00 | $65.00 | $27.00 | $42.75 |
| 13 | FL BS (compacted in place)(type A GR 1-2) (10") (247-7090) | SY | 52,999 | $22.00 | $23.00 | $27.00 | $28.00 | $27.00 | $34.50 | $34.40 |
| 14 | Rework BS metal (type B)(8")(ord comp) (251-7027) | SY | 42,405 | $2.75 | $3.00 | $1.25 | $2.25 | $5.00 | $5.45 | $2.46 |
| 15 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 211 | $400.00 | $325.00 | $300.00 | $390.00 | $400.00 | $335.00 | $325.00 |
| 16 | Lime TRT (existing material)(10") (260-7008) | SY | 15,015 | $7.00 | $3.00 | $2.50 | $5.25 | $3.20 | $7.25 | $5.80 |
| 17 | Cement (275-7001) | TON | 853 | $220.00 | $225.00 | $199.00 | $210.00 | $251.00 | $216.00 | $225.00 |
| 18 | Cement TRT (existing material)(10") (275-7004) | SY | 60,066 | $3.00 | $2.50 | $1.25 | $2.50 | $3.00 | $1.80 | $2.61 |
| 19 | Asphalt (AC-20-5TR) (316-7007) | GAL | 41,335 | $3.60 | $3.75 | $4.45 | $5.00 | $4.50 | $4.50 | $6.87 |
| 20 | Asphalt (RC-250) (316-7016) | GAL | 15,018 | $5.75 | $5.00 | $4.75 | $5.25 | $4.00 | $5.00 | $7.48 |
| 21 | Aggregate (type-PB or PL, GR-4)(sac-A) (316-7241) | CY | 853 | $200.00 | $160.00 | $227.00 | $200.00 | $170.00 | $221.00 | $240.51 |
| 22 | Aggregate (type-B or L, GR-5) (316-7251) | CY | 406 | $150.00 | $105.00 | $180.00 | $170.00 | $146.00 | $145.00 | $223.52 |
| 23 | Cut & restoring pavement (400-7006) | SY | 17 | $83.42 | $200.00 | $60.00 | $100.00 | $144.00 | $245.00 | $285.80 |
| 24 | Cem stabil BKFL (400-7010) | CY | 41 | $297.01 | $150.00 | $125.00 | $120.00 | $102.00 | $200.00 | $185.00 |
| 25 | Trench excavation protection (402-7001) | LF | 43 | $9.30 | $25.00 | $50.00 | $24.00 | $2.00 | $13.00 | $12.00 |
| 26 | Riprap (mow strip)(4 in) (432-7013) | CY | 103 | $652.13 | $650.00 | $800.00 | $670.00 | $600.00 | $866.00 | $800.00 |
| 27 | Riprap (stone protection)(18 in) (432-7043) | CY | 4 | $229.12 | $350.00 | $330.00 | $300.00 | $444.00 | $270.00 | $250.00 |
| 28 | RC pipe (CL III)(18 in) (464-7003) | LF | 761 | $75.00 | $85.00 | $80.00 | $75.00 | $106.20 | $65.00 | $60.00 |
| 29 | RC pipe (CL III)(24 in) (464-7005) | LF | 143 | $150.00 | $125.00 | $95.00 | $89.00 | $124.00 | $135.00 | $125.00 |
| 30 | RC pipe (CL III)(36 in) (464-7009) | LF | 48 | $226.72 | $225.00 | $200.00 | $210.00 | $227.00 | $270.00 | $250.00 |
| 31 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 52 | $1,200.00 | $1,500.00 | $1,650.00 | $1,300.00 | $2,033.00 | $1,030.00 | $950.00 |
| 32 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 8 | $2,218.75 | $2,200.00 | $2,100.00 | $2,600.00 | $2,700.00 | $2,705.00 | $2,500.00 |
| 33 | Set (type II) (36 in) (RCP) (3: 1) (C) (467-7365) | EACH | 4 | $4,255.00 | $4,500.00 | $3,900.00 | $4,200.00 | $3,342.00 | $4,872.00 | $4,500.00 |
| 34 | Clean existing culverts (480-7001) | EACH | 2 | $3,619.24 | $3,000.00 | $5,000.00 | $2,500.00 | $4,504.00 | $1,625.00 | $1,500.00 |
| 35 | Removing structure (set) (496-7004) | EACH | 62 | $500.00 | $500.00 | $300.00 | $330.00 | $700.00 | $758.00 | $700.00 |
| 36 | Removing structure (pipe) (496-7007) | LF | 54 | $31.12 | $30.00 | $45.00 | $20.00 | $26.75 | $49.00 | $45.00 |
| 37 | Removing structure (pipe) (496-7037) | EACH | 32 | $1,072.50 | $500.00 | $585.00 | $770.00 | $850.00 | $1,300.00 | $1,200.00 |
| 38 | Mobilization (500-7001) | LS | 1 | $392,350 | $275,000 | $339,069 | $250,000 | $193,720 | $335,950 | $455,000 |
| 39 | Barricades, signs and traffic handling (502-7001) | MO | 15 | $4,000.00 | $3,000.00 | $13,000 | $8,000.00 | $2,472.50 | $950.00 | $5,191.00 |
| 40 | Portable changeable message sign (503-7002) | EACH | 2 | $5,166.67 | $10,000 | $5,000.00 | $5,700.00 | $20,525 | $9,500.00 | $25,000 |
| 41 | TMA (stationary) (505-7001) | DAY | 218 | $200.00 | $150.00 | $175.00 | $260.00 | $244.00 | $450.00 | $225.00 |
| 42 | TMA (mobile operation) (505-7003) | DAY | 15 | $283.95 | $500.00 | $500.00 | $750.00 | $566.00 | $450.00 | $300.00 |
| 43 | Rock filter dams (install) (type 2) (506-7002) | LF | 1,180 | $35.00 | $30.00 | $35.00 | $44.00 | $47.75 | $37.00 | $45.00 |
| 44 | Rock filter dams (remove) (506-7011) | LF | 1,180 | $10.00 | $7.00 | $10.00 | $13.00 | $21.50 | $10.00 | $20.00 |
| 45 | Temporary sediment control fence (install) (506-7039) | LF | 2,660 | $4.00 | $4.00 | $3.50 | $4.50 | $4.75 | $3.60 | $3.50 |
| 46 | Temporary sediment control fence (remove) (506-7041) | LF | 2,660 | $2.79 | $1.00 | $1.00 | $1.25 | $1.20 | $1.00 | $1.00 |
| 47 | Driveways (concrete) (530-7006) | SY | 87 | $150.00 | $150.00 | $300.00 | $110.00 | $98.00 | $238.00 | $220.00 |
| 48 | Driveways (ACP) (530-7010) | SY | 490 | $35.00 | $45.00 | $85.00 | $68.00 | $51.50 | $100.00 | $46.88 |
| 49 | Driveways (surface treat) (530-7016) | SY | 2,279 | $30.00 | $25.00 | $125.00 | $41.00 | $29.25 | $102.00 | $44.35 |
| 50 | Turnouts (surface treat) (530-7019) | SY | 502 | $73.65 | $45.00 | $56.00 | $29.00 | $34.20 | $58.00 | $35.95 |
| 51 | Metal W-beam guard fence (timber post) (540-7001) | LF | 1,350 | $24.09 | $30.00 | $23.00 | $29.00 | $33.50 | $25.00 | $28.35 |
| 52 | Remove metal beam guard fence (542-7001) | LF | 248 | $2.93 | $5.00 | $5.00 | $6.25 | $6.00 | $5.25 | $3.15 |
| 53 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $3,331.43 | $3,250.00 | $3,250.00 | $4,100.00 | $3,629.00 | $3,515.00 | $3,097.50 |
| 54 | Guardrail end treatment (remove) (544-7003) | EACH | 2 | $243.57 | $500.00 | $500.00 | $630.00 | $300.00 | $540.00 | $262.50 |
| 55 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 29 | $500.00 | $320.00 | $315.00 | $400.00 | $602.75 | $341.00 | $235.00 |
| 56 | Mailbox install-D (TWW-post) type 4 (560-7009) | EACH | 5 | $309.93 | $370.00 | $365.00 | $460.00 | $713.00 | $395.00 | $255.00 |
| 57 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 71 | $550.00 | $550.00 | $515.00 | $650.00 | $804.00 | $557.00 | $650.00 |
| 58 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 2 | $957.80 | $950.00 | $950.00 | $1,200.00 | $1,342.00 | $1,029.00 | $790.00 |
| 59 | Remove SM RD SN sup&AM (644-7073) | EACH | 73 | $129.06 | $110.00 | $110.00 | $140.00 | $155.00 | $119.00 | $100.00 |
| 60 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 16 | $37.33 | $35.00 | $32.00 | $40.00 | $18.00 | $35.00 | $20.00 |
| 61 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 12 | $98.48 | $90.00 | $85.00 | $110.00 | $18.00 | $92.00 | $56.00 |
| 62 | Remove delin & object marker assms (658-7078) | EACH | 12 | $24.50 | $25.00 | $20.00 | $25.00 | $6.00 | $22.00 | $15.00 |
| 63 | Install OM SM RD sign (1-OM-PW)R (658-7318) | EACH | 4 | $105.00 | $25.00 | $25.00 | $32.00 | $85.00 | $27.00 | $11.00 |
| 64 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 31,796 | $0.27 | $0.20 | $0.17 | $0.25 | $0.50 | $0.25 | $0.25 |
| 65 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 31,796 | $0.33 | $0.35 | $0.35 | $0.50 | $0.50 | $0.25 | $0.25 |
| 66 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 4,769 | $2.92 | $1.50 | $1.10 | $0.50 | $0.70 | $1.08 | $2.25 |
| 67 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 52 | $6.00 | $20.00 | $20.00 | $28.00 | $9.50 | $7.85 | $8.50 |
| 68 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 31,436 | $0.50 | $0.45 | $0.45 | $0.75 | $0.50 | $0.35 | $0.25 |
| 69 | Reflectorized pavement marking type II (W) 24" (solid) (666-7184) | LF | 52 | $4.75 | $8.00 | $8.00 | $11.00 | $6.00 | $6.75 | $4.00 |
| 70 | Reflectorized pavement marking type II (Y) 6" (broken) (666-7211) | LF | 1,679 | $0.50 | $0.45 | $0.45 | $0.75 | $0.50 | $0.40 | $0.25 |
| 71 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 19,841 | $0.58 | $0.45 | $0.45 | $0.75 | $0.50 | $0.35 | $0.25 |
| 72 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 31,436 | $0.98 | $0.96 | $1.00 | $1.25 | $0.80 | $0.65 | $0.75 |
| 73 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 1,679 | $1.28 | $1.00 | $1.00 | $1.50 | $0.80 | $0.68 | $0.75 |
| 74 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 19,841 | $1.01 | $1.00 | $1.00 | $1.50 | $0.80 | $0.65 | $0.75 |
| 75 | PRFB rumble strip (BLK)(1')(centerline) (668-7002) | LF | 15,898 | $2.64 | $0.10 | $0.10 | $0.25 | $1.10 | $4.00 | $1.25 |
| 76 | PRFB rumble strip (BLK)(1')(edgeline) (668-7137) | LF | 31,436 | $3.50 | $0.10 | $0.10 | $0.25 | $1.10 | $3.45 | $1.25 |
| 77 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 363 | $5.92 | $8.00 | $8.00 | $11.00 | $7.15 | $6.75 | $5.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 1, 2026. Compiled by Mirage Metrics.