TxDOT contract A00207748 bid tabulation

METAL BEAM GUARD FENCE REPAIR, IH0035W (Various Locations In to Johnson County). Let by Texas DOT on June 5, 2025, Johnson, Fort Worth District. 8 bids received; low bid $865,191 by T&L Cleaning Services LLC, -22% against the engineer's estimate of $1,113,881.

Owner
Texas DOT
Letting
05 JUN 2025
Pay items
33
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1T&L Cleaning Services LLC$865,191Low-22%
2Short-Line Corporation$868,7260.0%-22%
3BK Field Operations LLC$906,836+5.0%-19%
4Ross Sa Enterprise LLC$1,023,032+18%-8.0%
5Above All Contracting LLC$1,280,670+48%+15%
6Marcom'S Mowing Service, LLC$1,636,570+89%+47%
7Gratiot Construction, LTD.$1,578,725+82%+42%
8Vann/Elli, Inc.$1,976,750+128%+77%
TxDOT contract A00207748: bids by rank

Engineer's estimate: $1,113,881.

Bid tabulation

LinePay itemUnitQuantityEstimate1. T&L Cleaning Services LLC2. Short-Line Corporation3. BK Field Operations LLC4. Ross Sa Enterprise LLC5. Above All Contracting LLC6. Marcom'S Mowing Service, LLC
1Mobilization (callout) (500-7002)EACH45$1.00$1.00$1.00$1.00$1.00$1.00$1.00
2Mobilization (emergency) (500-7033)EACH1$1.00$1.00$1.00$1.00$1,000.00$1,000.00$4,000.00
3TMA (stationary) (505-7001)DAY100$250.00$1.00$1.00$1.00$1,500.00$1.00$1.00
4Metal W-beam guard fence (timber post) (540-7001)LF2,700$47.00$22.00$1.00$28.00$30.00$32.00$32.00
5Metal beam guard fence trans (thrie-beam) (540-7005)EACH8$1,500.00$1,500.00$2,000.00$1,850.00$1,500.00$2,500.00$1,950.00
6Downstream anchor terminal section (540-7015)EACH12$1,000.00$1,250.00$1,500.00$800.00$850.00$1,500.00$950.00
7Remove metal beam guard fence (542-7001)LF1,300$5.00$0.01$35.00$1.00$5.00$5.00$3.00
8Remove downstream anchor terminal (542-7003)EACH3$340.00$100.00$500.00$1,000.00$1,000.00$500.00$250.00
9Guardrail end treatment (install) (544-7001)EACH2$2,500.00$1,000.00$3,000.00$1,000.00$2,500.00$4,000.00$4,000.00
10Guardrail end treatment (remove) (544-7003)EACH2$300.00$500.00$100.00$1,000.00$1.00$500.00$500.00
11Replace rail element (W-beam) (770-7001)LF7,000$20.00$18.00$25.00$8.00$40.00$25.00$32.00
12Replace rail element (thrie-beam) (770-7002)LF50$112.00$20.00$75.00$40.00$80.00$60.00$45.00
13Repl rail elmnt(thrie-BM trans to W-BM) (770-7003)EACH25$45.00$20.00$75.00$40.00$1.00$100.00$450.00
14Replace timber post W/O concrete FND (770-7006)EACH300$39.00$1.00$75.00$200.00$400.00$50.00$30.00
15Replace steel post W/O concrete FND (770-7007)EACH300$39.00$30.00$1.00$1.00$1.00$100.00$60.00
16Replace timber post W/ concrete FND (770-7008)EACH10$15.00$50.00$100.00$300.00$350.00$50.00$80.00
17Replace steel post W/ concrete FND (770-7009)EACH10$15.00$50.00$50.00$1.00$1.00$100.00$100.00
18Realign posts (770-7010)EACH20$25.00$1.00$75.00$100.00$50.00$30.00$100.00
19Rem obsolete get & repl W/ SGT (770-7013)EACH125$3,400.00$2,500.00$2,600.00$2,200.00$500.00$3,500.00$3,920.00
20Repl single gdrail terminal impact head (770-7015)EACH8$980.00$1,250.00$1,000.00$1,300.00$1,000.00$800.00$900.00
21Replace single gdrail terminal rail (770-7016)LF300$27.00$100.00$25.00$20.00$40.00$35.00$45.00
22Replace single gdrail terminal post (770-7017)EACH30$138.00$200.00$50.00$200.00$150.00$120.00$200.00
23Replace blockout (770-7018)EACH275$37.00$10.00$5.00$6.00$50.00$15.00$15.00
24Reset SGT impact head (770-7020)EACH20$200.00$10.00$1.00$10.00$100.00$100.00$200.00
25Repair rail element (curved rail) (770-7027)LF450$100.00$25.00$25.00$28.00$20.00$50.00$45.00
26Replace posts (TL-4)(gibraltar) (771-7005)EACH700$124.00$150.00$300.00$486.00$150.00$220.00$280.00
27Replace posts (TL-4)(trinity) (771-7007)EACH700$124.00$200.00$1.00$1.00$1.00$220.00$340.00
28Cable splice / turnbuckle (TL-4) (771-7010)EACH3$500.00$100.00$100.00$300.00$500.00$300.00$500.00
29Repair concrete foundation (TL-4) (771-7012)EACH2$30.00$50.00$100.00$500.00$500.00$1,000.00$500.00
30Repair or replace cable barrier terminal sec(TL-4) (771-7014)EACH35$715.00$500.00$100.00$500.00$1,000.00$2,500.00$1,500.00
31Replace cable (TL-4) (771-7016)LF200$4.00$0.01$5.00$0.10$10.00$10.00$5.00
32Check / RE-tension cable (TL-4) (771-7018)EACH110$115.00$1.00$1.00$1.00$150.00$50.00$200.00
33Replace post hardware (TL-4) (771-7020)EACH1,800$20.00$1.00$1.00$1.00$40.00$10.00$100.00
TxDOT contract A00207748: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of June 5, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy